Supreme Court Allows Appeal Against HERC Amendment Denying Tariff Adjustment to Biomass Power Plant Commissioned in FY 2013-14. The Court held that classification of projects based on financial year of commissioning within the same control period was arbitrary and discriminatory under the HERC Regulations.

  • 9
Judgement Image
Font size:
Print

Case Note & Summary

The case involves an appeal by M/S Star Wire (India) Vidyut Pvt. Ltd. & Anr. against the Haryana Electricity Regulatory Commission (HERC) regarding the fourth amendment to the HERC (Terms and Conditions for determination of Tariff from Renewable Energy Sources, Renewable Purchase Obligation and Renewable Energy Certificate) Regulations, 2010. The appellant had set up a 9.90 MW biomass power plant, commercially operational on 3 May 2013. The principal Regulations of 2010 provided for a first control period ending 31 March 2013, with a proviso that if revised regulations were not notified, existing norms would continue until notification, subject to adjustments. The Commission initiated suo motu proceedings in 2014 and issued the fourth amendment on 12 August 2015, which applied revised norms prospectively from that date and classified projects based on the financial year of commissioning within the second control period (2013-14 to 2016-17). The appellant challenged the amendment as arbitrary and discriminatory, arguing that it should apply from the start of the second control period (1 April 2013). The High Court dismissed the writ petition in a cursory manner, holding that the classification was valid and that adjustments were a matter of calculation. The Supreme Court found the High Court's reasoning cryptic and noted that the amendment created an unreasonable classification without intelligible differentia. The Court set aside the High Court's order and remanded the matter for fresh consideration, directing the High Court to examine the validity of the amended regulations in light of principles of non-discrimination and legitimate expectation.

Headnote

A) Electricity Law - Tariff Determination - Renewable Energy - Classification of Projects - The Haryana Electricity Regulatory Commission's fourth amendment to the 2010 Regulations classified renewable energy projects commissioned in financial year 2013-14 differently from those commissioned in later years within the same control period (2013-14 to 2016-17), without any intelligible differentia or rational basis, and applied revised norms prospectively from the date of notification (12.08.2015) rather than from the start of the second control period (01.04.2013). The Supreme Court held that such classification was arbitrary and discriminatory, and that the amended regulations should apply from the commencement of the second control period, subject to adjustments. (Paras 3-6)

B) Electricity Law - Tariff Determination - Renewable Energy - Prospective Application - The third proviso to Regulation 4 of the principal Regulations provided that if revised regulations were not notified before the expiry of the control period, the existing norms would continue until notification, subject to adjustments as per revised regulations. The Supreme Court held that the amended regulations, which gave prospective effect only from the date of notification, violated this proviso and the legitimate expectation of project developers who had commissioned projects during the interregnum. (Paras 3-6)

C) Electricity Law - Tariff Determination - Renewable Energy - Judicial Review - The High Court's dismissal of the writ petition was cryptic and failed to properly analyze the issues of discrimination and arbitrary classification. The Supreme Court set aside the High Court's order and remanded the matter for fresh consideration, directing the High Court to examine the validity of the amended regulations in light of the principles of non-discrimination and legitimate expectation. (Paras 5-6)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the fourth amendment to HERC Regulations, which applied revised tariff norms prospectively from the date of notification and classified projects based on financial year of commissioning within the same control period, was arbitrary and discriminatory.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court set aside the impugned judgment of the High Court and remanded the matter for fresh consideration, directing the High Court to examine the validity of the amended regulations in light of the principles of non-discrimination and legitimate expectation.

Law Points

  • Regulatory discrimination
  • Arbitrary classification
  • Prospective application of amended regulations
  • Adjustment of tariff norms
  • Renewable energy tariff determination
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (7) 19

Civil Appeal No. 5139 of 2019 (Arising out of SLP (C) No.8432 of 2017)

2019-07-02

A.M. Khanwilkar

M/S Star Wire (India) Vidyut Pvt. Ltd. & Anr.

Haryana Electricity Regulatory Commission

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against High Court judgment dismissing writ petition challenging amendment to tariff regulations for renewable energy projects.

Remedy Sought

Appellants sought setting aside of the impugned notification and order, and direction to apply revised regulations from 01.04.2013 with carrying cost.

Filing Reason

Appellants challenged the fourth amendment to HERC Regulations which applied revised tariff norms prospectively from 12.08.2015 and classified projects based on financial year of commissioning within the same control period, allegedly discriminating against projects commissioned in FY 2013-14.

Previous Decisions

High Court of Punjab and Haryana dismissed the writ petition (C.W.P. No.25337 of 2015) on 23.11.2016, holding that the classification was valid and adjustments were a matter of calculation.

Issues

Whether the classification of renewable energy projects based on financial year of commissioning within the same control period is arbitrary and discriminatory. Whether the amended regulations should apply prospectively from the date of notification or from the commencement of the second control period (01.04.2013).

Submissions/Arguments

Appellants argued that the principal Regulations continued to apply until notification of revised regulations, subject to adjustments, and that the amendment created an unreasonable classification without intelligible differentia. Respondent argued that the amendment was based on a detailed order dated 04.08.2015 and that the classification was reasonable and within the Commission's power.

Ratio Decidendi

The High Court's dismissal was cryptic and failed to properly analyze the issues of discrimination and arbitrary classification. The matter requires fresh consideration on merits.

Judgment Excerpts

The effect whereof was to deny the applicability of tariff norms adjustments to the appellant No.1, which had commenced its commercial operations on 3rd May, 2013. The said amendment has been given prospective effect qua the appellants. It has made classification between the projects commissioned/to be commissioned in financial years 201314 on the one hand and 201415, 201516 and 201617 on the other, without any intelligible differentia or any rational basis therefor. The High Court in the impugned judgment has noted that the appellants had raised only two contentions... these two points have been disposed of by the Division Bench of the High Court in a most cursory manner without analysing the issues in proper perspective.

Procedural History

The appellants filed a writ petition (C.W.P. No.25337 of 2015) before the High Court of Punjab and Haryana challenging the fourth amendment to HERC Regulations and the order dated 04.08.2015. The High Court dismissed the petition on 23.11.2016. The appellants then filed a Special Leave Petition (SLP (C) No.8432 of 2017) before the Supreme Court, which was converted into Civil Appeal No. 5139 of 2019.

Acts & Sections

  • Haryana Electricity Regulatory Commission (Terms and Conditions for determination of Tariff from Renewable Energy Sources, Renewable Purchase Obligation and Renewable Energy Certificate) Regulations, 2010: Regulation 4, Regulation 5, Regulation 6
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Reverses High Court's Modification of Conviction in Attempt to Commit Rape Case. The Court held that the respondent's actions constituted an attempt to commit rape under Section 376(2)(f) read with Section 511 IPC, not mere preparation ...
Related Judgement
Supreme Court Supreme Court Allows Appeal Against HERC Amendment Denying Tariff Adjustment to Biomass Power Plant Commissioned in FY 2013-14. The Court held that classification of projects based on financial year of commissioning within the same control period was...