Bombay High Court Partially Allows Challenge to Arbitral Award in Construction Contract Dispute — Excess Material Consumption Claim Upheld, Defective Work Claim Set Aside. Court Interprets Contractual Wastage Allowances and Holds That Arbitrator's Findings on Excess Consumption Are Not Perverse, But Award for Defective Work Lacks Evidence.

High Court: Bombay High Court Bench: BOMBAY
  • 18
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, New Consolidated Construction Co. Ltd., challenged an arbitral award dated 16th September 2013 under Section 34 of the Arbitration and Conciliation Act, 1996. The dispute arose from construction contracts for three buildings in a Special Economic Zone. Initially, the parties entered into a turnkey contract where the petitioner was to obtain materials and construct. Later, it was modified to a labour contract where the respondent supplied materials and the petitioner provided labour. The initial contract set permissible wastages. The arbitrator granted three claims to the respondent: excess consumption of material, defective work, and refund of excess amount paid. The petitioner argued that the award was contrary to the contract and perverse. The court examined each claim. For excess consumption, the court found that the arbitrator's finding was based on evidence and not perverse, as the contract allowed certain wastages and the respondent's calculations showed excess. For defective work, the court found that the arbitrator relied on a consultant's report that was not proved in evidence, and the respondent failed to provide independent evidence of defects; thus, the award on this claim was perverse and set aside. For refund of excess payment, the court upheld the award as it was based on the contract and evidence. The court partly allowed the petition, setting aside only the claim for defective work.

Headnote

A) Arbitration Law - Section 34 of Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Excess Consumption of Material - The court examined whether the arbitrator's finding that the petitioner exceeded the contractual wastage allowance was perverse. The contract provided for permissible wastages, and the arbitrator relied on the respondent's calculations showing excess consumption. The court held that the finding was based on evidence and not perverse, and thus not liable to be interfered with under Section 34. (Paras 4-10)

B) Arbitration Law - Section 34 of Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Defective Work - The court considered the claim for defective work requiring rectification. The arbitrator awarded the claim based on a report from a consultant, but the court found that the report was not proved in evidence and the respondent failed to provide any independent evidence of defects. The court held that the award on this claim was perverse and set it aside. (Paras 11-15)

C) Arbitration Law - Section 34 of Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Refund of Excess Amount Paid - The court examined the claim for refund of excess payment. The arbitrator found that the respondent had overpaid the petitioner based on the contract rates and quantities. The court held that this finding was based on the contract and evidence, and not perverse, and thus upheld the award. (Paras 16-18)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award granting claims for excess consumption of material, defective work, and refund of excess amount paid is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of being contrary to the contract, perverse, or against public policy.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court partly allowed the petition. The award in respect of the claim for defective work was set aside. The award in respect of the claims for excess consumption of material and refund of excess amount paid was upheld.

Law Points

  • Interpretation of contract
  • Arbitral award
  • Section 34 of Arbitration and Conciliation Act
  • 1996
  • Public policy
  • Perversity
  • Evidence
  • Wastage allowance
  • Labour contract
  • Turn key contract
Subscribe to unlock Law Points Subscribe Now

Case Details

2014:BHC-OS:9130

Arbitration Petition No.307 of 2014

2014-09-02

Mrs. Roshan Dalvi, J.

2014:BHC-OS:9130

Mr. Aspi Chinoy, Sr. Adv., a/w. Mr. Sunip Sen, Adv. a/w. Mr. R A K NijamESSani, Adv. i/b. Maneksha & Sethna for the petitioner. Mr. Ravi Kadam, Sr. Adv., a/w. Mr. Aditya Mehta, Adv. a/w. Mr. R.J. Gagrat, Adv. Ms. Sheetal D. Sabnis, Adv. Mr. Praveen Kejriwal, Adv. a/w. Ms. Kanchan Shivkar, Adv. i/b. Gagrats for the respondents.

New Consolidated Construction Co. Ltd.

M/s. Serum Bio Pharma Park & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

Setting aside of the arbitral award dated 16th September 2013.

Filing Reason

The petitioner challenged the award on grounds that it was contrary to the contract and perverse.

Previous Decisions

The arbitral award dated 16th September 2013 granted three claims to the respondent: excess consumption of material, defective work, and refund of excess amount paid.

Issues

Whether the arbitral award granting claim for excess consumption of material is perverse or contrary to the contract. Whether the arbitral award granting claim for defective work is perverse or contrary to the contract. Whether the arbitral award granting claim for refund of excess amount paid is perverse or contrary to the contract.

Submissions/Arguments

The petitioner argued that the arbitrator's findings on excess consumption were contrary to the contract and perverse. The petitioner argued that the claim for defective work was not supported by evidence and the arbitrator relied on an unproved report. The petitioner argued that the refund claim was not justified under the contract. The respondent argued that the award was based on evidence and within the terms of the contract.

Ratio Decidendi

Under Section 34 of the Arbitration and Conciliation Act, 1996, an arbitral award can be set aside if it is perverse or contrary to the contract. A finding is perverse if it is based on no evidence or ignores vital evidence. The court will not interfere with findings of fact that are based on evidence, even if another view is possible.

Judgment Excerpts

The claims which are granted are in respect of : a. excess consumption of material used for construction ; b. defective work required to be rectified; and c. refund of excess amount paid. The court held that the finding on excess consumption was not perverse. The court set aside the award for defective work as it was based on no evidence.

Procedural History

The parties entered into a turnkey contract on 27th May 2006, later modified to a labour contract. Disputes arose and were referred to arbitration. The arbitrator passed an award on 16th September 2013. The petitioner filed this petition under Section 34 of the Arbitration and Conciliation Act, 1996 on 2nd September 2014.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Partially Allows Challenge to Arbitral Award in Construction Contract Dispute — Excess Material Consumption Claim Upheld, Defective Work Claim Set Aside. Court Interprets Contractual Wastage Allowances and Holds That Arbitrator's ...
Related Judgement
High Court Bombay High Court Allows Appeal Against Acquittal in Cheque Bounce Case — Presumption Under Section 139 NI Act Not Rebutted by Accused. Hand Loan of Rs.30 Lakhs Held Legally Enforceable Debt, Conviction Restored.