Case Note & Summary
The petitioners, two contractors working with respondent no.1 (Maharashtra State Power Generation Co. Ltd.), challenged the rejection of their bids and the award of a cleaning contract to respondent no.2. A tender notice was published on 16 October 2013 for a six-month contract for cleaning and allied works at Koradi Thermal Power Station, with an estimated cost of Rs. 1,63,20,500. Both petitioners submitted their tenders by the deadline of 29 October 2013. The tender required submission of a Techno-Commercial Bid and a Price Bid. The petitioners' Techno-Commercial Bids were rejected as non-responsive due to non-submission of mandatory documents, including a valid EPF registration certificate. The contract was awarded to respondent no.2, who was the lowest bidder and had submitted all required documents. The petitioners filed a writ petition under Article 226 of the Constitution, arguing that their bids were wrongly rejected and that the award was arbitrary. The court examined the tender conditions and found that the petitioners had not submitted the required documents, making their bids non-responsive. The court held that the employer's decision was reasonable and not arbitrary, and that the High Court's scope of interference in contractual matters is limited to examining the decision-making process. The court dismissed the petition, upholding the award of the contract to respondent no.2.
Headnote
A) Tender Law - Judicial Review - Scope of Interference under Article 226 - The court held that in contractual matters, the High Court under Article 226 does not sit as a court of appeal but examines the decision-making process for arbitrariness, mala fides, or procedural violations. The employer's decision to reject bids as non-responsive was found to be reasonable and not arbitrary. (Paras 1-10) B) Tender Law - Responsiveness of Bids - Evaluation of Techno-Commercial Bids - The petitioners' bids were rejected because they did not meet the mandatory requirement of submitting a valid EPF registration certificate and other documents. The court held that the employer's interpretation of the tender conditions was correct and the rejection was justified. (Paras 5-8) C) Tender Law - Award of Contract - Public Interest - The court noted that the contract was awarded to the lowest bidder (respondent no.2) who had fulfilled all conditions. The court found no mala fides or arbitrariness in the award and declined to interfere, emphasizing that public interest lies in the timely execution of the contract. (Paras 9-10)
Issue of Consideration
Whether the High Court under Article 226 of the Constitution of India can interfere with the decision of the employer to reject the petitioners' bids and award the contract to respondent no.2, and whether the petitioners' bids were wrongly rejected as non-responsive.
Final Decision
The High Court dismissed the writ petition, holding that the rejection of petitioners' bids was justified as they were non-responsive, and the award of contract to respondent no.2 was valid. No interference under Article 226 was warranted.
Law Points
- Tender law
- Judicial review of contractual matters
- Scope of interference under Article 226
- Public interest in contract awards
- Employer's discretion in evaluating bids





