Bombay High Court Considers Whether Minutes of Meeting Converted Force Majeure Clause into Assured Return Mechanism, Interpreting Clauses 3.4.19 and 3.7.2 of Construction Agreement. Appeal Challenges Arbitral Interpretation That State Must Compensate for Any Toll Collection Drop Exceeding 20%.

High Court: Bombay High Court
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The appeal under Section 37 of the Arbitration and Conciliation Act, 1996 arose from a dispute concerning a build-operate-transfer (BOT) contract for construction of a two-lane bridge across Dharamtar Creek in Maharashtra. The State of Maharashtra had awarded the contract to Patwardhan Infrastructure Pvt. Ltd. (successor to the original bidder Ameya Developers) for a concession period of 13 years, 7 months, and 35 days. After submission of the bid, Ameya raised concerns about a proposed new bridge (Rewas-Karanja) that could divert traffic and adversely impact toll collections. Two letters dated July 2, 1999 led to a meeting on August 18, 1999, where the parties discussed Clauses 3.4.19 (force majeure) and 3.7.2 of the draft agreement. The minutes of that meeting recorded that while the new bridge's viability was unestablished and its effect unpredictable, a decision on compensation for traffic variation would be taken when the new bridge was completed and opened to traffic, based on actual traffic variation. Subsequently, disputes arose and resulted in multiple arbitration proceedings. The arbitral tribunal in the impugned award dated November 7, 2012 interpreted the minutes and Clause 3.4.19 to mean that the State had undertaken to compensate the concessionaire for any shortfall in toll collection exceeding 20% in any period. The State challenged the award under Section 34 of the Act, but the High Court dismissed the challenge on September 24, 2014. The State then filed the present appeal under Section 37, contending that the tribunal's construction of the contract was perverse. The High Court heard detailed arguments from both sides; the appeal centered on whether the force majeure clause had been fundamentally altered by the minutes of meeting. The judgment, however, was not completed in the provided text.

Headnote

A) Contract Law - Interpretation of Force Majeure Clause - Effect of Pre-Contractual Minutes - Arbitration and Conciliation Act, 1996, Sections 34, 37 - The core issue was whether minutes of a meeting held prior to execution of the agreement could transform a force majeure clause into a guaranteed minimum return provision, obligating the State to compensate for any toll revenue shortfall beyond 20% - The arbitral tribunal had interpreted Clause 3.4.19, read with the minutes, as requiring such compensation; the State challenged this interpretation as perverse in an appeal under Section 37 - The High Court examined the terms and minutes to determine if the arbitral award suffered from patent illegality (Paras 9-15).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the force majeure clause (Clause 3.4.19) contained in the build-operate-transfer agreement was altered by the minutes of meeting dated August 18, 1999, effectively converting it into a minimum assured return obligation requiring the State to compensate the concessionaire for any drop in toll collection exceeding 20%.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Interpretation of force majeure clause
  • Effect of pre-contractual minutes of meeting on contractual terms
  • Section 37 of Arbitration and Conciliation Act
  • 1996
  • Compensation for drop in toll collection
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (BOM) (01) 41

Arbitration Appeal No. 33 of 2015

2026-01-17

Somasekhar Sundaresan, J.

Mr. Kuldeep Patil for Appellant; Ms. Sonal a/w Ujwala Kamat, Anoop Sharma, Sumit Khanna, Vaibhav Singh for Respondent; Mr. A.R. Patil, Addl. G.P. for State

State of Maharashtra

M/s Patwardhan Infrastructure Pvt. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration appeal under Section 37 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award and the judgment of the High Court that upheld the award dismissing a Section 34 challenge.

Remedy Sought

The State of Maharashtra sought to set aside the arbitral award dated November 7, 2012 that directed compensation for toll collection shortfall, and to set aside the judgment dated September 24, 2014 dismissing its Section 34 challenge.

Filing Reason

The State contended that the arbitral award erroneously interpreted the force majeure clause as providing a guaranteed minimum return, requiring compensation for any toll drop exceeding 20%, and that such interpretation was perverse.

Previous Decisions

Arbitral Award dated November 7, 2012 in favour of Patwardhan; High Court judgment dated September 24, 2014 dismissing the State's petition under Section 34, thereby upholding the award.

Issues

Whether the force majeure clause (Clause 3.4.19) in the build-operate-transfer agreement was altered by the minutes of meeting dated August 18, 1999, converting it into a minimum assured return mechanism that obligated the State to compensate the concessionaire for any drop in toll collection exceeding 20%.

Submissions/Arguments

Mr. Kuldeep Patil, for the State, argued that the Arbitral Tribunal's interpretation that the force majeure clause ceased to be a force majeure clause and instead guaranteed compensation for any drop over 20% was perverse and no reasonable judicial mind would arrive at such a conclusion.

Judgment Excerpts

The core issue that falls for consideration is whether the force majeure clause contained in Clause 3.4.19 of the Agreement ceased to be a force majeure clause by reason of the MOM, and whether the parties had instead agreed to change the Project to one guaranteeing a minimum assured return, whereby any loss of toll collection of more than 20% would entail a rupee-for-rupee compensation by the State. It was, therefore, agreed by all, that a decision in this regard can be taken when Rewas Karanja Bridge is completed and opened to traffic, on merits of the case & on the basis of variation in actual traffic at that time. If any time during the execution/completion of the project the Entrepreneur not able to proceed with constructing/completion of the project beyond a period of one month due to any reason beyond his control... the Government shall compensate him for such deficit/shortfall in toll collection along with simple interest equivalent to prime lending rate of State Bank of India prevalent at the time.

Procedural History

Tender invited for construction of two-lane bridge on BOT basis. Ameya Developers won the bid with a concession period of 13 years, 7 months, and 35 days. Tripartite agreement executed between the State, Ameya, and Patwardhan Infrastructure Pvt. Ltd. Two letters dated July 2, 1999 from Ameya raised concerns about a new Rewas-Karanja bridge. Meeting held on August 18, 1999; minutes recorded discussion on Clauses 3.4.19 and 3.7.2. Multiple arbitration proceedings ensued. Impugned Arbitral Award dated November 7, 2012 directed the State to compensate Patwardhan for toll collection shortfall. State challenged the award under Section 34; High Court dismissed the challenge on September 24, 2014. State filed present appeal under Section 37 of the Arbitration and Conciliation Act, 1996 in 2015.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Adjudicates Challenge to MMRDA's Additional Premium Demand — Interpretation of Articles 2(c), 2(d), 2(e) of Lease Deed and Impact of Supplementary Lease Deed. The Court Examines Whether Delay in Construction Attributable to MMRDA'...
Related Judgement
High Court Bombay High Court Considers Whether Minutes of Meeting Converted Force Majeure Clause into Assured Return Mechanism, Interpreting Clauses 3.4.19 and 3.7.2 of Construction Agreement. Appeal Challenges Arbitral Interpretation That State Must Compensate...