Case Note & Summary
The judgment concerns two writ petitions filed by landowners challenging the acquisition of their lands for the Waghur Project in Jalgaon, Maharashtra. The petitioners sought to quash notifications under Sections 4 and 6 of the Land Acquisition Act, 1894, and the subsequent award. The acquisition process began in 1995-1996 with the issuance of Section 4 notifications, followed by Section 6 declarations and an award in 1998. The petitioners participated in the award proceedings and accepted compensation without any protest. They filed the writ petitions in 2014 and 2015, nearly 20 years after the initiation of acquisition. The court framed the issue of whether such belated challenges are maintainable. The petitioners argued that the acquisition was for a public purpose but the project was not implemented, and that the compensation was inadequate. The respondents contended that the petitions were barred by delay and laches, and that the petitioners had acquiesced by accepting compensation. The court analyzed the facts and held that the petitioners had slept over their rights for an inordinate period and had accepted the benefits of the award without protest. The court also noted that the petitioners had an alternative remedy under Section 18 of the Act to seek higher compensation, which they did not avail. Relying on principles of delay and laches and acquiescence, the court dismissed both writ petitions, holding that the challenge was not maintainable after such a long delay and after accepting compensation.
Headnote
A) Land Acquisition - Delay and Laches - Challenge to Acquisition After 20 Years - Petitioners challenged notifications under Sections 4 and 6 of the Land Acquisition Act, 1894 and the award after accepting compensation without protest - Held that the challenge is barred by delay and laches as the petitioners slept over their rights for nearly two decades and accepted the benefits of the award (Paras 1-10). B) Land Acquisition - Acquiescence - Acceptance of Compensation Without Protest - Petitioners participated in the award proceedings and received compensation without any objection - Held that by accepting compensation, they acquiesced to the acquisition and cannot later challenge the same (Paras 1-10). C) Land Acquisition - Maintainability of Writ Petition - Alternative Remedy - Petitioners could have sought reference under Section 18 of the Land Acquisition Act, 1894 for higher compensation but did not - Held that writ jurisdiction under Article 226 is not a substitute for statutory remedies and the petitions are not maintainable (Paras 1-10).
Issue of Consideration
Whether the writ petitions challenging the land acquisition proceedings initiated in 1995-1996 are maintainable after the petitioners accepted compensation without protest and after a delay of about 20 years.
Final Decision
Both writ petitions are dismissed. The challenge to the land acquisition proceedings is barred by delay and laches and the petitioners have acquiesced by accepting compensation without protest.
Law Points
- Delay and laches
- Acquiescence
- Estoppel by acceptance of compensation
- Limitation for challenging land acquisition
- Section 4 notification
- Section 6 declaration
- Section 11 award
- Section 12 notice
- Section 18 reference
- Section 31 payment of compensation




