Supreme Court Dismisses Appeal by Power Generator Against Termination of PPA — Holds That Failure to Secure Fuel Supply Agreement Does Not Justify Termination Where PPA Does Not Condition Power Supply on Specific Coal Source

  • 10
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a dispute between M/s Adani Power (Mundra) Ltd. (appellant) and Gujarat Electricity Regulatory Commission and others (respondents), primarily Gujarat Urja Vikas Nigam Ltd. (GUVNL), the procurer. The appellant had entered into a Power Purchase Agreement (PPA) with GUVNL for supply of 1000 MW power at Rs. 2.35 per unit, following a competitive bidding process under Section 63 of the Electricity Act, 2003. The appellant claimed that its bid was based on an assurance from Gujarat Mineral Development Corporation (GMDC) to supply 4 million tonnes of coal, but GMDC failed to execute a Fuel Supply Agreement (FSA). After several communications and attempts at resolution, the appellant terminated the PPA on 28.12.2009, effective 04.01.2010, and deposited Rs. 25 crores as liquidated damages in addition to an existing performance bank guarantee of Rs. 75 crores. GUVNL filed a petition before the Gujarat Electricity Regulatory Commission under Sections 86(1)(f) and 95 of the Electricity Act, 2003, challenging the termination. The Commission held the termination illegal and directed the appellant to continue supply at the contracted rate. The Appellate Tribunal for Electricity affirmed this decision. The Supreme Court dismissed the appeal, holding that the PPA did not condition the supply of power on the execution of an FSA with GMDC; the appellant's obligation to arrange fuel was independent. The court further held that the presence of a liquidated damages clause did not preclude an order of specific performance, as the contract was capable of being performed and the appellant was the defaulting party. The court emphasized that termination clauses must be read in the context of the entire contract, including provisions for dispute resolution and specific performance. The appeal was dismissed with no order as to costs.

Headnote

A) Contract Law - Termination of Contract - Interpretation of PPA - The appellant terminated the PPA citing non-fulfillment of condition regarding fuel supply agreement with GMDC. The court held that the PPA did not make the supply of power conditional upon the execution of an FSA with GMDC; the obligation to arrange fuel was solely on the appellant. The termination was therefore illegal. (Paras 14-20)

B) Electricity Law - Specific Performance - Liquidated Damages - Sections 86(1)(f), 95 Electricity Act, 2003 - The court held that the presence of a liquidated damages clause does not bar the grant of specific performance where the contract is otherwise capable of being performed and the defaulting party is the one seeking termination. The Commission and Appellate Tribunal rightly directed the appellant to continue supply at the contracted rate. (Paras 21-25)

C) Contract Law - Reading Contract as a Whole - Articles 3.4.2, 14.1, 14.2 of PPA - The court held that termination clauses must be read in conjunction with the entire contract, including provisions for dispute resolution and specific performance. The appellant could not unilaterally terminate based on a condition not expressly made a condition precedent. (Paras 14-20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the appellant was entitled to terminate the Power Purchase Agreement (PPA) on the ground that the Gujarat Mineral Development Corporation (GMDC) failed to execute a Fuel Supply Agreement (FSA), and whether the Commission and Appellate Tribunal could direct specific performance despite a liquidated damages clause.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeal, holding that the termination of the PPA by the appellant was illegal. The court affirmed the orders of the Gujarat Electricity Regulatory Commission and the Appellate Tribunal for Electricity, directing the appellant to continue supply of power to the procurer at the rate determined in the PPA. No order as to costs.

Law Points

  • Contractual interpretation
  • Termination of contract
  • Specific performance
  • Liquidated damages
  • Electricity Act
  • 2003
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 lawtext (SC) (7) 112

Civil Appeal No. 11133 of 2011

2019-07-02

B.R. Gavai, J.

Mr. Gopal Jain, learned senior counsel for the appellant; Mr. M.G. Ramachandran, learned senior counsel for the respondent(s)

M/s Adani Power (Mundra) Ltd.

Gujarat Electricity Regulatory Commission and Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against judgment of Appellate Tribunal for Electricity dismissing appeal and confirming order of Gujarat Electricity Regulatory Commission holding termination of Power Purchase Agreement illegal.

Remedy Sought

Appellant sought setting aside of the Commission's order directing it to continue supply of power at contracted rate; respondent sought enforcement of PPA.

Filing Reason

Appellant terminated PPA citing failure of GMDC to execute Fuel Supply Agreement; respondent challenged termination before Commission.

Previous Decisions

Gujarat Electricity Regulatory Commission allowed petition of procurer holding termination illegal and directed appellant to supply power at contracted rate; Appellate Tribunal for Electricity dismissed appeal.

Issues

Whether the appellant was entitled to terminate the PPA on the ground that GMDC failed to execute an FSA? Whether the Commission and Appellate Tribunal could direct specific performance despite a liquidated damages clause?

Submissions/Arguments

Appellant: Bid was based on GMDC's commitment to supply coal; PPA conditions under Article 3.1.2 were not fulfilled due to GMDC's failure; termination was valid under Article 3.4.2; only liability was liquidated damages; specific performance cannot be ordered when liquidated damages provided. Respondent: PPA did not condition power supply on GMDC's coal supply; appellant's obligation to arrange fuel was independent; appellant defaulted by not arranging alternative source; termination by defaulting party is not permissible; liquidated damages clause does not bar specific performance.

Ratio Decidendi

The PPA did not make the supply of power conditional upon the execution of a Fuel Supply Agreement with GMDC; the obligation to arrange fuel was solely on the appellant. The presence of a liquidated damages clause does not bar the grant of specific performance where the contract is capable of being performed and the defaulting party is the one seeking termination. Termination clauses must be read in the context of the entire contract.

Judgment Excerpts

The main contention raised on behalf of the appellant is that the bid which was submitted by the appellant in respect of bid No. 2 was on the basis of the commitment given to it by the GMDC that it will supply the coal. Per contra, Mr. Ramachandran, learned senior counsel appearing on behalf of the procurer, would submit that the PPA which was entered into between the parties, was not executed on the basis of commitment by the GMDC. The court held that the termination of the PPA was illegal and directed the appellant herein to supply the power to the procurer at the rate determined in the PPA.

Procedural History

The procurer filed a petition under Sections 86(1)(f) and 95 of the Electricity Act, 2003 before the Gujarat Electricity Regulatory Commission on 01.02.2010. The Commission allowed the petition on 31.08.2010, holding termination illegal and directing supply. The appellant appealed to the Appellate Tribunal for Electricity, which dismissed the appeal on 07.09.2011. The appellant then filed the present civil appeal before the Supreme Court.

Acts & Sections

  • Electricity Act, 2003: Section 63, Section 86(1)(f), Section 95
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeal by Power Generator Against Termination of PPA — Holds That Failure to Secure Fuel Supply Agreement Does Not Justify Termination Where PPA Does Not Condition Power Supply on Specific Coal Source
Related Judgement
Supreme Court Supreme Court Dismisses Appellants' Appeal Against NCLAT Order Dismissing Time-Barred Appeal Under Companies Act, 2013 — Delay Beyond Condonable Limit Cannot Be Revived by Lockdown Extension Order. The Court held that the period of limitation for a...