Case Note & Summary
The case involves special leave petitions filed by original claimants (landowners) challenging a common judgment dated 2.4.1996 of the Allahabad High Court in First Appeal No. 919/1993 and allied appeals, which reduced compensation for land acquired in villages Gulsitapur and Tilpta under the Land Acquisition Act. The notification under Section 4 was issued in 1985, possession taken in January 1987, and the Land Acquisition Officer awarded compensation at Rs.8-10 per square yard in 1988. On reference under Section 18, the Reference Court enhanced compensation to Rs.30 per square yard on 22.3.1993. However, the High Court reduced it to Rs.22-20 per square yard. After approximately 21 years, the petitioners filed special leave petitions in 2017, claiming compensation at Rs.65 per square yard, relying on a subsequent decision for village Kasna (notification in 1989). The petitioners sought condonation of delay of 7534, 7542, and 7886 days. The Supreme Court heard arguments on the delay issue. The petitioners argued that they were entitled to fair compensation and that delay should not defeat their rights, citing decisions in Market Committee, Hodal v. Krishan Murari, Dhiraj Singh v. State of Haryana, and K. Subbarayudu v. Special Deputy Collector. The respondents (UPSIDC and Greater Noida Industrial Development Authority) opposed, arguing that the delay was inordinate, no sufficient cause was shown, the lands were not comparable, and reopening the judgment would have a cascading effect. The Supreme Court held that the petitioners failed to make out a case for condonation of the huge delay of approximately 21 years. The only explanation was that they came to know about the enhanced compensation for village Kasna in January 2017. The Court found this insufficient and dismissed the applications for condonation of delay and the special leave petitions as barred by limitation.
Headnote
A) Limitation - Condonation of Delay - Sufficient Cause - Land Acquisition Compensation - The petitioners sought condonation of a 21-year delay in filing special leave petitions challenging a 1996 High Court judgment on compensation. The Supreme Court held that no sufficient cause was shown, and the delay was inordinate, warranting dismissal of the petitions. (Paras 3-10) B) Land Acquisition - Compensation - Parity - The petitioners claimed compensation at par with another village (Kasna) acquired four years later. The Court noted that the lands were not comparable and the delay was unexplained, rejecting the claim for parity. (Paras 4-7) C) Limitation - Acquiescence - The Court observed that the petitioners had accepted the compensation and did not challenge the High Court judgment for 21 years, indicating acquiescence. (Para 5.4)
Issue of Consideration
Whether the inordinate delay of approximately 21 years in filing the special leave petitions should be condoned.
Final Decision
The Supreme Court dismissed the applications for condonation of delay and consequently dismissed the special leave petitions as barred by limitation.
Law Points
- Condonation of delay
- Sufficient cause
- Inordinate delay
- Land acquisition compensation
- Limitation



