Case Note & Summary
The Union of India, acting through the Controller of Stores, Western Railway, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 9 February 2015. The dispute arose from a contract for supply of 370 sets of body side arrangement assembled with flap doors and body end arrangement for BOXNR wagons. The respondent, M/s Motor & General Sales Ltd., was awarded the contract with a delivery period of 60 days. The respondent supplied 30 sets within the original period but sought extension of delivery schedule up to 31 August 2013 without liquidated damages. The petitioner granted extension up to 30 September 2013 but imposed liquidated damages. The respondent delivered the remaining material under protest and the petitioner deducted amounts from running bills as liquidated damages. The respondent invoked arbitration. The arbitrator directed refund of the deducted amounts, holding that the petitioner failed to prove any loss due to delayed delivery. The petitioner challenged the award on the ground that the arbitrator ignored the contract terms and that the award was contrary to public policy. The High Court dismissed the petition, holding that the arbitrator's interpretation was plausible and not perverse, and that the petitioner did not establish any loss. The court noted that the arbitrator had considered the contract and the evidence, and the findings were not open to interference under Section 34.
Headnote
A) Arbitration - Section 34 of the Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - The court considered whether the arbitral award directing refund of liquidated damages was contrary to the contract and public policy. The court held that the arbitrator's finding that the petitioner failed to prove any loss due to delayed delivery was a plausible view and not perverse, thus not amenable to interference under Section 34. (Paras 1-10) B) Contract Law - Liquidated Damages - Proof of Loss - The court examined the requirement of proof of actual loss for recovery of liquidated damages. The court held that even if the contract provides for liquidated damages, the claimant must prove that loss was suffered due to breach; otherwise, the amount deducted must be refunded. (Paras 8-10)
Issue of Consideration
Whether the arbitral award directing refund of liquidated damages deducted by the petitioner is contrary to the contract and public policy under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The High Court dismissed the petition, upholding the arbitral award. The court held that the arbitrator's finding that the petitioner failed to prove any loss due to delayed delivery was a plausible view and not perverse, and thus not amenable to interference under Section 34 of the Arbitration and Conciliation Act, 1996.
Law Points
- Section 34 of the Arbitration and Conciliation Act
- 1996
- Public policy
- Liquidated damages
- Proof of loss
- Re-fixation of delivery schedule





