Bombay High Court Allows Appointment of Arbitrator in Railway Contract Dispute Under Section 11 of Arbitration and Conciliation Act, 1996. Failure of Respondent to Appoint Arbitrator Within 30 Days of Demand Triggers Court's Power to Appoint Arbitrator.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 103
Judgement Image
Font size:
Print

Case Note & Summary

The applicant, M/s. Railtech Infraventure Pvt. Ltd., filed an application under Section 11 of the Arbitration and Conciliation Act, 1996 seeking appointment of an arbitrator to adjudicate disputes arising out of a contract with the Union of India and the Divisional Railway Manager, Central Railway, Pune. The contract, dated October 10, 2009, was for deep screening and ballast renewal works in the Pune-Lonavla section, with a total cost of Rs. 1,43,49,245.79. The contract was governed by the General Conditions of Contract (GCC) of Central Railways, which contained arbitration clauses 63 and 64. Clause 63 defined excepted matters that were not arbitrable, while clause 64 provided for arbitration. The applicant contended that disputes arose and it made a demand for arbitration on January 10, 2014, but the respondent failed to appoint an arbitrator within 30 days as required. The respondent argued that the disputes were excepted matters under clause 63 and thus not arbitrable. The court examined the arbitration agreement and found that the disputes raised by the applicant were not covered by the excepted matters listed in clause 63. The court noted that the respondent did not appoint an arbitrator within 30 days of the demand, as required by clause 64(3)(a). Therefore, the court held that it had the power to appoint an arbitrator under Section 11 of the Act. The court appointed a retired judge of the Bombay High Court as the sole arbitrator to adjudicate the disputes, excluding excepted matters. The arbitrator was directed to make a disclosure under Section 12 of the Act and to file the award within the time prescribed by law.

Headnote

A) Arbitration Law - Appointment of Arbitrator - Section 11 of the Arbitration and Conciliation Act, 1996 - Failure to Appoint - Applicant contractor sought appointment of arbitrator after respondent failed to appoint one within 30 days of demand - Court held that since respondent did not appoint arbitrator within the stipulated time, the court is empowered to appoint an arbitrator - Held that the arbitration agreement exists and the dispute is arbitrable except for excepted matters (Paras 1-8).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the court should appoint an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 when the respondent failed to appoint an arbitrator within 30 days of the demand, despite the existence of an arbitration agreement.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the application and appointed a retired judge of the Bombay High Court as the sole arbitrator to adjudicate the disputes between the parties, excluding excepted matters. The arbitrator was directed to make a disclosure under Section 12 of the Act and to file the award within the time prescribed by law.

Law Points

  • Section 11 of the Arbitration and Conciliation Act
  • 1996
  • General Conditions of Contract (GCC) Clauses 63 and 64
  • Excepted matters
  • Appointment of arbitrator by court when party fails to act as per arbitration agreement
Subscribe to unlock Law Points Subscribe Now

Case Details

2014 LawText (BOM) (11) 48

Arbitration Application No. 63 of 2014

2014-11-12

S.J. Kathawalla, J.

Mr. Y. Singh, instructed by M/s. Auris Legal, for the Applicant; Mr. Suresh Kumar for the Respondent.

M/s. Railtech Infraventure Pvt. Ltd.

Union of India and another

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Application under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator.

Remedy Sought

Appointment of a retired judge of the High Court or any other person as arbitrator to adjudicate disputes between the parties.

Filing Reason

Disputes arose under a contract for deep screening and ballast renewal works; respondent failed to appoint arbitrator within 30 days of demand.

Issues

Whether the court should appoint an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 when the respondent failed to appoint an arbitrator within 30 days of the demand. Whether the disputes raised by the applicant are excepted matters under Clause 63 of the GCC and thus not arbitrable.

Submissions/Arguments

Applicant: Tenders were invited, bid accepted, contract executed; disputes arose; demand for arbitration made on 10.01.2014; respondent failed to appoint arbitrator within 30 days; hence court should appoint arbitrator. Respondent: The disputes are excepted matters under Clause 63 of GCC and not arbitrable; therefore, no arbitrator can be appointed.

Ratio Decidendi

When a party fails to appoint an arbitrator within 30 days of a demand for arbitration as per the arbitration agreement, the court is empowered under Section 11 of the Arbitration and Conciliation Act, 1996 to appoint an arbitrator. The existence of excepted matters does not bar arbitration of other disputes.

Judgment Excerpts

The above Application is filed by the Applicant under Section 11 of the Arbitration and Conciliation Act,1996 (“the Act”) for the following relief: ... According to the Applicant, Clauses 63 and 64 of GCC pertain to the arbitration agreement entered into between the Parties. The Respondent has not appointed an Arbitrator within 30 days of the demand. Hence, this Court has the power to appoint an Arbitrator.

Procedural History

The applicant filed Arbitration Application No. 63 of 2014 under Section 11 of the Arbitration and Conciliation Act, 1996 before the Bombay High Court. The court heard the parties and delivered judgment on 12 November 2014.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11, Section 12
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Appointment of Arbitrator in Railway Contract Dispute Under Section 11 of Arbitration and Conciliation Act, 1996. Failure of Respondent to Appoint Arbitrator Within 30 Days of Demand Triggers Court's Power to Appoint Arbitrat...
Related Judgement
High Court Bombay High Court Upholds Reinstatement of Workman with 75% Backwages in Unfair Dismissal Case. Employer's challenge to Labour Court order dismissed; workman's cross-petition for full backwages partly allowed.