Case Note & Summary
The petitioner, M/s B.E. Billimoria & Co. Ltd., filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging part of an arbitral award dated 27 March 2014. The dispute arose from a construction contract between the petitioner (original claimant) and the respondent (original claimant in arbitration), M/s Raheja Universal Private Ltd., for developing a piece of land in Mangalore and constructing two residential towers. The contract value was Rs. 86,66,62,094.03, with a completion period of 21 calendar months from 13 March 2012 to 12 December 2013. The petitioner alleged that the respondent delayed handing over the site and failed to provide necessary approvals, causing delays. The respondent, however, claimed that the petitioner was responsible for the delay and levied liquidated damages. The arbitrator allowed the respondent's claim for liquidated damages. The petitioner challenged this part of the award, arguing that the arbitrator ignored the petitioner's claims of delay caused by the respondent and that the award was patently illegal. The court examined the evidence and the arbitrator's reasoning, noting that the arbitrator had considered the correspondence and submissions of both parties. The court found that the arbitrator's findings were based on evidence and were not perverse or patently illegal. The court held that the scope of interference under Section 34 is limited and that the award did not shock the conscience of the court. Consequently, the court dismissed the petition, upholding the arbitral award on liquidated damages.
Headnote
A) Arbitration - Section 34 of the Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Liquidated Damages - The petitioner challenged the arbitral award granting liquidated damages to the respondent for delay in completion of a construction project. The court held that the arbitrator's findings on delay and quantification of liquidated damages were based on evidence and not patently illegal. The court refused to interfere under Section 34 as the award did not shock the conscience of the court. (Paras 1-17) B) Contract - Liquidated Damages - Construction Contract - Delay - The contract provided for liquidated damages for delay. The arbitrator found that the petitioner was responsible for delay and allowed the respondent's claim. The court upheld the award, noting that the arbitrator had considered the evidence and the terms of the contract. (Paras 3-15)
Issue of Consideration
Whether the arbitral award granting liquidated damages to the respondent is patently illegal or contrary to public policy under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The court dismissed the petition, upholding the arbitral award on liquidated damages.
Law Points
- Section 34 of the Arbitration and Conciliation Act
- 1996
- Liquidated damages
- Patent illegality
- Public policy
- Construction contract
- Delay in performance




