Case Note & Summary
The case involves two arbitration petitions filed under Section 34 of the Arbitration and Conciliation Act, 1996, challenging a common arbitral award dated 31 October 2011. The petitioners are M/s. Aawas Builders (a partnership firm) and its partners (the builder) in one petition, and the legal heirs of late Ramnath Hiraji Pathare (the owners) in the other. The dispute arose from a development agreement dated 20 April 2005, whereby the owners agreed to develop their property in Parel, Mumbai, through the builder. The owners terminated the agreement on 15 July 2006, alleging that the builder failed to obtain necessary approvals and commence construction within the stipulated time. The builder disputed the termination and claimed damages for loss of profit and expenses incurred. The Arbitral Tribunal, by a majority award, held that the termination was wrongful and awarded the builder damages of Rs. 1,50,00,000/- with interest at 18% per annum from the date of the award until realization. The owners challenged the award on grounds of patent illegality and perversity, arguing that the tribunal ignored evidence of the builder's breach. The builder cross-challenged the award, seeking higher damages and modification of the interest rate. The High Court, after hearing both sides, held that the tribunal's findings on termination and damages were based on evidence and not perverse, thus not liable to be interfered with under Section 34. However, the court found the interest rate of 18% to be excessive and modified it to 12% per annum from the date of the award until realization. The court also clarified that the builder was entitled to retain the constructed area as per the agreement. Both petitions were disposed of accordingly, with no order as to costs.
Headnote
A) Arbitration - Challenge to Award - Section 34 Arbitration and Conciliation Act, 1996 - Scope of Interference - The court reiterated that under Section 34, interference is limited to grounds of patent illegality, perversity, or violation of public policy. The court cannot reappreciate evidence or substitute its own view. (Paras 4-6) B) Development Agreement - Termination - Damages - The Arbitral Tribunal found that the owners terminated the development agreement without valid cause and awarded damages for loss of profit. The court upheld this finding as it was based on evidence and not perverse. (Paras 7-10) C) Interest - Rate of Interest - The Arbitral Tribunal awarded interest at 18% per annum. The court modified this to 12% per annum from the date of the award until realization, as 18% was considered excessive and not in line with commercial realities. (Para 11) D) Development Agreement - Retention of Constructed Area - The builder was entitled to retain the constructed area as per the agreement. The court upheld the award on this aspect, noting that the builder had performed its obligations and the termination was wrongful. (Paras 8-9)
Issue of Consideration
Whether the Arbitral Award dated 31 October 2011 is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of patent illegality, perversity, or violation of public policy.
Final Decision
Both arbitration petitions are disposed of. The Arbitral Award dated 31 October 2011 is upheld except for the rate of interest, which is modified from 18% per annum to 12% per annum from the date of the award until realization. No order as to costs.
Law Points
- Arbitration
- Development Agreement
- Termination
- Damages
- Interest
- Section 34 Arbitration and Conciliation Act
- 1996




