Case Note & Summary
The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 arose from a construction dispute between Country Club (India) Ltd. (petitioner, original respondent in arbitration) and Choudhury & Choudhury (India) Ltd. (respondent, original claimant). In 2007, the petitioner invited tenders for construction of a Club House and related facilities at Kolad, Raigad. The respondent's bid for Rs.14,64,49,410 was accepted, with a completion period of 12 months. The respondent allegedly failed to complete the work by April 2009 and abandoned the site. Disputes arose regarding defective work and outstanding payments. The respondent invoked arbitration under the contract, claiming Rs.1,97,05,428 plus interest, and a former High Court judge was appointed as sole arbitrator. In the arbitral proceedings, the respondent filed a statement of claim seeking Rs.7,18,87,248, a significantly higher amount. The petitioner objected that many claims exceeded the scope of the reference as defined in the notice invoking arbitration. The arbitrator made an award on 8 August 2012, allowing several claims and directing the petitioner to pay Rs.1,65,64,239.69 with interest, along with other amounts, while allowing a set-off for the counterclaim. The petitioner challenged the award under Section 34, raising two primary grounds: (i) the arbitrator exceeded jurisdiction by entertaining claims beyond those mentioned in the notice of invocation, and (ii) the award relied on three certificates issued by the Project Architect which were not proved by examining the Architect, thereby violating the Evidence Act and principles of natural justice. The petitioner argued that the arbitrator brushed aside jurisdictional objections and that perversity was evident. The court considered these submissions. The judgment text excerpt does not contain the final decision or the complete reasoning of the court.
Issue of Consideration
Whether the arbitral award is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the ground that the arbitrator exceeded his jurisdiction by entertaining claims beyond the scope of reference, and whether the award is vitiated by relying on unproved documents in violation of the principles of natural justice
Law Points
- Arbitrator's jurisdiction is limited to claims referred in the notice invoking arbitration
- claims beyond notice are without jurisdiction
- unproved documents cannot be relied upon
- award based on unproved evidence is patently illegal and against public policy
Case Details
2016 LawText (BOM) (10) 87
Arbitration Petition No. 29 of 2013
R.S. Apte, Anoop Sharma, Shibu Devasia, Ghanshyam Tripathi, Chetan Kapadia, Ashish Gatagat
Country Club (India) Ltd.
Choudhury & Choudhury (India) Ltd.
Subscribe to unlock Case Details (Citation, Judge, Date & more)
Subscribe Now
Nature of Litigation
Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award arising from a construction contract dispute.
Remedy Sought
Petitioner (original respondent in arbitration) seeks setting aside of the arbitral award dated 8 August 2012.
Filing Reason
Petitioner alleges that the arbitrator exceeded jurisdiction by allowing claims beyond the scope of reference and relied on unproved documents, violating natural justice.
Previous Decisions
Arbitral award dated 8 August 2012 allowed some claims of respondent and partly allowed counterclaims, directing petitioner to pay Rs.1,65,64,239.69 plus interest and other amounts, with set-off for counterclaim.
Issues
Whether the arbitrator exceeded his jurisdiction by entertaining claims beyond the amount and nature specified in the notice invoking arbitration, thereby acting beyond the scope of reference.
Whether the arbitral award is vitiated by patent illegality and violation of natural justice due to reliance on unproved certificates and perverse findings.
Submissions/Arguments
Petitioner argued that the arbitrator's jurisdiction was limited to the claims stated in the respondent's notice dated 19 June 2009; the statement of claim inflated the sum from Rs.1,97,05,428 to Rs.7,18,87,248, which was beyond the terms of reference, and the arbitrator failed to consider this jurisdictional objection.
Petitioner contended that the award relied on three certificates issued by the Project Architect (dated 6 October 2008, 6 March 2009, and 25 May 2009) without the Architect being examined as a witness, making such evidence unproved and inadmissible, in violation of the Evidence Act and principles of natural justice.
Petitioner submitted that the award suffered from perversity because the arbitrator accepted a certificate stating completion of the Spa building first floor slab, contrary to the admission of the respondent's own witness that the slab was not cast.
Judgment Excerpts
It is submitted by the learned senior counsel that scope of the arbitration before the learned arbitrator was limited to the claims referred in the letter dated 19th June 2009 addressed by the learned advocate for the respondent and the letter dated 15th July 2009 addressed by the petitioner. He submits that the respondent had invoked arbitration agreement vide their letter dated 19th June 2009 seeking reference to the arbitration of claims of the value of Rs.3,13,97,099/- which included a principal sum of Rs.1,97,05,428.22 and interest thereon totalling to Rs.3,13,97,099/-. He submits that the respondent, however raised claim for an amount of Rs.7,18,87,248/- in their statement of claims.
It is submitted by the learned senior counsel that since the three certificates alleged to have been issued by the Project Architect were not proved and could not be relied upon, the learned arbitrator could not have rejected the contention of the petitioner that the quality of the material used by the respondent which was poor and inferior and the poor workmanship of the workers engaged by the respondent.
Procedural History
In 2007, petitioner invited tenders for construction work; respondent's bid accepted on 12 October 2007 with completion due by 11 October 2008. Respondent allegedly failed to complete work by April 2009 and stopped work on 30 April 2009. On 11 August 2009, petitioner issued show cause notice threatening termination. Respondent through notice dated 19 June 2009 demanded payment of Rs.1,97,05,428 plus interest and invoked arbitration. Petitioner terminated contract and jointly appointed former High Court judge as sole arbitrator on 17 August 2009, specifying terms of reference in letter dated 29 August 2009. Respondent filed statement of claim with inflated amounts; petitioner filed written statement, counterclaim, and raised jurisdictional objection. Arbitrator passed award on 8 August 2012 allowing some claims and part of counterclaim. Petitioner filed present petition under Section 34 in 2013.
Acts & Sections
- Arbitration and Conciliation Act, 1996: Section 34