Bombay High Court Partially Allows Contractor's Appeal in Blast Hole Drilling Dispute, Upholds Rate of Rs.115 per Meter for Work Done Without Formal Contract. Court Holds That Absence of Formal Agreement Does Not Preclude Payment on Quantum Meruit Basis for Work Actually Performed and Accepted.

High Court: Bombay High Court Bench: NAGPUR
  • 92
Judgement Image
Font size:
Print

Case Note & Summary

The case involves two cross-appeals arising from a suit for recovery of Rs.22,76,673/- filed by M/s. Shri Sowmiya Enterprises (plaintiff/contractor) against Mineral Exploration Corporation Ltd. (defendant/employer) for blast hole drilling work carried out between 26.11.1989 and 31.3.1990. The plaintiff claimed payment at the rate of Rs.140 per meter, while the defendant contended that the agreed rate was Rs.115 per meter and that no formal contract was executed. The trial court decreed the suit for Rs.1,03,811.20 with interest at 6% per annum, holding that the plaintiff was entitled to payment at Rs.115 per meter. The plaintiff appealed for enhancement (First Appeal No.429/1994), and the defendant challenged the decree (First Appeal No.596/1994). The High Court framed the issue of whether there was a concluded contract at Rs.140 per meter. The court analyzed the evidence, including the work order dated 25.11.1989 which stated that the rates were subject to formal agreement, and found that no formal contract was ever executed. The court held that in the absence of a concluded contract, the plaintiff was entitled to reasonable compensation on quantum meruit basis. The trial court's rate of Rs.115 per meter was upheld as reasonable, considering that the plaintiff had accepted payments at that rate without protest and that it was the rate mentioned in the work order. The court also upheld the interest rate of 6% per annum. Consequently, First Appeal No.429/1994 was dismissed, and First Appeal No.596/1994 was allowed, setting aside the decree and substituting it with a decree for Rs.1,03,811.20 with interest at 6% per annum from the date of suit till realization.

Headnote

A) Contract Law - Concluded Contract - Rate Fixation - Whether a concluded contract existed between the parties for blast hole drilling at Rs.140 per meter - The plaintiff contractor claimed payment at Rs.140 per meter for work done from 26.11.1989 to 31.3.1990, but the defendant employer disputed the rate and contended that no formal contract was executed. The court held that there was no concluded contract at Rs.140 per meter as the work order was subject to formal agreement which never materialized. (Paras 3-10)

B) Contract Law - Quantum Meruit - Payment for Work Done - Entitlement to payment for work actually performed and accepted - Even in the absence of a concluded contract, the plaintiff is entitled to reasonable compensation on quantum meruit basis for the blast hole drilling work carried out and accepted by the defendant. The court upheld the trial court's rate of Rs.115 per meter as reasonable, considering the prevailing market rates and the fact that the plaintiff had accepted payments at that rate without protest. (Paras 11-15)

C) Interest - Rate of Interest - Discretion of Court - Whether the trial court's award of 6% interest per annum was proper - The court found no reason to interfere with the rate of interest awarded by the trial court, as it was within its discretion and consistent with the principles of justice. (Para 16)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether there was a concluded contract entitling the plaintiff to recover at the rate of Rs.140 per meter for blast hole drilling work, and if not, what rate is payable on quantum meruit basis.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

First Appeal No.429/1994 filed by the plaintiff is dismissed. First Appeal No.596/1994 filed by the defendant is allowed. The decree passed by the trial court is set aside and substituted with a decree for Rs.1,03,811.20 with interest at 6% per annum from the date of suit till realization.

Law Points

  • Quantum meruit
  • concluded contract
  • acceptance of work
  • rate fixation
  • interest rate
Subscribe to unlock Law Points Subscribe Now

Case Details

2014 LawText (BOM) (10) 121

First Appeal No. 429/1994 and First Appeal No. 596/1994

2014-10-07

R. K. Deshpande

Shri S.C. Mehadia for appellant in FA 429/1994 and respondent in FA 596/1994; Shri M.D. Samel for respondent in FA 429/1994 and appellant in FA 596/1994

M/s. Shri Sowmiya Enterprises (in FA 429/1994) and Mineral Exploration Corporation Ltd. (in FA 596/1994)

Mineral Exploration Corporation Ltd. (in FA 429/1994) and M/s. Shri Sowmiya Enterprises (in FA 596/1994)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil suit for recovery of money for blast hole drilling work

Remedy Sought

Plaintiff sought decree for Rs.22,76,673/- with interest

Filing Reason

Dispute over rate of payment for blast hole drilling work carried out between 26.11.1989 and 31.3.1990

Previous Decisions

Trial court decreed suit for Rs.1,03,811.20 with interest at 6% per annum

Issues

Whether there was a concluded contract entitling the plaintiff to recover at the rate of Rs.140 per meter for blast hole drilling work? What is the reasonable rate payable on quantum meruit basis for work done?

Submissions/Arguments

Plaintiff argued that there was a concluded contract at Rs.140 per meter based on work order and subsequent conduct. Defendant contended that no formal contract was executed and the agreed rate was Rs.115 per meter as per work order.

Ratio Decidendi

In the absence of a concluded contract, a contractor is entitled to reasonable compensation on quantum meruit basis for work actually performed and accepted by the employer. The rate of Rs.115 per meter was upheld as reasonable.

Judgment Excerpts

The decree is based upon the rate of Rs.115/ per meter as against the claim of the appellant/plaintiff at the rate of Rs.140/ per meter. Whether there was a concluded contract entitling the plaintiff to recover the amount of blast hole drilling work at the rate of Rs.140/ per meter for the period from 26.11.1989 to 31.3.1990?

Procedural History

The plaintiff filed Special Civil Suit No.568 of 1991 for recovery of Rs.22,76,673/-. The trial court decreed the suit on 12.7.1994 for Rs.1,03,811.20 with interest at 6% per annum. Both parties appealed: plaintiff filed FA 429/1994 for enhancement, defendant filed FA 596/1994 challenging the decree.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Partially Allows Contractor's Appeal in Blast Hole Drilling Dispute, Upholds Rate of Rs.115 per Meter for Work Done Without Formal Contract. Court Holds That Absence of Formal Agreement Does Not Preclude Payment on Quantum Meruit Ba...
Related Judgement
High Court Gujarat High Court Allows Transfer of Divorce Petition from Patan to Surat in Matrimonial Dispute — Wife's Convenience and Pending Proceedings at Surat Considered. Transfer Granted Under Section 24 CPC as Wife Resides at Surat with Senior Citizen P...