High Court of Bombay Upholds Arbitral Award in Favor of Contractor in Railway Contract Dispute — Extension of Time Granted Without Protest Bars Claim for Liquidated Damages and Interest on Delayed Payments is Allowed Under Interest Act, 1978.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 115
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Union of India, acting through the Chief Electrical Engineer (Construction), Central Railway, awarded a contract to the respondent, M/s Bright Power Project (I) Pvt. Ltd., on 15 July 1997 for design, supply, and erection of OHE in Koparkhairane-Turbhe-Vashi-Nerul at a total cost of Rs.2,32,28,205/-. The original contractual period was 18 months, ending on 14 January 1999. Due to various reasons, the work could not be completed within the stipulated period and was ultimately completed in August 2004. The respondent applied for extensions of time from time to time, which were granted by the petitioner through several letters without any protest or reservation of the right to claim liquidated damages. On 14 July 2004, the respondent invoked the arbitration agreement, and the matter was referred to arbitration. The arbitral tribunal passed an award on 1 July 2008, allowing some of the respondent's claims, including interest on delayed payments, and rejecting the petitioner's counterclaim for liquidated damages. The petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, primarily on the grounds that the arbitrator had erred in allowing interest and in rejecting the counterclaim for liquidated damages. The court held that the scope of interference under Section 34 is limited and that the arbitrator's findings were not perverse or patently illegal. The court noted that the petitioner had granted extensions of time without protest, which amounted to a waiver of the right to claim liquidated damages. Regarding interest, the court held that the arbitrator was empowered to award interest under the Interest Act, 1978, and that the rate of 12% per annum was reasonable. The court dismissed the petition, upholding the arbitral award.

Headnote

A) Arbitration - Section 34 of Arbitration and Conciliation Act, 1996 - Scope of Interference - Court held that the scope of interference under Section 34 is limited to grounds of public policy, patent illegality, or perversity. The court cannot re-appreciate evidence or substitute its own view. (Paras 1-10)

B) Contract - Extension of Time - Waiver of Liquidated Damages - Where the employer grants extension of time without protest or reservation of right to claim liquidated damages, it amounts to waiver of the right to claim such damages. The arbitrator's finding that the petitioner had waived its right to claim liquidated damages was upheld. (Paras 11-20)

C) Interest - Interest Act, 1978 - Applicability to Arbitral Awards - The arbitrator is empowered to award interest for the pre-reference, pendente lite, and post-award periods. The award of interest at 12% per annum from the date of the award till payment was held to be in accordance with law. (Paras 21-30)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award granting claims for interest on delayed payments and rejecting the petitioner's counterclaim for liquidated damages is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed the petition and upheld the arbitral award dated 1 July 2008.

Law Points

  • Extension of time granted without protest amounts to waiver of right to claim liquidated damages
  • Interest Act
  • 1978 applies to arbitral awards
  • Section 34 of Arbitration and Conciliation Act
  • 1996 has limited scope of interference
Subscribe to unlock Law Points Subscribe Now

Case Details

2015 LawText (BOM) (04) 58

Arbitration Petition No.933 of 2013

2015-04-07

R.D. Dhanuka, J.

Mr. Suresh Kumar a/w Ms. Sangita Yadav for the petitioner/UOI, Mr. A.M. Vernekar a/w Mr. Samarth Pai for the respondent

Union of India, Acting through Chief Electrical Engineer (Construction), Central Railway, Mumbai CST, Mumbai

M/s Bright Power Project (I) Pvt. Ltd., 305, Creative Industrial Estate, Sunder Nagar, Road No.2, Kalina, Santacruz (E), Mumbai- 400 098

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

The petitioner sought to set aside the arbitral award dated 1 July 2008.

Filing Reason

The petitioner challenged the award on grounds that the arbitrator erred in allowing interest on delayed payments and in rejecting the petitioner's counterclaim for liquidated damages.

Previous Decisions

The arbitral tribunal passed an award on 1 July 2008 allowing some claims of the respondent and rejecting the petitioner's counterclaim.

Issues

Whether the arbitral award granting interest on delayed payments is liable to be set aside? Whether the arbitrator's rejection of the petitioner's counterclaim for liquidated damages is perverse or patently illegal?

Submissions/Arguments

The petitioner argued that the arbitrator erred in allowing interest on delayed payments as there was no provision in the contract for interest. The petitioner contended that the arbitrator wrongly rejected its counterclaim for liquidated damages despite delays attributable to the respondent. The respondent argued that the extensions of time were granted without protest, waiving the right to liquidated damages, and that interest was rightly awarded under the Interest Act, 1978.

Ratio Decidendi

The court held that the scope of interference under Section 34 of the Arbitration and Conciliation Act, 1996 is limited to grounds of public policy, patent illegality, or perversity. The arbitrator's findings that the petitioner had waived its right to claim liquidated damages by granting extensions without protest, and that the respondent was entitled to interest on delayed payments under the Interest Act, 1978, were not perverse or patently illegal. Therefore, the award was upheld.

Judgment Excerpts

By this petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short 'the said Arbitration Act'), the petitioner has impugned the arbitral award dated 1st July 2008 allowing some of the claims made by the respondent. It is not in dispute that the respondent vide various letters applied for extension of contractual period from time to time to the petitioner. The petitioner granted extension of time by various letters i.e. 21st January 2000, 29th June 2000, 20th October 2000, 10th May 2001, 19th March 2002, 29th July 2002, 24th February 2003 and 31st August 2004.

Procedural History

The respondent invoked arbitration on 14 July 2004. The matter was referred to arbitration, and the arbitral tribunal passed an award on 1 July 2008. The petitioner filed Arbitration Petition No.933 of 2013 under Section 34 of the Arbitration and Conciliation Act, 1996 before the High Court of Bombay, which was dismissed on 7 April 2015.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
  • Interest Act, 1978:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay Upholds Arbitral Award in Favor of Contractor in Railway Contract Dispute — Extension of Time Granted Without Protest Bars Claim for Liquidated Damages and Interest on Delayed Payments is Allowed Under Interest Act, 1978.
Related Judgement
High Court Bombay High Court Sets Aside Arbitral Award Dismissing Claims Under Section 25 of Arbitration Act for Lack of Notice. Arbitrator's Termination of Mandate Without Opportunity to Show Cause Held Patently Illegal and Against Public Policy.