Case Note & Summary
The case involves a dispute between M/s Adani Power (Mundra) Ltd. (appellant) and Gujarat Electricity Regulatory Commission and others (respondents), primarily Gujarat Urja Vikas Nigam Ltd. (GUVNL), the procurer. The appellant had entered into a Power Purchase Agreement (PPA) with GUVNL for supply of 1000 MW power at Rs. 2.35 per unit, following a competitive bidding process under Section 63 of the Electricity Act, 2003. The appellant claimed that its bid was based on an assurance from Gujarat Mineral Development Corporation (GMDC) to supply 4 million tonnes of coal, but GMDC failed to execute a Fuel Supply Agreement (FSA). After several communications and attempts at resolution, the appellant terminated the PPA on 28.12.2009, effective 04.01.2010, and deposited Rs. 25 crores as liquidated damages in addition to an existing performance bank guarantee of Rs. 75 crores. GUVNL filed a petition before the Gujarat Electricity Regulatory Commission under Sections 86(1)(f) and 95 of the Electricity Act, 2003, challenging the termination. The Commission held the termination illegal and directed the appellant to continue supply at the contracted rate. The Appellate Tribunal for Electricity affirmed this decision. The Supreme Court dismissed the appeal, holding that the PPA did not condition the supply of power on the execution of an FSA with GMDC; the appellant's obligation to arrange fuel was independent. The court further held that the presence of a liquidated damages clause did not preclude an order of specific performance, as the contract was capable of being performed and the appellant was the defaulting party. The court emphasized that termination clauses must be read in the context of the entire contract, including provisions for dispute resolution and specific performance. The appeal was dismissed with no order as to costs.
Headnote
A) Contract Law - Termination of Contract - Interpretation of PPA - The appellant terminated the PPA citing non-fulfillment of condition regarding fuel supply agreement with GMDC. The court held that the PPA did not make the supply of power conditional upon the execution of an FSA with GMDC; the obligation to arrange fuel was solely on the appellant. The termination was therefore illegal. (Paras 14-20) B) Electricity Law - Specific Performance - Liquidated Damages - Sections 86(1)(f), 95 Electricity Act, 2003 - The court held that the presence of a liquidated damages clause does not bar the grant of specific performance where the contract is otherwise capable of being performed and the defaulting party is the one seeking termination. The Commission and Appellate Tribunal rightly directed the appellant to continue supply at the contracted rate. (Paras 21-25) C) Contract Law - Reading Contract as a Whole - Articles 3.4.2, 14.1, 14.2 of PPA - The court held that termination clauses must be read in conjunction with the entire contract, including provisions for dispute resolution and specific performance. The appellant could not unilaterally terminate based on a condition not expressly made a condition precedent. (Paras 14-20)
Issue of Consideration
Whether the appellant was entitled to terminate the Power Purchase Agreement (PPA) on the ground that the Gujarat Mineral Development Corporation (GMDC) failed to execute a Fuel Supply Agreement (FSA), and whether the Commission and Appellate Tribunal could direct specific performance despite a liquidated damages clause.
Final Decision
The Supreme Court dismissed the appeal, holding that the termination of the PPA by the appellant was illegal. The court affirmed the orders of the Gujarat Electricity Regulatory Commission and the Appellate Tribunal for Electricity, directing the appellant to continue supply of power to the procurer at the rate determined in the PPA. No order as to costs.
Law Points
- Contractual interpretation
- Termination of contract
- Specific performance
- Liquidated damages
- Electricity Act
- 2003



