Bombay High Court Dismisses Contractor/Developer's Challenge to Majority Arbitral Award in Construction Dispute. Court upholds award of Rs.7,35,000, Rs.10,80,000, interest, and costs under Section 34 of the Arbitration and Conciliation Act, 1996, finding no patent illegality or conflict with public policy.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 165
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, M/s. Raviuday Construction Co., a partnership firm, challenged a majority arbitral award dated 15 May 2012 passed by a three-member arbitral tribunal. The dispute arose out of agreements between the petitioner (contractor/developer) and the respondent, Bhaktiyog Cooperative Housing Society Ltd., a cooperative housing society. The majority award directed the petitioner to pay the respondent Rs.7,35,000 towards the last installment, Rs.10,80,000 for excess FSI with 18% interest from 1 October 2007, Rs.25,00,572 as interest as per an annexed chart, Rs.9,73,753 towards construction of a community hall, and Rs.7,00,000 towards costs. The petitioner's counter claim was rejected. One arbitrator dissented, supporting the petitioner. The petitioner filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the award. The court examined the limited scope of interference under Section 34, which is confined to grounds of patent illegality or conflict with public policy. The court noted that the majority award was based on a plausible interpretation of the agreements and evidence on record. The dissenting opinion did not make the majority award perverse or unreasonable. The court held that the award of interest at 18% and costs of Rs.7,00,000 were within the tribunal's discretion and not patently illegal. The rejection of the counter claim was also upheld. Consequently, the court dismissed the arbitration petition, upholding the majority award.

Headnote

A) Arbitration Law - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Scope of Interference - The court considered the limited grounds for setting aside an arbitral award under Section 34, including patent illegality and conflict with public policy. The court held that the majority award was based on a plausible interpretation of the agreements and evidence, and the dissenting opinion did not render the majority award perverse. The court refused to interfere with the award. (Paras 1-10)

B) Arbitration Law - Interest and Costs - Section 31(7) of the Arbitration and Conciliation Act, 1996 - The arbitral tribunal awarded 18% interest on certain amounts and costs of Rs.7,00,000. The court held that the award of interest and costs was within the discretion of the tribunal and not patently illegal. (Paras 2-5)

C) Arbitration Law - Counter Claim - Rejection of Counter Claim - The tribunal rejected the respondent's counter claim. The court found no reason to interfere as the tribunal's decision was based on evidence. (Para 2)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the majority arbitral award dated 15 May 2012 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of patent illegality or being against public policy.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court dismissed the arbitration petition, upholding the majority arbitral award dated 15 May 2012.

Law Points

  • Arbitration and Conciliation Act
  • 1996
  • Section 34
  • Scope of interference
  • Patent illegality
  • Public policy
  • Majority award
  • Dissenting opinion
  • Interest rate
  • Costs
Subscribe to unlock Law Points Subscribe Now

Case Details

2015 LawText (BOM) (02) 58

Arbitration Petition No. 1200 of 2012

2015-02-10

Anoop V. Mohta, J.

Mr. Girish Godbole with Mr. Sumit Kothari i/by M/s. Jaykar & Partners for the Petitioner; Mr. A.M. Vernekar with Mr. Samarth Pai for the Respondent

M/s. Raviuday Construction Co.

Bhaktiyog Cooperative Housing Society Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to majority arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

Petitioner sought to set aside the majority arbitral award dated 15 May 2012.

Filing Reason

Petitioner challenged the award on grounds of patent illegality and being against public policy.

Previous Decisions

The arbitral tribunal passed a majority award on 15 May 2012, with one arbitrator dissenting.

Issues

Whether the majority arbitral award is patently illegal or against public policy warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Petitioner argued that the majority award was perverse and contrary to the terms of the agreements. Respondent supported the majority award, submitting that it was based on evidence and within the tribunal's jurisdiction.

Ratio Decidendi

The court held that the scope of interference under Section 34 of the Arbitration and Conciliation Act, 1996 is limited to cases of patent illegality or conflict with public policy. The majority award was based on a plausible interpretation of the agreements and evidence, and the dissenting opinion did not render it perverse. Therefore, the award was not liable to be set aside.

Judgment Excerpts

The PetitionerContractor/Developer, has challenged award dated 15 May 2012 passed by the Arbitral Tribunal as appointed by the consent, based upon the agreements between the parties. Two learned Arbitrator's majority award, is under challenge. The operative part of the majority award is as under: ...

Procedural History

The arbitral tribunal was constituted by consent. The majority award was passed on 15 May 2012. The petitioner filed Arbitration Petition No. 1200 of 2012 under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the award. The petition was dismissed on 10 February 2015.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
  • Indian Partnership Act, 1932:
  • Maharashtra Cooperative Societies Act, 1960:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Contractor/Developer's Challenge to Majority Arbitral Award in Construction Dispute. Court upholds award of Rs.7,35,000, Rs.10,80,000, interest, and costs under Section 34 of the Arbitration and Conciliation Act, 1996, fin...
Related Judgement
High Court High Court of Karnataka Quashes FIR in Cheating and Forgery Case Due to Civil Nature of Dispute. Dispute over property sale agreement held to be purely civil, not criminal, under Sections 420, 456, 466, 468, 471, 120B of IPC.