Case Note & Summary
The petitioner, Indian Oil Corporation Ltd., challenged an arbitral award dated 30 June 2005 under Section 34 of the Arbitration and Conciliation Act, 1996. The dispute arose from a contract for a crude distribution system awarded to the respondent, Artson Engineering Ltd., in February 1998. The contract was governed by General and Special Conditions of Contract. The respondent claimed that delays were caused by the petitioner and its consultant, Engineers India Ltd., and sought damages. The sole arbitrator allowed some claims, awarding Rs. 1,23,00,000 with interest at 18% per annum. The petitioner argued that the award was contrary to public policy and perverse, particularly regarding delay findings and interest rate. The court held that the arbitrator's findings on delay were based on evidence and not perverse, as the petitioner had contributed to delays. However, the court found the interest rate of 18% excessive and reduced it to 9% per annum, modifying the award accordingly. The petition was partly allowed.
Headnote
A) Arbitration Law - Challenge to Arbitral Award under Section 34 - Public Policy - Perversity - The court examined whether the arbitral award was contrary to public policy or perverse. Held that the arbitrator's findings on delay and damages were based on evidence and not perverse; the court cannot re-appreciate evidence under Section 34. (Paras 1-10) B) Contract Law - Delay in Performance - Liquidated Damages - The court considered whether the respondent was responsible for delay and whether the petitioner was entitled to liquidated damages. Held that the arbitrator's finding that the petitioner contributed to delay was plausible and not perverse. (Paras 11-20) C) Interest - Award of Interest at 18% - Section 31(7)(a) of Arbitration and Conciliation Act, 1996 - The court held that the arbitrator's award of interest at 18% per annum was excessive and reduced it to 9% per annum, as the rate was not justified by the circumstances. (Paras 21-30)
Issue of Consideration
Whether the arbitral award dated 30 June 2005 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of being contrary to public policy, perverse, or patently illegal.
Final Decision
The petition is partly allowed. The arbitral award is modified to the extent that the rate of interest is reduced from 18% per annum to 9% per annum. The rest of the award is upheld.
Law Points
- Section 34 of Arbitration and Conciliation Act
- 1996
- Public policy
- Perversity
- Interest rate
- Contract interpretation
- Delay damages




