Bombay High Court Dismisses Developer's Section 9 Petition for Appointment of Court Receiver in Redevelopment Dispute. Court holds that disputes regarding possession of flats by dissenting members are not arbitrable under the agreement and that the developer failed to establish a prima facie case for interim relief.

High Court: Bombay High Court Bench: BOMBAY
  • 54
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Aditya Developers, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking appointment of a Court Receiver to take possession of flats from respondent nos.2 to 7 and hand them over to the petitioner for demolition and redevelopment pursuant to a Redevelopment Agreement dated 25.9.2013 with respondent no.1 Society. The agreement contained an arbitration clause (Clause 62) for resolution of disputes between the parties. The petitioner alleged that respondent nos.2 to 7, who were members of the Society, were obstructing the redevelopment by not vacating their flats. The court examined whether the disputes with respondent nos.2 to 7 were arbitrable, as they were not parties to the agreement. The court held that the arbitration agreement only bound the petitioner and the Society, and disputes with third parties could not be referred to arbitration. Consequently, no interim relief could be granted under Section 9 against respondent nos.2 to 7. The court also noted that the petitioner failed to establish a prima facie case, balance of convenience, or irreparable loss. The petition was dismissed.

Headnote

A) Arbitration - Interim Relief under Section 9 - Prima Facie Case - The petitioner sought appointment of Court Receiver for possession of flats from dissenting members for demolition and redevelopment. The court held that the disputes regarding possession of flats by respondent nos.2 to 7 were not covered by the arbitration agreement as they were not parties to the agreement. The petitioner failed to make out a prima facie case for interim relief. (Paras 2-5)

B) Arbitration - Scope of Arbitration Agreement - Third Parties - The arbitration agreement was between the petitioner and respondent no.1 Society only. The court held that disputes with respondent nos.2 to 7, who were not signatories to the agreement, could not be referred to arbitration. Therefore, no interim relief could be granted against them under Section 9. (Paras 3-5)

C) Arbitration - Balance of Convenience - Irreparable Loss - The court found that the balance of convenience was not in favor of the petitioner as the dissenting members were in possession and the petitioner had not obtained their consent. The petitioner also failed to show irreparable loss. (Para 5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner is entitled to appointment of Court Receiver in respect of the property under Section 9 of the Arbitration and Conciliation Act, 1996, pending arbitration.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is dismissed. No order as to costs.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • Prima facie case
  • Balance of convenience
  • Irreparable loss
  • Arbitrability of disputes
  • Scope of arbitration agreement
Subscribe to unlock Law Points Subscribe Now

Case Details

2016 LawText (BOM) (02) 60

Arbitration Petition No.1521 of 2015

2016-02-10

K.K. Tated

Mr. Vishal Kanade a/w Mr.M.P.Vora i/b M/s.Pramodkumar & Co. for the petitioner, Mr.Sachin V. Masurkar a/w Ms.Sunitha Perumal for the respondent no.1, Mr.Bharat Joshi for the respondent no.3, Mr.A.S.Patil for the respondent no.5, Mr.R.R.Varma for the respondent nos.6 and 7

Aditya Developers

Nirmal Anand Cooperative Housing Society Ltd. & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 9 of the Arbitration and Conciliation Act, 1996 for appointment of Court Receiver.

Remedy Sought

Appointment of Court Receiver to take possession of flats from respondent nos.2 to 7 and hand over to petitioner for demolition and redevelopment.

Filing Reason

Respondent nos.2 to 7, members of the Society, were obstructing redevelopment by not vacating their flats.

Issues

Whether the petitioner is entitled to appointment of Court Receiver under Section 9 of the Arbitration and Conciliation Act, 1996. Whether the disputes with respondent nos.2 to 7 are arbitrable under the arbitration agreement.

Submissions/Arguments

Petitioner argued that respondent nos.2 to 7 were obstructing redevelopment and that interim relief was necessary. Respondents argued that they were not parties to the arbitration agreement and that the petition was not maintainable against them.

Ratio Decidendi

The arbitration agreement only binds the parties to it. Disputes with third parties who are not signatories to the agreement cannot be referred to arbitration, and no interim relief under Section 9 can be granted against them. The petitioner failed to establish a prima facie case, balance of convenience, or irreparable loss.

Judgment Excerpts

Heard the learned counsel for the parties. This petition is under section 9 of the Arbitration and Conciliation Act, 1996 for appointment of Court Receiver in respect of the property as described in Exhibit-A with power to take possession of flats from respondent nos.2 to 7 or their family members or any person found in possession thereof and hand over the same to the petitioner for demolition and redevelopment in accordance with the re-development agreement dated 25.9.2013.

Procedural History

The petitioner filed Arbitration Petition No.1521 of 2015 under Section 9 of the Arbitration and Conciliation Act, 1996. The court heard the learned counsel for the parties and dismissed the petition on 10/02/2016.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Developer's Section 9 Petition for Appointment of Court Receiver in Redevelopment Dispute. Court holds that disputes regarding possession of flats by dissenting members are not arbitrable under the agreement and that the d...
Related Judgement
High Court Bombay High Court Quashes Transfer Order of Chief Engineer in MSETCL for Non-Compliance with Transfer Policy. Transfer of Employee Mid-Academic Year Without Considering Family Circumstances Violates Principles of Natural Justice and Departmental Tran...