Bombay High Court Addresses Section 11 Application for Appointment of Arbitrator; Validity of 20% Claim Cap Clause Under Scrutiny. The Court Examines Whether a Contractual Condition Limiting Arbitration to Claims Not Exceeding 20% of Contract Value Is Arbitrary and Discriminatory.

High Court: Bombay High Court Bench: BOMBAY
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from a contract dated 7 May 2018 between a contractor and the Central Railways for the preparation of design and structural drawings for bridges in the Manmad-Jalgaon 3rd line project. The contract value was Rs.84,52,157.61. After the contract was terminated on 23 December 2021 and the contractor was debarred, the contractor estimated its claims at Rs.3 crores and sought appointment of an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996. The contract contained an arbitration clause (Clause 39 read with Clauses 63 and 64 of the General Conditions of Contract) which allowed arbitration only for claims not exceeding 20% of the contract value. The Railways opposed the application on the ground that the claim exceeded the monetary cap. The contractor argued that the cap was arbitrary and discriminatory because no similar restriction applied to the Railways’ counterclaims, thereby creating unequal bargaining power. Reliance was placed on precedents including ICOMM Tele Limited (2019) 4 SCC 401 and Lombard Engineering Limited (2024) 4 SCC 341 to contend that such unfair conditions violated Article 14 of the Constitution and could be invalidated. It was also argued that if the cap was held invalid, the arbitration agreement could be severed and the valid part enforced, as per Shin Satellite (2006) 2 SCC 628. The Railways countered that the cap was a contractual term intended to prevent inflated claims and that the contractor could pursue claims above 20% in a civil suit. It cited Railtech Infraven Pvt. Ltd. (2014 SCC Online Bom 1662) and other decisions upholding similar monetary limits. The court heard rival contentions and reserved judgment. The extracted portion of the judgment ends with the matter being taken up for consideration, and the final decision is not contained in the provided text.

Headnote

A) Arbitration Law - Appointment of Arbitrator - Section 11, Arbitration and Conciliation Act, 1996 - Restrictive Arbitration Clause - The contract contained Clause 39 read with Clauses 63 and 64 of the General Conditions of Contract (GCC), which limited arbitrable claims to not more than 20% of the contract value. The Applicant’s estimated claim of Rs. 3 crores far exceeded the cap, and the Respondent-Railways opposed the appointment of an arbitrator on this ground. The Court considered whether such a restrictive condition defeated the arbitration agreement and whether it should be severed. (Paras 1-8)

B) Arbitration Law - Validity of Restrictive Condition - Article 14, Constitution of India - Discriminatory Bargain - The Applicant argued that the 20% cap was arbitrary and discriminatory because no similar cap applied to counterclaims by the Railways, creating an unequal bargaining position. Reliance was placed on ICOMM Tele Limited v. Punjab State Water Supply and Sewerage Board (2019) 4 SCC 401 and Lombard Engineering Limited v. Uttarakhand Jal Vidyut Nigam Limited (2024) 4 SCC 341 to contend that such unfair conditions could be invalidated. The Court examined whether the condition violated the principle of equality. (Paras 3-5)

C) Arbitration Law - Severability of Arbitration Clause - Section 11, Arbitration and Conciliation Act, 1996 - Principle of Severability - The Applicant contended that if the 20% cap was held invalid, the remaining part of the arbitration agreement should be enforced, relying on Shin Satellite Public Company Limited v. Jain Studios Limited (2006) 2 SCC 628. The Court considered whether the valid parts could be severed from the invalid condition. (Para 5)

D) Arbitration Law - Scope of Section 11 Jurisdiction - Section 11, Arbitration and Conciliation Act, 1996 - Court’s Power to Examine Validity - Relying on Lombard Engineering Limited v. Uttarakhand Jal Vidyut Nigam Limited (2024) 4 SCC 341, the Applicant submitted that the court under Section 11 could decide on the validity or reasonableness of the arbitration clause. The Court examined the extent of its power at the appointment stage. (Para 5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitration clause imposing a restriction that only claims up to 20% of the contract value are arbitrable is valid and enforceable, and whether the court should appoint an arbitrator despite the claim exceeding that cap.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • arbitration clause with unfair bargaining strength can be invalidated
  • principle of equality applies at appointment stage
  • severability of contract
  • court can declare arbitrary conditions invalid under Article 14
  • monetary restriction for arbitration may be valid if reasonable
  • no similar cap on counterclaims renders clause discriminatory
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (BOM) (01) 138

Commercial Arbitration Application No. 688 of 2025

2026-01-28

Sandeep V. Marne, J.

