Bombay High Court Allows Appeal Under Section 37 of Arbitration and Conciliation Act, Sets Aside Injunction Against Company Not a Party to Arbitration Agreement. Court Holds That Interim Relief Under Arbitration and Conciliation Act Cannot Be Granted Against a Third Party Not Signatory to Arbitration Clause.

High Court: Bombay High Court Bench: AURANGABAD In Favour of Accused
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The appeal arose from a partnership dispute between respondent Nos. 1 and 2 who had formed a firm named M/s Kasliwal Empires for a housing project in Aurangabad. The partnership deed contained an arbitration clause. They jointly obtained a loan of Rs.9 crore from Buldhana Urban Cooperative Credit Society, which was later transferred to the account of the appellant company, Tapadiya Construction Ltd., under the control of respondent No.2. Alleging fraud, respondent No.1 filed an application under Section 9 of the Arbitration and Conciliation Act, 1996 against the appellant company and respondent No.2, seeking an injunction to restrain alienation of an immovable property purchased by the company in Hingoli, claiming the property was acquired with partnership funds. The Principal District Judge, Parbhani granted the injunction pending arbitration. The appellant company, which was not a party to the arbitration agreement, challenged the order under Section 37 of the Act. The High Court considered whether Section 9 could be invoked against a non-signatory to the arbitration agreement and whether the Parbhani court had territorial jurisdiction. The Court held that Section 9 permits interim measures only against a party to the arbitration agreement and a third-party company cannot be subjected to such relief. It also found that no part of the cause of action arose in Parbhani, as the partnership and project were in Aurangabad and the loan was from Buldhana; the mere location of the property in Hingoli did not confer jurisdiction. The company being a separate legal entity, its property could not be treated as belonging to the partners. Consequently, the appeal was allowed, the impugned order was set aside, and the Section 9 application against the appellant company was dismissed.

Headnote

A) Arbitration – Interim Measures – Section 9 of the Arbitration and Conciliation Act, 1996 – Scope – Held, an application under Section 9 for interim relief can be filed only against a party to the arbitration agreement; a third party cannot be subjected to such interim relief; the court cannot grant injunction against a company which was not a signatory to the arbitration clause (Paras 14-16).

B) Jurisdiction – Territorial – Section 9, Arbitration and Conciliation Act – The court held that the District Court at Parbhani lacked territorial jurisdiction as no part of cause of action arose in Parbhani; the partnership was based in Aurangabad, the project in Aurangabad, and the loan was from Buldhana; mere location of the property in Hingoli was not sufficient (Paras 10-12).

C) Company Law – Separate Legal Entity – A company is a distinct legal entity from its shareholders/directors; the appellant company’s property cannot be treated as property of the partners (Para 16).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether an interim injunction under Section 9 of the Arbitration and Conciliation Act, 1996 can be granted against a third party who is not a signatory to the arbitration agreement?

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court allowed the appeal, set aside the order of the District Court, and held that the appellant company being a third party to the arbitration agreement cannot be injuncted under Section 9. The District Court's order was without jurisdiction both as to the person and territory. The Section 9 application against the appellant company was dismissed. No order as to costs.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996 is available only against parties to the arbitration agreement
  • no injunction can be granted against a third party to the arbitration agreement
  • the court under Section 9 can grant interim measures only against a party to the arbitration proceeding
  • the remedy under Section 9 is ancillary to the arbitration and cannot be used against a stranger
Subscribe to unlock Law Points Subscribe Now

Case Details

2015 LawText (BOM) (12) 21

Arbitration Appeal No. 6 of 2015

2015-12-03

T. V. Nalawade, J.

Mr. Bajaj Anil S. for Appellant; Mr. P. M. Shah, Senior Counsel with Mr. S. V. Advant for Respondent No.1; Mr. R. F. Totala with Mr. S. A. Nirbar for Respondent No.2

Tapadiya Construction Ltd. (through its Director Jugalkishor Chhaganlal Tapadia)

1. Sanjay Suganchand Kasliwal, 2. Jugalkishor Chhaganlal Tapadia

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration appeal under Section 37 of the Arbitration and Conciliation Act, 1996 against an order of interim injunction under Section 9.

Remedy Sought

Appellant sought to set aside the injunction granted by the District Court, Parbhani restraining alienation of its immovable property in Hingoli.

Filing Reason

Respondent No.1 had filed application under Section 9 claiming that the appellant company's property was purchased with partnership funds and sought to prevent alienation pending arbitration.

Previous Decisions

The Principal District Judge, Parbhani had allowed a Section 9 application and granted injunction against the appellant company and respondent No.2, with option to give bank guarantee to vacate the injunction.

Issues

Whether an interim injunction under Section 9 of the Arbitration and Conciliation Act, 1996 can be granted against a third party who is not a signatory to the arbitration agreement? Whether the District Court at Parbhani had territorial jurisdiction to entertain the application under Section 9?

Submissions/Arguments

Appellant argued that the company was not a party to the partnership agreement containing the arbitration clause and therefore no application under Section 9 could be maintained against it; the property was owned by the company and not by the partnership; and the Parbhani court lacked territorial jurisdiction. Respondent No.1 contended that the appellant company was used as a vehicle to siphon off partnership funds; the property was purchased with the loan amount meant for the partnership; thus, the company’s property was liable and the arbitration clause covered the dispute.

Ratio Decidendi

An application under Section 9 of the Arbitration and Conciliation Act, 1996 for interim measures can be maintained only against a party to the arbitration agreement; a third party cannot be subjected to such interim relief. A company is a distinct legal entity, and its property cannot be automatically treated as that of the partners. The court exercising jurisdiction under Section 9 must have territorial jurisdiction based on the cause of action; mere location of property is insufficient.

Judgment Excerpts

The only point that arises for consideration is whether an interim injunction under Section 9 of the Arbitration and Conciliation Act can be granted against a third party who is not a signatory to the arbitration agreement. This Court holds that Section 9 of the Act provides for interim measures by the Court only against a party to the arbitration agreement and not against a third party. The District Court, Parbhani had no territorial jurisdiction.

Procedural History

Respondent No.1 filed Miscellaneous Application No.198/2014 under Section 9 of the Arbitration and Conciliation Act, 1996 before the Court of Principal District Judge, Parbhani seeking interim injunction against the appellant company and Respondent No.2 restraining alienation of property. The District Judge granted the injunction with option to furnish bank guarantee. The appellant then filed the present Arbitration Appeal No.6 of 2015 under Section 37 of the Act before the High Court of Bombay at Aurangabad, which was heard finally on 3rd December 2015.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 9, 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Contempt Petition Against Town Planner and Panchayat Secretary for Alleged Violation of Undertaking in Land Access Dispute. The Court Held Contempt Not Maintainable Against Non-Parties to Original Proceeding as Undertaking...
Related Judgement
High Court Bombay High Court Allows Appeal Under Section 37 of Arbitration and Conciliation Act, Sets Aside Injunction Against Company Not a Party to Arbitration Agreement. Court Holds That Interim Relief Under Arbitration and Conciliation Act Cannot Be Granted...