Case Note & Summary
The petitioner, Atlanta Limited, a public limited company, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking an order and injunction against the respondents, the Executive Engineer and the State of Maharashtra, from preventing the petitioner from collecting toll on the Mumbra Bypass under the present contract until 5th October 2024. The background of the dispute is that on 12th July 2000, the respondent awarded a contract to the petitioner for construction of Mumbra Bypass off Mumbai Pune Road National Highway No.4 on a Build-Operate-Transfer (BOT) basis. Disputes arose between the parties regarding additional costs allegedly incurred by the petitioner, which were referred to arbitration. During the pendency of the contract, the petitioner made claims for extension of the period for collection of toll. The petitioner contended that at various levels, officers of the respondents recommended an extension period of 24 years 9 months and 28 days to the government for approval. Before the arbitral tribunal, the petitioner made money claims as well as claims for extension of the toll collection period. The arbitral tribunal rendered a finding of fact that the officers of the respondent, particularly the Superintendent Engineer, had recommended the period of extension to the government and such recommendation was final and conclusive. The tribunal considered extension for a period of 40 years and 6 months. The contract was set to expire on 21st September 2014. The petitioner sought interim relief to collect toll at least for the period recommended by the Superintendent Engineer. The respondents opposed the petition, arguing that the recommendation was not final and binding on the government, and that the petitioner was indirectly seeking execution of the award, which was automatically stayed by the filing of Section 34 petitions by both parties. The court noted that both parties had impugned the arbitral award under Section 34 of the Act and those petitions were admitted and pending. The court held that the subject matter of the arbitration required protection and granted interim relief, allowing the petitioner to collect toll until the disposal of the Section 34 petitions or until further orders, subject to the petitioner furnishing an undertaking to pay the amount collected as toll with interest at 9% per annum if the court ultimately decides against the petitioner. The court also directed the petitioner to file an affidavit of undertaking within one week.
Headnote
A) Arbitration - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Protection of Subject Matter - The court considered whether to grant interim relief to the petitioner to continue toll collection beyond the original contract period based on the engineer's recommendation for extension, which the arbitral tribunal found to be final and conclusive. The court held that the subject matter of arbitration required protection and granted interim relief to allow the petitioner to collect toll until the disposal of the Section 34 petitions or until further orders, subject to conditions. (Paras 1-7) B) Contract Law - BOT Contract - Finality of Engineer's Recommendation - The arbitral tribunal found that the Superintendent Engineer's recommendation for extension of toll collection period was final and conclusive under the contract. The court noted this finding while granting interim relief, emphasizing that the petitioner's right to collect toll for the recommended period needed protection pending challenge to the award. (Paras 5-7)
Issue of Consideration
Whether the petitioner is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, to continue collecting toll beyond the original contract period pending arbitration, based on the engineer's recommendation for extension.
Final Decision
The court granted interim relief in favour of the petitioner, allowing the petitioner to collect toll on Mumbra Bypass until the disposal of the Section 34 petitions or until further orders, subject to the petitioner filing an undertaking to pay the amount collected as toll with interest at 9% per annum if the court ultimately decides against the petitioner. The petitioner was directed to file an affidavit of undertaking within one week.
Law Points
- Section 9 of the Arbitration and Conciliation Act
- 1996
- interim measures
- protection of subject matter of arbitration
- finality of engineer's recommendation under BOT contract




