Case Note & Summary
The dispute arose out of a contract dated 18 September 1999 between Ultratech Cement Ltd. (appellant, formerly Larsen & Toubro Ltd.) and Sunfield Resources Pty. Ltd. (respondent) for the supply of non-coking coal of South African origin. The respondent shipped five firm cargoes to the appellant at Pipavav and Chennai ports, all of which went on demurrage. According to clause 10(v) of the contract, demurrage was payable by the buyer within 60 days of submission of laytime statement with supporting documents, and any disagreement had to be raised within 30 days, failing which the statement would be deemed accepted. The respondent submitted invoices and documents for demurrage totalling US$245,337.92. The appellant did not raise any disagreement within the contractual period. Thereafter, the appellant invoked arbitration without specifying the dispute and sought appointment of an arbitrator. The respondent filed a claim for demurrage and interest, while the appellant filed a counterclaim for damages of US$478,619.62 for non-supply of option cargo. The sole arbitrator (Justice M.N. Chandurkar) framed issues, recorded evidence, and by award dated 4 July 2003 allowed the respondent's claim for demurrage with interest at 5% per annum from 15 September 2000 till award and 18% from award till payment, and dismissed the counterclaim. The arbitrator held that clause 10(v) created a primary liability and not an indemnity, that the laytime statement had become binding as no disagreement was raised, and that the counterclaim was not maintainable as no prior dispute had been raised. The appellant challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The learned Single Judge dismissed the petition on 30 June 2005, finding no ground to interfere. In appeal under Section 37, the Division Bench noted the limited scope of interference, that the award was based on appreciation of evidence and interpretation of the contract, and that concurrent findings could not be disturbted unless patently illegal or perverse. The court found no such infirmity. It upheld the arbitrator's interpretation that demurrage was a primary liability, the binding effect of the unchallenged laytime statement, and the rejection of the counterclaim. The appeal was accordingly dismissed, with the award and the Single Judge's order confirmed.
Headnote
A) Arbitration Law - Scope of Interference under Section 34 and 37 - Concurrent Findings of Fact and Law - Arbitration and Conciliation Act, 1996, Sections 34, 37 - The arbitrator allowed the respondent-claimant's demurrage claim and dismissed the appellant's counterclaim; the Single Judge dismissed the Section 34 petition, thus there were concurrent findings. The Division Bench held that the award did not suffer from patent illegality or perversity, and the interpretation given to the contractual clause was a possible one, hence no interference warranted. Held: Appeal dismissed (Paras 1, 14). B) Contract Law - Interpretation of Demurrage Clause - Primary Liability vs. Indemnity - Clause 10(v) of the Contract - The clause provided that 'buyers shall pay demurrage' and settlement to be within 60 days; the arbitrator interpreted this as creating a primary obligation on the buyer, not an indemnity, and that proof of prior payment to vessel owner was not required. The High Court upheld this interpretation as not contrary to the contract's plain terms. Held: Arbitrator's finding was within jurisdiction and not perverse (Paras 4, 9, 13). C) Procedural Law - Limitation and Estoppel - Binding Effect of Unchallenged Laytime Statement - Clause 10(v) of the Contract - As per clause, any disagreement over laytime statement must be raised within 30 days; the appellant failed to do so. The arbitrator held that the statement was accepted as correct and demurrage became payable. The High Court concurred that this finding was based on evidence and contract terms, and no interference was called for. Held: Finding upheld (Paras 6, 7, 13-14). D) Arbitration - Counterclaim - Maintainability - Requirement of Prior Dispute Notice - Arbitration and Conciliation Act, 1996 - The appellant raised a counterclaim for damages pertaining to option cargo, which was never previously disputed. The arbitrator rejected it as not maintainable, noting that the counterclaim did not form part of the original dispute. The High Court upheld this finding, as it was not arbitrary. Held: Rejection of counterclaim sustained (Paras 10, 11, 13). E) Arbitration - Interest on Awarded Sum - Discretion of Arbitrator - The arbitrator awarded interest at 5% p.a. from 15 September 2000 till award and 18% p.a. from award till payment; the High Court found no error in the exercise of discretion, thus no interference (Paras 14).
Issue of Consideration
Whether the arbitral award allowing the demurrage claim and rejecting the counterclaim suffered from any infirmity warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996; whether the award was patently illegal or perverse.
Final Decision
Appeal dismissed. The judgment and order of the Single Judge dated 30 June 2005 rejecting the petition under Section 34 of the Arbitration and Conciliation Act, 1996 is confirmed. The arbitral award dated 4 July 2003 (operative award dated 4 June 2003) allowing the respondent's demurrage claim of US$245,337.92 with interest at 5% per annum from 15 September 2000 till award and at 18% per annum from award till payment, and dismissing the counterclaim, is upheld. Costs of the appeal to be borne by the appellant.
Law Points
- Limited scope of interference under Sections 34 and 37 of Arbitration and Conciliation Act
- 1996
- interpretation of contract is a matter for arbitrator
- concurrent findings of fact and law not to be disturbed unless perverse
- laytime statement becomes binding if not challenged within contractual timeline
- demurrage clause creates primary liability not indemnity
- counterclaim not maintainable if dispute not raised prior to arbitration



