Bombay High Court Allows Contractor's Appeal in ONGC Arbitration Dispute Over Conversion Rate for Reimbursement of Spares and Consumables. Court Holds That Arbitral Tribunal's Determination of Conversion Rate Was Not Patently Illegal and Did Not Warrant Interference Under Section 34 of the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 41
Judgement Image
Font size:
Print

Case Note & Summary

The case involves two appeals arising from a common order dated 19 September 2005 passed by a learned Single Judge of the Bombay High Court under Section 34 of the Arbitration and Conciliation Act, 1996. The order set aside the findings of an arbitral tribunal on one specific issue pertaining to the rate of conversion to be adopted in respect of a claim for reimbursement of costs of spares and consumables. The appellant, Oil and Natural Gas Corporation Ltd. (ONGC), had entered into an agreement dated 10 November 1993 with the respondent, Dolphin Offshore Enterprises (I) Ltd. (Contractor), for operation and management of marine and diving services on board ONGC's vessel 'MSV SAMUDRA PRABHA'. Under the contract, the contractor was required to provide consumables and spares and undertake repairs with ONGC's approval. The contract was performed, but disputes arose, including a claim for costs of material. The arbitral tribunal passed an award, which ONGC challenged under Section 34. The Single Judge set aside the tribunal's finding on the conversion rate. Both parties appealed: ONGC in Appeal No.1079 of 2005 and Dolphin in Appeal No.29 of 2006. The Division Bench of the High Court, comprising Chief Justice Mohit S. Shah and Justice A.K. Menon, heard the appeals. The court examined the scope of interference under Section 34, noting that the arbitral tribunal's determination of the conversion rate was based on a plausible interpretation of the contract and evidence. The court held that the Single Judge erred in interfering with the tribunal's finding as it did not suffer from patent illegality. The court allowed Dolphin's appeal (Appeal No.29 of 2006) and set aside the Single Judge's order to the extent it set aside the tribunal's finding on the conversion rate. ONGC's appeal (Appeal No.1079 of 2005) was dismissed. The court restored the arbitral award on that issue.

Headnote

A) Arbitration Law - Section 34 of the Arbitration and Conciliation Act, 1996 - Scope of Interference - Patent Illegality - The court considered whether the arbitral tribunal's determination of the conversion rate for reimbursement of costs of spares and consumables was patently illegal. The court held that the tribunal's decision was based on a plausible interpretation of the contract and evidence, and did not fall within the narrow grounds of patent illegality under Section 34. The Single Judge's interference was not warranted. (Paras 2-5)

B) Contract Law - Reimbursement of Costs - Conversion Rate - The dispute pertained to the rate of conversion to be adopted for reimbursement of costs of spares and consumables under a contract between ONGC and Dolphin Offshore. The arbitral tribunal adopted a particular rate, which was challenged. The court held that the tribunal's finding was a reasonable interpretation of the contract terms and did not suffer from any error apparent on the face of the record. (Paras 3-4)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned Single Judge was justified in setting aside the arbitral tribunal's finding on the rate of conversion to be adopted in respect of the claim for reimbursement of costs of spares and consumables under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Division Bench allowed Dolphin's appeal (Appeal No.29 of 2006) and set aside the Single Judge's order to the extent it set aside the arbitral tribunal's finding on the conversion rate. ONGC's appeal (Appeal No.1079 of 2005) was dismissed. The arbitral award on that issue was restored.

Law Points

  • Arbitration and Conciliation Act
  • 1996
  • Section 34
  • Scope of interference with arbitral award
  • Patent illegality
  • Conversion rate determination
  • Reimbursement of costs
Subscribe to unlock Law Points Subscribe Now

Case Details

2015 LawText (BOM) (07) 76

Appeal No.1079 of 2005 in Arbitration Petition No.195 of 2002 and Appeal No.29 of 2006 in Arbitration Petition No.195 of 2002

2015-07-31

Mohit S. Shah, C.J., A.K. Menon, J.

Mr. Pankaj Savant, Senior Advocate with Mr. Hemant Prabhulkar and Ms. Sonali Jain i/b Juris Consultus for the Appellant in Appeal No.1079/2005 and Respondent in Appeal No.29/2006; Mr. V.K. Ramabhadran, Senior Advocate with Mr. Subra Karmarkar for the Respondent in Appeal No.1079/2005 and Appellant in Appeal No.29/2006 & Appeal No.31/2006

Oil and Natural Gas Corporation Ltd. (in Appeal No.1079/2005); Dolphin Offshore Enterprises (I) Ltd. (in Appeal No.29/2006)

Dolphin Offshore Enterprises (I) Ltd. (in Appeal No.1079/2005); Oil and Natural Gas Corporation Ltd. (in Appeal No.29/2006)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeals against an order under Section 34 of the Arbitration and Conciliation Act, 1996 setting aside part of an arbitral award.

Remedy Sought

ONGC sought to uphold the Single Judge's order setting aside the arbitral tribunal's finding on conversion rate; Dolphin sought to restore the tribunal's finding.

Filing Reason

Dispute over the rate of conversion to be adopted for reimbursement of costs of spares and consumables under a contract between ONGC and Dolphin.

Previous Decisions

Arbitral tribunal passed an award; Single Judge set aside the tribunal's finding on conversion rate under Section 34.

Issues

Whether the learned Single Judge was justified in setting aside the arbitral tribunal's finding on the rate of conversion for reimbursement of costs of spares and consumables under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

ONGC argued that the arbitral tribunal's finding on conversion rate was patently illegal and the Single Judge correctly set it aside. Dolphin argued that the tribunal's finding was based on a plausible interpretation of the contract and evidence, and the Single Judge exceeded the scope of Section 34.

Ratio Decidendi

The arbitral tribunal's determination of the conversion rate for reimbursement of costs of spares and consumables was based on a plausible interpretation of the contract and evidence, and did not suffer from patent illegality. The scope of interference under Section 34 of the Arbitration and Conciliation Act, 1996 is narrow, and the Single Judge erred in setting aside the tribunal's finding.

Judgment Excerpts

The order impugned in these appeals dated 19.9.2005 is passed by a learned Single Judge of this Court under section 34 of the Arbitration and Conciliation Act, 1996, setting aside the findings of the arbitral tribunal on one specific issue pertaining to rate of conversion to be adopted in respect of claim for reimbursement of costs of spares and consumables. The brief facts which led to passing of the arbitral award and subsequent challenge under section 34 of the Arbitration and Conciliation Act are as under :

Procedural History

The arbitral tribunal passed an award. ONGC challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 before a learned Single Judge of the Bombay High Court. The Single Judge set aside the tribunal's finding on the conversion rate. Both parties appealed: ONGC in Appeal No.1079 of 2005 and Dolphin in Appeal No.29 of 2006. The Division Bench heard the appeals and delivered a common judgment on 31 July 2015.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Upholds Life Imprisonment for Doctor in Wife's Murder Case — Circumstantial Evidence Sufficient to Prove Guilt Beyond Reasonable Doubt. The court held that the chain of circumstances including last seen, motive, and recovery of we...
Related Judgement
High Court Bombay High Court Allows Contractor's Appeal in ONGC Arbitration Dispute Over Conversion Rate for Reimbursement of Spares and Consumables. Court Holds That Arbitral Tribunal's Determination of Conversion Rate Was Not Patently Illegal and Did Not Warr...