Case Note & Summary
The petitioner, Rashmi Housing Private Limited, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 29 March 2011. The dispute arose from a Deal Memo dated 26 November 2007, whereby the respondent, Pan India Infraprojects Private Limited (formerly Essel Sports Private Limited), appointed the petitioner as sponsor of the Indian Cricket League (ICL) tournament for a consideration of Rs. 2 crores. The petitioner paid Rs. 50 lakhs upon signing but failed to pay the remaining Rs. 1.5 crores. The respondent initiated arbitration, claiming the balance amount with interest. The arbitrator allowed the claim, awarding Rs. 1,74,72,000/- with interest at 18% per annum from the due date until the award, and thereafter at 12% per annum until payment, and rejected the petitioner's counterclaim for damages due to alleged breach of exclusivity. The petitioner challenged the award on grounds that the arbitrator exceeded jurisdiction by awarding interest from the due date contrary to the contract, which provided for interest only after 30 days of default, and that the counterclaim was rejected without proper consideration. The court analyzed the Deal Memo and found that Clause 6 provided for interest at 18% per annum only after 30 days from the due date. The court held that the arbitrator's award of interest from the due date was contrary to the contract and thus patently illegal. Regarding the counterclaim, the court noted that the arbitrator merely stated that the counterclaim was not proved without any reasoning, which violated the requirement of a reasoned award under Section 31(3) of the Act. The court set aside the award on the issue of interest and remitted the counterclaim back to the arbitrator for fresh consideration. The court upheld the principal award of Rs. 1,74,72,000/- but modified the interest to run from 30 days after the due date. The petition was partly allowed.
Headnote
A) Arbitration - Section 34 Petition - Public Policy - Interest Award - The court examined whether the arbitrator's award of interest at 18% per annum from the due date was contrary to the terms of the Deal Memo which provided for interest at 18% per annum only after 30 days of default. The court held that the arbitrator exceeded jurisdiction by awarding interest from the due date, as the contract specified a grace period. (Paras 10-15) B) Arbitration - Counterclaim - Rejection Without Reasons - The court considered whether the arbitrator's rejection of the counterclaim for damages due to alleged breach of exclusivity was sustainable. The court held that the arbitrator failed to provide any reasoning for rejecting the counterclaim, which amounted to a violation of the requirement of a reasoned award under Section 31(3) of the Act. (Paras 20-25) C) Contract - Sponsorship Agreement - Exclusivity Clause - The court analyzed the Deal Memo and found that there was no express exclusivity clause preventing the claimant from entering into other sponsorship agreements. The court held that the respondent's claim of breach of exclusivity was not supported by the contract terms. (Paras 30-35)
Issue of Consideration
Whether the arbitral award granting interest at 18% per annum from the due date and rejecting the counterclaim without proper consideration is contrary to the terms of the contract and the public policy of India under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The court partly allowed the petition. The award of interest at 18% per annum from the due date was set aside and modified to run from 30 days after the due date. The rejection of the counterclaim was set aside and remitted to the arbitrator for fresh consideration. The principal award of Rs. 1,74,72,000/- was upheld.
Law Points
- Arbitration and Conciliation Act
- 1996
- Section 34
- Public Policy
- Interest Award
- Counterclaim
- Exclusivity Clause
- Breach of Contract
- Reasoned Award





