Case Note & Summary
The petitioner, Punjab and Maharashtra Co-op. Bank Ltd., filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 6 September 2011 that rejected its claim against the respondents. The dispute arose from a counter guarantee issued by the bank in favour of the Export and Import Bank of India (EXIM Bank) to secure a performance guarantee for a sub-contract in Kuwait. The respondents had approached the bank for issuance of a counter guarantee in the sum of KD 1,20,245. The bank claimed that the respondents failed to reimburse the amount paid by the bank to EXIM Bank upon invocation of the guarantee. The arbitral tribunal rejected the claim on two primary grounds: first, that the claim was barred by limitation as the cause of action arose on 9 September 2002 when the guarantee was invoked, and the arbitration was commenced only in 2008; second, that the bank failed to prove that the guarantee was validly invoked within its validity period. The court, in its analysis, upheld the tribunal's findings, noting that the bank did not provide sufficient evidence to establish the date of invocation or that the invocation occurred within the guarantee's validity. The court also held that the award did not violate public policy and was not perverse. Consequently, the petition was dismissed, and the arbitral award was upheld.
Headnote
A) Arbitration - Challenge to Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - Limitation - The court considered whether the arbitral tribunal erred in holding that the claim was barred by limitation. The court upheld the tribunal's finding that the claim was filed beyond the period of limitation, as the cause of action arose on the date of invocation of the guarantee, and the arbitration was commenced after the expiry of three years. (Paras 10-15) B) Bank Guarantee - Invocation - Counter Guarantee - The court examined whether the petitioner-bank had proved valid invocation of the counter guarantee. The court held that the bank failed to prove that the guarantee was invoked within its validity period, and thus the claim was not maintainable. (Paras 16-20) C) Arbitration - Public Policy - Section 34 of Arbitration and Conciliation Act, 1996 - The court held that the arbitral award did not conflict with the public policy of India as the tribunal's findings were based on evidence and were not perverse. (Paras 21-25)
Issue of Consideration
Whether the arbitral award rejecting the petitioner-bank's claim for recovery under a counter guarantee is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996, on the grounds of being barred by limitation and for not proving valid invocation of the guarantee.
Final Decision
The court dismissed the arbitration petition and upheld the arbitral award dated 6 September 2011.
Law Points
- Limitation for arbitration claims
- Invocation of bank guarantee
- Counter guarantee
- Section 34 of Arbitration and Conciliation Act
- 1996
- Limitation Act
- 1963




