Case Note & Summary
The appellant, Hindustan Construction Company Ltd., was awarded a contract by the respondent, Bihar Rajya Pul Nirman Nigam Ltd. (BRPNNL), on 04.03.2014 for construction of a bridge over River Sone in Bihar. The contract contained Clause 25 providing for settlement of disputes through arbitration. During execution, the appellant raised a claim before the Deputy Chief Engineer on 18.09.2018 seeking compensation for additional costs and losses. Receiving no response, the appellant preferred an appeal to the Managing Director on 20.10.2018 and issued a notice dated 14.12.2018 expressing intention to commence arbitration. The respondent did not respond. The appellant then filed a request case under Section 11 of the Arbitration and Conciliation Act, 1996 before the Patna High Court for appointment of an arbitrator. The High Court dismissed the request on 09.12.2024, holding that the pre-arbitration procedure under Clause 25 was not exhausted. The Supreme Court granted leave and allowed the appeal, setting aside the High Court's order. The Court held that the High Court's approach was contrary to the principle of minimal judicial intervention and party autonomy enshrined in the Act. The Court noted that the appellant had complied with the pre-arbitration steps, and the respondent's silence amounted to a refusal to arbitrate. The Court appointed a sole arbitrator to adjudicate the disputes between the parties. The Supreme Court emphasized that the role of the court under Section 11 is limited to examining the existence of an arbitration agreement, and that the High Court's insistence on exhaustion of pre-arbitration procedure was unwarranted.
Headnote
A) Arbitration Law - Appointment of Arbitrator - Section 11 of the Arbitration and Conciliation Act, 1996 - Pre-Arbitration Procedure - The appellant contractor invoked arbitration after raising claims and filing an appeal as per Clause 25 of the contract, but the respondent did not respond. The High Court dismissed the Section 11 application holding that the pre-arbitration procedure was not exhausted. The Supreme Court held that the High Court's approach was contrary to the principle of minimal judicial intervention and party autonomy, and that the existence of an arbitration agreement was sufficient to appoint an arbitrator. The Court appointed a sole arbitrator to adjudicate the disputes. (Paras 2-10) B) Arbitration Law - Judicial Intervention - Section 5 of the Arbitration and Conciliation Act, 1996 - Minimal Intervention - The Supreme Court reiterated that courts should not interfere with the arbitral process at the stage of appointment of arbitrator under Section 11, and that the role of the court is limited to examining the existence of an arbitration agreement. The Court observed that the High Court's insistence on exhaustion of pre-arbitration procedure amounted to excessive judicial intervention, which is impermissible under the Act. (Paras 3-8) C) Contract Law - Government Contracts - Clause 25 - Dispute Resolution - The contract between the parties contained a multi-tiered dispute resolution clause requiring the contractor to first raise claims before the Deputy Chief Engineer, then appeal to the Managing Director, and then invoke arbitration. The appellant complied with these steps, but the respondent did not respond. The Supreme Court held that the respondent's silence amounted to a refusal to arbitrate, and the appellant was entitled to approach the court under Section 11. (Paras 4-6)
Issue of Consideration
Whether the High Court was justified in dismissing the appellant's application under Section 11 of the Arbitration and Conciliation Act, 1996, on the ground that the pre-arbitration procedure under Clause 25 of the contract was not exhausted.
Final Decision
The Supreme Court allowed the appeal, set aside the High Court's order dated 09.12.2024, and appointed a sole arbitrator to adjudicate the disputes between the parties.
Law Points
- Section 11 of the Arbitration and Conciliation Act
- 1996
- party autonomy
- minimal judicial intervention
- pre-arbitration procedure
- appointment of arbitrator
- government contracts





