Bombay High Court Dismisses Developer's Petition for Interim Relief Under Section 9 of Arbitration Act — Dispute Over Possession of Flats for Redevelopment Not Arbitrable as Members Not Bound by Development Agreement. The court held that interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, cannot be granted against persons who are not parties to the arbitration agreement, and the members of the society were not bound by the arbitration clause in the development agreement.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 13
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Shri Krishan Sai Development Corporation, filed an Arbitration Petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim reliefs including appointment of a receiver and possession of Flat Nos. 404 and 202 from respondent nos. 2 and 3, who were members of respondent no. 1 society. The petitioner had entered into a development agreement with the society for redevelopment of the property, which contained an arbitration clause. However, respondent nos. 2 and 3 were not parties to that agreement. The court examined whether interim relief under Section 9 could be granted against persons who are not parties to the arbitration agreement. The court noted that the arbitration clause only bound the petitioner and the society, and respondent nos. 2 and 3, as members, were not signatories and did not claim through the society. The court held that the petition was not maintainable against them as there was no arbitration agreement between the petitioner and respondent nos. 2 and 3. Consequently, the court dismissed the petition, leaving the petitioner to pursue other remedies available in law.

Headnote

A) Arbitration - Interim Relief under Section 9 - Maintainability - The petitioner sought appointment of receiver and possession of flats from respondent nos. 2 and 3, who were not parties to the development agreement containing the arbitration clause - The court held that interim relief under Section 9 can only be granted against a party to the arbitration agreement or a person claiming through such party - Since respondent nos. 2 and 3 were not signatories to the agreement and did not claim through the society, the petition was not maintainable against them (Paras 1-34).

B) Arbitration - Parties to Arbitration Agreement - Third Party - The development agreement was between the petitioner and the society only - Respondent nos. 2 and 3, as members of the society, were not bound by the arbitration clause in the absence of any specific agreement or statutory provision making them parties - The court held that the arbitration clause cannot be enforced against non-signatory members (Paras 2-34).

C) Arbitration - Interim Relief - Possession of Property - The petitioner sought possession of flats for redevelopment, but the dispute regarding possession was not covered by the arbitration agreement as the members were not parties - The court held that no interim relief could be granted under Section 9 as the main arbitration itself was not maintainable against respondent nos. 2 and 3 (Paras 1-34).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, seeking possession of flats from respondent nos. 2 and 3, who are members of the society but not parties to the development agreement containing the arbitration clause.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court dismissed the Arbitration Petition, holding that the petition under Section 9 of the Arbitration and Conciliation Act, 1996 is not maintainable against respondent nos. 2 and 3 as they are not parties to the arbitration agreement. The petitioner is at liberty to take such other remedies as may be available in law.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • interim relief
  • arbitrability
  • parties to arbitration agreement
  • third party
  • redevelopment agreement
  • cooperative society
  • member's rights
Subscribe to unlock Law Points Subscribe Now

Case Details

2015 LawText (BOM) (05) 37

Arbitration Petition No. 852 of 2014

2015-05-08

S.J. Kathawalla, J.

Mr. M.M. Vashi, Senior Advocate, instructed by M/s. M.P. Vashi & Associates, for the Petitioner; Mr. Vijay Patil, instructed by Mr. Nitesh Bhutekar, for Respondent No. 1; Mr. Vishal Kanade, instructed by Mr. D.S. Patil, for Respondent Nos. 2 and 3

Shri Krishan Sai Development Corporation

Young Men's Progressive Cooperative Society Limited and Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim reliefs including appointment of receiver and possession of flats.

Remedy Sought

Petitioner sought appointment of Court Receiver to take possession of Flat Nos. 404 and 202 from respondent nos. 2 and 3, and handover possession to petitioner for demolition and redevelopment; alternatively, mandatory order directing respondent nos. 2 and 3 to handover vacant possession.

Filing Reason

Petitioner claimed that respondent nos. 2 and 3 were obstructing redevelopment of the property by refusing to handover possession of their flats, despite a development agreement between petitioner and the society containing an arbitration clause.

Issues

Whether the petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996 against respondent nos. 2 and 3 who are not parties to the arbitration agreement. Whether the arbitration clause in the development agreement between the petitioner and the society binds the members of the society.

Submissions/Arguments

Petitioner argued that respondent nos. 2 and 3, as members of the society, are bound by the development agreement and the arbitration clause, and interim relief should be granted to facilitate redevelopment. Respondent nos. 2 and 3 contended that they are not parties to the development agreement and the arbitration clause does not bind them; therefore, the petition under Section 9 is not maintainable against them.

Ratio Decidendi

Interim relief under Section 9 of the Arbitration and Conciliation Act, 1996 can only be granted against a party to the arbitration agreement or a person claiming through such party. Since respondent nos. 2 and 3 were not signatories to the development agreement containing the arbitration clause and did not claim through the society, the petition was not maintainable against them.

Judgment Excerpts

The above Arbitration Petition is filed by the Petitioner ... under Section 9 of the Arbitration and Conciliation Act, 1996 ... The relevant facts for deciding the present Petition, are briefly set out hereunder : The court held that the petition is not maintainable against respondent nos. 2 and 3.

Procedural History

The petitioner filed Arbitration Petition No. 852 of 2014 under Section 9 of the Arbitration and Conciliation Act, 1996 in the High Court of Judicature at Bombay. The court reserved order on 3rd February, 2015 and pronounced judgment on 8th May, 2015.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Developer's Petition for Interim Relief Under Section 9 of Arbitration Act — Dispute Over Possession of Flats for Redevelopment Not Arbitrable as Members Not Bound by Development Agreement. The court held that interim re...
Related Judgement
High Court Bombay High Court Allows Petition Against Customs for Demurrage Charges Due to Delay in Assessment. Customs Department Directed to Bear Warehousing Charges for Inordinate Delay in Finalising Assessment of Imported Goods.