High Court of Bombay Dismisses Appeal Under Section 37 of Arbitration and Conciliation Act, 1996, Upholding Demurrage Claim. Interpretation of Clause 10(v) of Coal Supply Contract as Creating Primary Liability, Not Indemnity, and Binding Effect of Laytime Statement When No Disagreement Raised Within 30 Days Upheld.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose out of a contract dated 18 September 1999 between Ultratech Cement Ltd. (appellant, formerly Larsen & Toubro Ltd.) and Sunfield Resources Pty. Ltd. (respondent) for the supply of non-coking coal of South African origin. The respondent shipped five firm cargoes to the appellant at Pipavav and Chennai ports, all of which went on demurrage. According to clause 10(v) of the contract, demurrage was payable by the buyer within 60 days of submission of laytime statement with supporting documents, and any disagreement had to be raised within 30 days, failing which the statement would be deemed accepted. The respondent submitted invoices and documents for demurrage totalling US$245,337.92. The appellant did not raise any disagreement within the contractual period. Thereafter, the appellant invoked arbitration without specifying the dispute and sought appointment of an arbitrator. The respondent filed a claim for demurrage and interest, while the appellant filed a counterclaim for damages of US$478,619.62 for non-supply of option cargo. The sole arbitrator (Justice M.N. Chandurkar) framed issues, recorded evidence, and by award dated 4 July 2003 allowed the respondent's claim for demurrage with interest at 5% per annum from 15 September 2000 till award and 18% from award till payment, and dismissed the counterclaim. The arbitrator held that clause 10(v) created a primary liability and not an indemnity, that the laytime statement had become binding as no disagreement was raised, and that the counterclaim was not maintainable as no prior dispute had been raised. The appellant challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The learned Single Judge dismissed the petition on 30 June 2005, finding no ground to interfere. In appeal under Section 37, the Division Bench noted the limited scope of interference, that the award was based on appreciation of evidence and interpretation of the contract, and that concurrent findings could not be disturbted unless patently illegal or perverse. The court found no such infirmity. It upheld the arbitrator's interpretation that demurrage was a primary liability, the binding effect of the unchallenged laytime statement, and the rejection of the counterclaim. The appeal was accordingly dismissed, with the award and the Single Judge's order confirmed.

Headnote

A) Arbitration Law - Scope of Interference under Section 34 and 37 - Concurrent Findings of Fact and Law - Arbitration and Conciliation Act, 1996, Sections 34, 37 - The arbitrator allowed the respondent-claimant's demurrage claim and dismissed the appellant's counterclaim; the Single Judge dismissed the Section 34 petition, thus there were concurrent findings. The Division Bench held that the award did not suffer from patent illegality or perversity, and the interpretation given to the contractual clause was a possible one, hence no interference warranted. Held: Appeal dismissed (Paras 1, 14).

B) Contract Law - Interpretation of Demurrage Clause - Primary Liability vs. Indemnity - Clause 10(v) of the Contract - The clause provided that 'buyers shall pay demurrage' and settlement to be within 60 days; the arbitrator interpreted this as creating a primary obligation on the buyer, not an indemnity, and that proof of prior payment to vessel owner was not required. The High Court upheld this interpretation as not contrary to the contract's plain terms. Held: Arbitrator's finding was within jurisdiction and not perverse (Paras 4, 9, 13).

C) Procedural Law - Limitation and Estoppel - Binding Effect of Unchallenged Laytime Statement - Clause 10(v) of the Contract - As per clause, any disagreement over laytime statement must be raised within 30 days; the appellant failed to do so. The arbitrator held that the statement was accepted as correct and demurrage became payable. The High Court concurred that this finding was based on evidence and contract terms, and no interference was called for. Held: Finding upheld (Paras 6, 7, 13-14).

D) Arbitration - Counterclaim - Maintainability - Requirement of Prior Dispute Notice - Arbitration and Conciliation Act, 1996 - The appellant raised a counterclaim for damages pertaining to option cargo, which was never previously disputed. The arbitrator rejected it as not maintainable, noting that the counterclaim did not form part of the original dispute. The High Court upheld this finding, as it was not arbitrary. Held: Rejection of counterclaim sustained (Paras 10, 11, 13).

E) Arbitration - Interest on Awarded Sum - Discretion of Arbitrator - The arbitrator awarded interest at 5% p.a. from 15 September 2000 till award and 18% p.a. from award till payment; the High Court found no error in the exercise of discretion, thus no interference (Paras 14).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award allowing the demurrage claim and rejecting the counterclaim suffered from any infirmity warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996; whether the award was patently illegal or perverse.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal dismissed. The judgment and order of the Single Judge dated 30 June 2005 rejecting the petition under Section 34 of the Arbitration and Conciliation Act, 1996 is confirmed. The arbitral award dated 4 July 2003 (operative award dated 4 June 2003) allowing the respondent's demurrage claim of US$245,337.92 with interest at 5% per annum from 15 September 2000 till award and at 18% per annum from award till payment, and dismissing the counterclaim, is upheld. Costs of the appeal to be borne by the appellant.

