Case Note & Summary
The petitioners, Reid & Taylor (I) Limited, S.Kumars Nationwide Ltd., and Nitin S. Kasliwal, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 6th May 2015. The respondent, L & T Finance Limited, had sanctioned a term loan of Rs.50 crores to petitioner no.1 under a Facility Agreement dated 13th October 2011, with petitioners no.2 and 3 as guarantors. The loan was repayable in 36 monthly installments. The petitioners defaulted on payment of installments from March 2013. The respondent invoked arbitration and claimed the entire outstanding amount, including future installments, with interest. The learned arbitrator passed an award directing the petitioners jointly and severally to pay Rs.51,03,66,127.61, comprising overdue installments, future installments, compensation, and interest at 18% p.a. from 16th March 2013 till payment. The petitioners challenged the award on grounds that the arbitrator erred in awarding future installments and interest at 18% p.a., and that the award was contrary to the terms of the contract and public policy. The court, after examining the Facility Agreement and the award, held that the arbitrator's interpretation of the contract was plausible and not perverse. The agreement contained an acceleration clause allowing the lender to demand immediate payment of all outstanding amounts upon default. The court also found that the interest rate of 18% p.a. was within the contractual rate and not excessive. The court dismissed the petition, upholding the award in its entirety.
Headnote
A) Arbitration Law - Section 34 of Arbitration and Conciliation Act, 1996 - Scope of Interference - The court considered the limited grounds for setting aside an arbitral award under Section 34, including patent illegality and conflict with public policy. The court held that the arbitrator's interpretation of the contract, including acceleration of future installments and interest rate, was plausible and not perverse, and thus not open to interference. (Paras 1-10) B) Contract Law - Facility Agreement - Acceleration Clause - The Facility Agreement dated 13th October 2011 contained a clause allowing the lender to demand immediate payment of all outstanding amounts upon default. The court upheld the arbitrator's finding that the respondent was entitled to claim future installments upon default, as per the contract. (Paras 2-5) C) Interest - Rate of Interest - 18% p.a. - The arbitrator awarded interest at 18% p.a. on the awarded amount from 16th March 2013 till payment. The court found no infirmity in the rate of interest, as it was within the contractual rate and not excessive. (Para 6) D) Guarantee - Liability of Guarantors - The petitioners no.2 and 3 were guarantors under the Facility Agreement. The court upheld the arbitrator's finding that they were jointly and severally liable for the debt, as per the guarantee clause. (Para 3)
Issue of Consideration
Whether the arbitral award dated 6th May 2015 directing the petitioners to pay Rs.51,03,66,127.61 with interest @18% p.a. is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of being contrary to the terms of the contract, public policy, or the substantive law of India.
Final Decision
The court dismissed the petition and upheld the arbitral award dated 6th May 2015.
Law Points
- Section 34 of Arbitration and Conciliation Act
- 1996
- Scope of interference with arbitral award
- Public policy
- Interpretation of contract terms
- Interest rate
- Future installments
- Guarantee liability





