Case Note & Summary
The petitioner, M/s. Prasad Gas Agency, was appointed as a distributor of LPG (Bharat Gas) by the respondent, Bharat Petroleum Corporation Limited, under an agreement dated 7th October 1986. The agreement contained Clause 29, which allowed either party to terminate the agreement by giving 30 days' notice without assigning any reason. The respondent terminated the distributorship by a notice dated 30th March 2004, citing Clause 29. The petitioner challenged the termination and claimed damages, leading to arbitration. The sole arbitrator rejected the petitioner's claims, holding that the termination was valid under Clause 29 and that the petitioner had failed to prove any loss. The petitioner filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging the award on the ground that it was contrary to public policy and perverse. The High Court examined the arbitrator's findings and held that the interpretation of Clause 29 was plausible and not perverse. The court noted that the arbitrator had considered the evidence and the contract, and his conclusions were not so unreasonable as to shock the conscience of the court. The court dismissed the petition, upholding the arbitral award.
Headnote
A) Arbitration - Section 34 of Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Public Policy - The court considered whether the arbitral award rejecting claims for wrongful termination of distributorship agreement was contrary to public policy. The court held that the arbitrator's interpretation of Clause 29, which allowed termination without assigning reasons, was a plausible view and not perverse. The court found no ground to interfere under Section 34 as the award did not shock the conscience of the court. (Paras 1-15) B) Contract Law - Termination Clause - Distributorship Agreement - Clause 29 - The agreement allowed either party to terminate by giving 30 days' notice without assigning any reason. The court held that the arbitrator's finding that the termination was valid under Clause 29 was based on evidence and was not perverse. The court noted that the petitioner's claim for damages was rejected as the termination was in accordance with the contract. (Paras 2-10) C) Arbitration - Section 34 of Arbitration and Conciliation Act, 1996 - Perversity - The court examined whether the arbitrator's findings were perverse. It held that perversity must be such that no reasonable person would arrive at that conclusion. The court found that the arbitrator had considered the evidence and the contract, and his conclusions were not perverse. (Paras 11-15)
Issue of Consideration
Whether the arbitral award rejecting the petitioner's claims for wrongful termination of distributorship agreement is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the ground of being contrary to public policy or perverse.
Final Decision
The High Court dismissed the petition and upheld the arbitral award dated 7th September 2012.
Law Points
- Termination without assigning reasons under contract clause
- Section 34 of Arbitration and Conciliation Act
- 1996
- Public policy ground for setting aside award
- Perversity of findings
- Interpretation of contractual clauses





