Bombay High Court Partially Sets Aside Arbitral Award in Construction Dispute — Award of Interest on Interest and Pendente Lite Interest on Mobilisation Advance Held Contrary to Contract. The court found patent illegality in the award of compound interest and interest on mobilisation advance beyond contractual terms, and remitted counter claims for fresh consideration.

High Court: Bombay High Court Bench: BOMBAY
  • 103
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, M/s P.N. Writer & Co. Pvt. Ltd., challenged an arbitral award dated 13 February 2012 under Section 34 of the Arbitration and Conciliation Act, 1996. The dispute arose from a construction contract for extension of a warehouse at Vandalur, Tamil Nadu, where the respondent, M/s Mesuka Engineering Co. Pvt. Ltd., was the contractor. The contract was for Rs. 2,12,45,500 with a completion date of 31 December 2006. The respondent abandoned work in August/September 2007, leading to disputes. A winding up petition was filed, and by order dated 23 September 2009, the High Court referred all disputes to arbitration. The arbitrator allowed some claims of the respondent and rejected the petitioner's counter claims. The petitioner challenged the award on grounds of patent illegality, specifically the award of interest on interest and pendente lite interest on mobilisation advance, and the rejection of counter claims. The court held that the award of interest on interest was not permissible under the contract and amounted to patent illegality. The award of pendente lite interest on mobilisation advance was contrary to the express terms of the contract. The rejection of counter claims was set aside and remitted for fresh consideration. The petition was partly allowed.

Headnote

A) Arbitration Act - Section 34 - Setting Aside Award - Public Policy - Patent Illegality - The court examined whether the arbitral award granting interest on interest and pendente lite interest on mobilisation advance was contrary to the contract and law. Held that the award of interest on interest was not permissible under the contract and amounted to patent illegality, and the award of pendente lite interest on mobilisation advance was contrary to the express terms of the contract. (Paras 1-30)

B) Arbitration Act - Section 31(7)(a) - Interest - Award of Interest on Interest - The arbitrator awarded interest on the amount of interest already accrued, which was not provided for in the contract. Held that such award is contrary to the public policy of India and liable to be set aside. (Paras 15-20)

C) Arbitration Act - Section 34 - Counter Claims - Rejection Without Consideration - The arbitrator rejected the counter claims of the petitioner without properly considering the evidence and submissions. Held that the rejection of counter claims was not sustainable and the matter was remitted for fresh consideration. (Paras 25-30)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award granting interest on interest and pendente lite interest on mobilisation advance is contrary to the terms of the contract and the law, and whether the rejection of counter claims without proper consideration is sustainable.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is partly allowed. The impugned award is set aside to the extent of award of interest on interest and pendente lite interest on mobilisation advance. The rejection of counter claims is set aside and the matter is remitted to the arbitrator for fresh consideration of counter claims. The rest of the award is upheld.

Law Points

  • Arbitral award can be set aside if it is in conflict with the public policy of India
  • including patent illegality appearing on the face of the award
  • Arbitrator cannot award interest on interest unless contract provides
  • Pendente lite interest on mobilisation advance cannot be awarded when contract stipulates interest only after specified period
  • Counter claims cannot be rejected without considering evidence
  • Section 34 of Arbitration and Conciliation Act
  • 1996
  • Section 31(7)(a) of Arbitration and Conciliation Act
Subscribe to unlock Law Points Subscribe Now

Case Details

2015:BHC-OS:10428

Arbitration Petition No.724 of 2012

2015-08-13

R.D. Dhanuka, J.

2015:BHC-OS:10428

Mr.Gautam Ankhad with Ms.Nishitha Mohanty i/b Ms.Uma Wagle for the Petitioner; Mr.Ashish Kamat with Ms.Manorama Mohanty with Mr.A.P. Singh i/b S.K. Srivastav & Co. for the Respondent

M/s.P.N. Writer & Co. Pvt. Ltd.

M/s.Mesuka Engineering Co. Pvt. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside part of an arbitral award.

Remedy Sought

The petitioner sought to set aside the arbitral award to the extent it allowed claims of the respondent and rejected counter claims of the petitioner.

Filing Reason

The petitioner challenged the award on grounds of patent illegality, including award of interest on interest and pendente lite interest on mobilisation advance contrary to contract, and rejection of counter claims without proper consideration.

Previous Decisions

The High Court by order dated 23 September 2009 referred all disputes to arbitration and directed the petitioner to deposit Rs. 50 lacs.

Issues

Whether the arbitral award granting interest on interest is contrary to the contract and law? Whether the award of pendente lite interest on mobilisation advance is contrary to the contract? Whether the rejection of counter claims by the arbitrator is sustainable?

Submissions/Arguments

Petitioner argued that the award of interest on interest was not permissible under the contract and amounted to patent illegality. Petitioner argued that the award of pendente lite interest on mobilisation advance was contrary to the express terms of the contract. Petitioner argued that the arbitrator rejected counter claims without considering evidence and submissions. Respondent argued that the award was within the arbitrator's discretion and not contrary to law.

Ratio Decidendi

An arbitral award can be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 if it is in conflict with the public policy of India, including patent illegality appearing on the face of the award. The arbitrator cannot award interest on interest unless the contract provides for it. Pendente lite interest on mobilisation advance cannot be awarded when the contract stipulates interest only after a specified period. Counter claims cannot be rejected without proper consideration of evidence.

Judgment Excerpts

By this petition filed under section 34 of the Arbitration & Conciliation Act, 1996, the petitioner has impugned part of the arbitral award dated 13th February, 2012 read with corrigendum dated 3rd March, 2012, allowing some of the claims made by the respondent and rejecting the counter claims made by the petitioner. The award of interest on interest is not permissible under the contract and amounts to patent illegality. The award of pendente lite interest on mobilisation advance is contrary to the express terms of the contract.

Procedural History

The respondent filed a winding up petition against the petitioner under the Companies Act, 1956. On 23 September 2009, the High Court referred all disputes to arbitration and directed the petitioner to deposit Rs. 50 lacs. The arbitrator made an award on 13 February 2012, which was corrected by corrigendum on 3 March 2012. The petitioner filed this petition under Section 34 of the Arbitration Act on 13 August 2015.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34, 31(7)(a)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Partially Sets Aside Arbitral Award in Construction Dispute — Award of Interest on Interest and Pendente Lite Interest on Mobilisation Advance Held Contrary to Contract. The court found patent illegality in the award of compound i...
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging Eviction of Unauthorised Occupant from Railway Land. Section 5A of the Public Premises (Eviction of Unauthorised Occupants) Act, 1971 applies to pre-existing unauthorised constructions as it is procedu...