Law Points

  • Limited scope of interference under Sections 34 and 37 of Arbitration and Conciliation Act
  • 1996
  • interpretation of contract is a matter for arbitrator
  • concurrent findings of fact and law not to be disturbed unless perverse
  • laytime statement becomes binding if not challenged within contractual timeline
  • demurrage clause creates primary liability not indemnity
  • counterclaim not maintainable if dispute not raised prior to arbitration
Subscribe to unlock Law Points Subscribe Now

Case Details

2016 LawText (BOM) (12) 26

Appeal No. 881 of 2005 in Arbitration Petition No. 35 of 2004

2016-12-21

Anoop V. Mohta, G.S. Kulkarni

2016:BHC-OS:18054-DB

Pradip Sancheti, Birendra Saraf, Darshet Jain, Sachin Chandarana, Vijeyandra Purohit, Sanat Mukharjee

Ultratech Cement Ltd. (formerly Larsen And Toubro Ltd.)

Sunfield Resources Pty. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37 of the Arbitration and Conciliation Act, 1996 against the judgment of a Single Judge who had dismissed the appellant's petition under Section 34 of the same Act, thereby upholding an arbitral award.

Remedy Sought

Appellant sought to set aside the arbitral award and the Single Judge's order and to either dismiss the demurrage claim or allow the counterclaim.

Filing Reason

The appellant disputed the demurrage claim on grounds that clause 10(v) was an indemnity and that no demurrage had been proved to be paid to the vessel owner, and also claimed damages for non-supply of option cargo.

Previous Decisions

Sole Arbitrator allowed respondent's demurrage claim of US$245,337.92 with interest and dismissed appellant's counterclaim for US$478,619.62. Single Judge of High Court rejected the petition under Section 34 and upheld the award.

Issues

Whether clause 10(v) of the contract created a primary liability on the buyer to pay demurrage or was merely an indemnity requiring proof of payment to the vessel owner. Whether the laytime statement submitted by the respondent became binding on the appellant due to failure to raise disagreement within 30 days as per clause 10(v). Whether the counterclaim regarding option cargo was maintainable in the arbitration proceedings. Whether the arbitral award suffered from any patent illegality or perversity warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Appellant argued that demurrage under clause 10(v) was an indemnity and could only be claimed upon proof of payment to the vessel owner; no such evidence was furnished. Appellant contended that certain periods should be excluded from demurrage calculation and that the vessels did not go on demurrage as alleged. Appellant claimed that the respondent failed to supply option cargo, causing loss of US$478,619.62, which was raised as a counterclaim. Respondent submitted that clause 10(v) imposed a primary obligation on the buyer to settle demurrage within 60 days, and that no disagreement having been raised within 30 days, the laytime statement stood accepted as correct. Respondent argued that the counterclaim was not maintainable as no dispute regarding option cargo had been raised prior to the arbitration notice.

Ratio Decidendi

Under Section 34 of the Arbitration and Conciliation Act, 1996, the court does not sit in appeal over the arbitral award; interference is permissible only if the award exhibits patent illegality or is contrary to the explicit terms of the contract. The interpretation given by the arbitrator to clause 10(v) that it created a primary liability to pay demurrage and that the laytime statement became binding in the absence of timely disagreement was a plausible and reasonable interpretation based on evidence. The arbitrator's findings on the counterclaim's maintainability and the overall appreciation of evidence were not perverse. Concurrent findings of fact and law by the arbitrator and the Single Judge cannot be reopened under Section 37 unless there is gross miscarriage of justice, which was not made out.

Judgment Excerpts

Any disagreement over the laytime statement must be raised by the other party within 30 days after such statement is transmitted and received, otherwise, the statement is accepted as correct. The learned Arbitrator allowed the claim made by the Respondent (original claimant) and rejected the counterclaim of the Appellant (original Respondent). Thus there are concurrent findings of two forums against the Appellants. The Respondent's case is that though invoices alongwith the supporting documents were submitted by the Respondent to the Appellant, there was no disagreement on the part of the Appellant and thus as per Clause 10(v) the Appellant was under an obligation to settle the demurrage within sixty days of the submission of the invoices, which it failed to do.

Procedural History

Dispute arose under contract of 18 September 1999 regarding demurrage claims. Appellant invoked arbitration by letter dated 24 November 2000. Justice M.N. Chandurkar (Retd.) appointed as Sole Arbitrator. Arbitrator framed issues, recorded evidence, and passed award on 4 June 2003 allowing respondent's claim and dismissing counterclaim. Appellant filed petition under Section 34 of Arbitration and Conciliation Act, 1996 before Single Judge of Bombay High Court, which was dismissed on 30 June 2005. Appellant preferred appeal under Section 37 before Division Bench, which heard the matter and pronounced judgment on 21 December 2016 dismissing the appeal.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34, 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Karnataka Acquits Accused in Waging War Against State Case Due to Lack of Evidence and Procedural Irregularities. Conviction under Sections 121, 122, 124A IPC, Arms Act, and Explosive Substances Act set aside as prosecution failed to pr...
Related Judgement
High Court High Court of Karnataka Dismisses Writ Appeal in Land Grant Dispute — Appellant Failed to Prove Occupancy as on 1.3.1974. Land Tribunal's Order Confirmed as No Material Evidence of Cultivation or Possession on Appointed Date Under Karnataka Land Re...