Mr. Shardul Singh with Mr. Smeet Savla & Ms. Priyal Gandhi i/b M/s. SHS Chambers, for Applicant; Mr. Narayan Bubna with Ms. Pooja Malik, for Respondent

M/s. Sowil Limited

Deputy Chief Engineer (Construction) Bhusawal

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial arbitration application under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator.

Remedy Sought

The Applicant sought appointment of an arbitrator to adjudicate disputes arising from a terminated contract for preparation of design and structural drawings for railway bridges.

Filing Reason

The Applicant's contract was terminated and it wished to claim approximately Rs. 3 crores, but the arbitration clause limited arbitrable claims to 20% of the contract value, prompting a challenge to the validity of that restriction.

Previous Decisions

The Applicant had filed Writ Petition No. 2887/2023 challenging the termination, which was disposed of on 11 June 2025, granting liberty to file an application under Section 11 of the Arbitration Act.

Issues

Whether the arbitration clause imposing a restriction that only claims up to 20% of the contract value are arbitrable is valid and enforceable. Whether the condition is arbitrary and discriminatory as it does not equally apply to the Respondent's counterclaims. Whether the restrictive condition can be severed from the arbitration agreement, allowing the remaining part to be enforced.

Submissions/Arguments

Applicant argued that the 20% cap was arbitrary and discriminatory because no similar cap existed for the Railways' counterclaims, violating Article 14 of the Constitution. Applicant contended that the restriction was an unfair bargain and should be invalidated while preserving the valid portion of the arbitration clause, relying on precedents such as ICOMM Tele Limited (2019) 4 SCC 401 and Shin Satellite (2006) 2 SCC 628. Applicant submitted that the court under Section 11 could determine the validity of the arbitration clause and appoint an arbitrator, leaving the issue of jurisdiction (financial cap) to the arbitrator, citing Jai Salasar Balaji Construction Company (Raj HC) and Lombard Engineering (2024) 4 SCC 341. Respondent argued that the parties had expressly agreed to arbitrate only claims below 20% of the contract value, and that claims exceeding that limit could be pursued in a civil suit. Respondent relied on Railtech Infraven Pvt. Ltd. (2014 SCC Online Bom 1662) and other decisions to support the validity of the monetary cap, asserting that such clauses were designed to prevent inflated claims by contractors.

Judgment Excerpts

The relevant clause in the contract provides for resolution of disputes by arbitration only to the extent of 20% of the value of the contract. He would therefore submit that unreasonable condition is put in Clause 39 of the contract that provisions of Clauses 63 and 64 of the GCC are applicable only for settlement of claims of disputes between the parties for value less than or equal to 20% of the value of the contract. That there is no cap for the Respondent-Railways to have its claims/counterclaims decided through arbitration and the maximum cap is arbitrarily and selectively applied to the Applicant. He submits that the Apex Court has recognized the principle in Shin Satellite Public Company Limited (supra) that if the contract is in severed parts, some of which are legal and unenforceable, lawful parts can be enforced provided they are severable.

Procedural History

Tender notice issued on 10 November 2017. Letter of Acceptance issued on 12 February 2018 with contract value Rs.84,52,157.61. Contract dated 7 May 2018. Contract terminated on 23 December 2021. Applicant filed Writ Petition No. 2887/2023, disposed of on 11 June 2025 granting liberty to file Section 11 application. Present Commercial Arbitration Application No. 688 of 2025 filed thereafter.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11
  • Constitution of India: Article 14
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Reverses High Court Quashing of Criminal Proceedings Against Public Servant in Forgery Case Due to Lack of Sanction Requirement. The Court Held That Sanction Under Section 197 of the Code of Criminal Procedure, 1973 Is Not Necessary Whe...
Related Judgement
High Court Bombay High Court Partly Allows MIDC Appeal in Land Acquisition Compensation Case — Reduces Enhanced Rate from Rs.1,25,000 to Rs.1,00,000 per Hectare. Court Relies on Comparable Sale Instances and Potential Value of Land Under Maharashtra Industria...