High Court of Bombay at Nagpur Partly Allows Appeal by Employer in Arbitration Matter — Reduces Interest Rate from 18% to 12% per annum. The court upheld the arbitral award on merits but modified the interest component, holding that 18% interest was excessive under Section 29 of the Arbitration Act, 1940.

High Court: Bombay High Court Bench: NAGPUR
  • 75
Judgement Image
Font size:
Print

Case Note & Summary

The appellants, Central Mine Planning & Design Institute Ltd., a Union of India undertaking, had invited tenders for construction work. The respondent, M/s Anupam Rai, a registered partnership firm, submitted an offer and an agreement was entered into on 24-4-1986. The work was to be completed within 12 months from 10-4-1986 to 9-4-1987. The work could not be completed within the stipulated period and time was extended twice via communications dated 14-5-1987 and 14-12-1987. The work was completed on 31-1-1988. Disputes arose between the parties, and the respondent sought appointment of an arbitrator in terms of the agreement. By order dated 20-12-1995, the Civil Court directed the appellants to file the arbitration agreement and appointed a sole arbitrator. The arbitrator made his award on 30-6-1997, holding that the respondent was entitled to a total amount of Rs. 6,50,000 with interest at 18% per annum from the date of the award till realization. The appellants challenged the award in Special Civil Suit No.67/1992, which was dismissed by judgment dated 23-4-1998, making the award rule of the court. The appellants then filed the present appeal under Section 39 of the Arbitration Act, 1940. The main legal issues were whether the arbitrator exceeded jurisdiction, failed to consider counterclaims, and awarded excessive interest. The appellants argued that the arbitrator ignored the terms of the contract and awarded amounts not claimed. The respondent contended that the award was final and not liable to be interfered with. The court analyzed the scope of appeal under Section 39, holding that it is limited and findings of fact by the arbitrator are not open to reappraisal unless perverse. The court found that the arbitrator had considered the counterclaim and rejected it on merits. Regarding interest, the court held that while the arbitrator had discretion, the rate of 18% per annum was excessive and reduced it to 12% per annum from the date of award till realization. The appeal was partly allowed, modifying the interest rate.

Headnote

A) Arbitration Law - Appeal against decree making award rule of court - Section 39, Arbitration Act, 1940 - Scope of interference - The court held that an appeal under Section 39 is not an appeal against the award itself but against the judgment making it rule of court; interference is limited to grounds such as misconduct, error of law apparent on face, or jurisdictional error. The arbitrator's findings on facts and quantification of claims are final and not open to reappraisal unless perverse. (Paras 1-10)

B) Arbitration Law - Interest - Award of interest at 18% per annum - Section 29, Arbitration Act, 1940 - The court reduced the rate of interest from 18% to 12% per annum from the date of award till realization, holding that 18% was excessive in the facts and circumstances, though the arbitrator had discretion to award interest. (Paras 11-15)

C) Arbitration Law - Counterclaim - Failure to consider counterclaim - Section 30, Arbitration Act, 1940 - The court found that the arbitrator had considered the counterclaim and rejected it on merits; no ground to interfere as the arbitrator's decision on counterclaim is a finding of fact. (Paras 16-18)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the judgment of the trial court making the arbitral award rule of the court is liable to be set aside on the grounds raised by the appellants, including that the arbitrator exceeded jurisdiction, failed to consider counterclaims, and awarded excessive interest.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is partly allowed. The judgment of the trial court making the award rule of court is modified to the extent that the rate of interest awarded by the arbitrator at 18% per annum from the date of award till realization is reduced to 12% per annum. The rest of the award is upheld.

Law Points

  • Arbitration Act 1940
  • Section 39
  • scope of appeal
  • interference with arbitral award
  • interest rate
  • perversity
  • findings of fact
Subscribe to unlock Law Points Subscribe Now

Case Details

2015 LawText (BOM) (05) 57

First Appeal No.178 of 1998

2015-05-08

A.S. Chandurkar, J

Shri C. S. Samudra Advocate for the appellants, Shri A. S. Jaiswal Senior Advocate with Shri Shantanu Khedkar Advocate for the respondent

Central Mine Planning & Design Institute Ltd.

M/s Anupam Rai

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 39 of the Arbitration Act, 1940 against judgment making arbitral award rule of court.

Remedy Sought

Appellants sought to set aside the judgment dated 23-4-1998 in Special Civil Suit No.67/1992 making the award rule of court.

Filing Reason

Appellants challenged the award on grounds that arbitrator exceeded jurisdiction, failed to consider counterclaims, and awarded excessive interest.

Previous Decisions

The trial court dismissed the objections and made the award rule of court on 23-4-1998.

Issues

Whether the arbitrator exceeded his jurisdiction in awarding amounts not claimed or contrary to contract terms. Whether the arbitrator failed to consider the counterclaim of the appellants. Whether the rate of interest at 18% per annum awarded by the arbitrator is excessive and liable to be reduced.

Submissions/Arguments

Appellants argued that the arbitrator ignored the terms of the contract and awarded amounts not claimed, and failed to consider the counterclaim. Respondent contended that the award is final and not liable to be interfered with, and the arbitrator had discretion to award interest.

Ratio Decidendi

In an appeal under Section 39 of the Arbitration Act, 1940, the court's interference is limited to grounds such as misconduct, error of law apparent on face, or jurisdictional error. Findings of fact by the arbitrator are final and not open to reappraisal unless perverse. The arbitrator has discretion to award interest, but the rate must be reasonable; 18% per annum was held excessive and reduced to 12%.

Judgment Excerpts

The appellants in the present appeal filed under Section 39 of the Arbitration Act 1940 have challenged the judgment dated 23-4-1998 in Special Civil Suit No.67/1992 whereby the award made by the Arbitrator was made rule of the Court. The court held that the arbitrator's findings on facts and quantification of claims are not open to reappraisal in appeal under Section 39 of the Arbitration Act, 1940, unless perverse or contrary to law. The court reduced the rate of interest from 18% to 12% per annum from the date of award till realization, holding that 18% was excessive.

Procedural History

The respondent filed a claim before the arbitrator. The arbitrator made an award on 30-6-1997. The appellants filed objections in Special Civil Suit No.67/1992, which were dismissed on 23-4-1998, making the award rule of court. The appellants then filed the present First Appeal No.178 of 1998 under Section 39 of the Arbitration Act, 1940.

Acts & Sections

  • Arbitration Act, 1940: Section 29, Section 30, Section 39
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay at Nagpur Partly Allows Appeal by Employer in Arbitration Matter — Reduces Interest Rate from 18% to 12% per annum. The court upheld the arbitral award on merits but modified the interest component, holding that 18% interest wa...
Related Judgement
High Court Bombay High Court Upholds Dismissal of Conductor in MSRTC Ticketless Travel Case — No Interference with Industrial Court's Revision Order. The court held that allowing 18 passengers to travel without tickets constitutes serious misconduct warrantin...