Supreme Court Upholds High Court's Interpretation of Lease Deed in State of Bihar v. Tata Iron & Steel Co. Ltd. — Interest on Arrears of Rent Calculated on Lump Sum Basis, Not Per Annum, Under Clause (xii) of Lease Deed. The Court held that the absence of the words 'per annum' in Clause (xii) of the Lease Deed was deliberate and the demand for interest on a yearly basis was illegal.

  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a dispute between the State of Bihar (now Jharkhand) and Tata Iron & Steel Co. Ltd. regarding the calculation of interest on arrears of rent under a lease deed executed on 01.08.1985. The land was originally acquired by the respondent between 1912-1929 under the Land Acquisition Act, 1894 for setting up an industrial plant. The Bihar Land Reforms Act, 1950 (BLR Act) vested all lands in the State, but Section 2B exempted industrial lands until its deletion in 1972. After litigation, the Bihar Land Reforms (Amendment) Act, 1982 substituted Sections 7D and 7E, treating the respondent as a deemed lessee. An agreement for lease was entered into on 01.08.1984, followed by a formal lease deed on 01.08.1985. Clause (xii) of the lease deed provided for payment of rent and interest on arrears for certain categories of land (industrial and allied uses) at specified rates but without the words 'per annum'. Clause (xv) dealt with hats, melas, bazaars, etc., and expressly included 'per annum' for interest calculation. The respondent paid the initial demands raised in 1985. In 1993, the State sought to recalculate interest under Clause (xii) on a per annum basis, leading to a demand of Rs.5.97 crores. The respondent challenged this demand. The High Court initially held the demand to be a public demand under the Bihar and Orissa Public Demands Recovery Act, 1914, but allowed the respondent to raise objections. The Certificate Officer rejected the objections, and the respondent filed a writ petition. The High Court allowed the writ petition, holding that interest under Clause (xii) must be calculated on a lump sum basis (not per annum) and that the demand was not a public demand. The Supreme Court dismissed the State's appeal, affirming the High Court's interpretation of the contract and its finding that the demand was not a public demand. The Court emphasized that the absence of 'per annum' in Clause (xii) was deliberate, given the different nature of the lands covered, and that the State could not unilaterally alter the terms of the contract.

Headnote

A) Contract Law - Interpretation of Contracts - Expressio Unius Est Exclusio Alterius - Lease Deed dated 01.08.1985 - The High Court held that the absence of the words 'per annum' in Clause (xii) of the Lease Deed, while expressly included in Clause (xv), indicates a deliberate omission, and interest under Clause (xii) must be calculated on a lump sum basis, not per annum. The Supreme Court affirmed this interpretation, noting that the two clauses deal with different types of lands and the State cannot travel beyond the terms of the contract. (Paras 8-9)

B) Public Demands Recovery Act, 1914 - Public Demand - Section 3(6) - The High Court held that the demand for interest under Clause (xii) of the Lease Deed is not a 'public demand' under the Act as it arises from a contractual agreement, not from statutory provisions. The Supreme Court upheld this finding, observing that Sections 7D and 7E of the Bihar Land Reforms Act do not provide for interest, and the interest charged was purely contractual. (Paras 9-10)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the demand for interest on arrears of rent under Clause (xii) of the Lease Deed can be calculated on a 'per annum' basis and whether such demand constitutes a 'public demand' under the Bihar and Orissa Public Demands Recovery Act, 1914.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeal, affirming the High Court's judgment that the demand for interest under Clause (xii) of the Lease Deed is illegal as it was calculated on a per annum basis, and that the demand is not a public demand under the Bihar and Orissa Public Demands Recovery Act, 1914.

Law Points

  • Interpretation of contracts
  • Expressio Unius Est Exclusio Alterius
  • Public demand under Bihar and Orissa Public Demands Recovery Act
  • 1914
  • Lease deed interpretation
  • Interest calculation on arrears of rent
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (SC) (5) 26

Civil Appeal No. 3861 of 2014

2019-05-09

L. Nageswara Rao

State of Bihar (Now State of Jharkhand) Through the Sub Divisional Officer & Ors.

Tata Iron & Steel Co. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against High Court judgment allowing writ petition challenging demand for interest on arrears of rent under a lease deed.

Remedy Sought

The State of Bihar sought to recover Rs.5.97 crores as interest calculated on a per annum basis under Clause (xii) of the Lease Deed.

Filing Reason

The Certificate Officer issued a notice for recovery of interest on arrears of rent; the respondent objected and filed a writ petition after the objections were rejected.

Previous Decisions

The High Court initially held the demand to be a public demand under the Bihar and Orissa Public Demands Recovery Act, 1914, but allowed the respondent to raise objections. The Certificate Officer rejected the objections. The High Court then allowed the writ petition, holding the demand illegal and not a public demand.

Issues

Whether the demand for interest under Clause (xii) of the Lease Deed can be calculated on a 'per annum' basis? Whether the demand for interest under Clause (xii) constitutes a 'public demand' under the Bihar and Orissa Public Demands Recovery Act, 1914?

Submissions/Arguments

Appellant (State): The High Court erred in taking a different view from an earlier Division Bench judgment that held the demand to be a public demand; the word 'rent' is not defined in the BLR Act; interest should be calculated per annum. Respondent (Tata Iron & Steel Co. Ltd.): The absence of 'per annum' in Clause (xii) is deliberate; the demand is contractual and not a public demand; the State cannot travel beyond the terms of the lease deed.

Ratio Decidendi

The absence of the words 'per annum' in Clause (xii) of the Lease Deed, while expressly included in Clause (xv), indicates a deliberate omission; interest under Clause (xii) must be calculated on a lump sum basis. The demand for interest is contractual and not a public demand under the Bihar and Orissa Public Demands Recovery Act, 1914, as it arises from an agreement, not from statutory provisions.

Judgment Excerpts

The High Court found that Clause (xii) and Clause (xv) pertain to two different types of lands. The High Court held that the word 'per annum' was intentionally included in Clause (xv) of the Lease Deed and excluded from Clause (xii) of the Lease Deed. The High Court remarked that Sections 7D and 7E of the BLR Act did not provide for payment of interest and the interest charged by the State of Bihar was pursuant to an agreement.

Procedural History

The Certificate Officer issued a notice for recovery on 10.05.1994. The respondent's objections were rejected on 23.01.1996. The respondent filed a writ petition (Writ Petition No. 2761 of 1994) which was dismissed as not maintainable but liberty was granted to raise objections under Section 9 of the Public Demands Act. The respondent filed LPA No.276 of 1995 (R) which was dismissed. The Certificate Officer rejected objections on 23.01.1996. The respondent filed another writ petition which was allowed by the High Court. The State appealed to the Supreme Court.

Acts & Sections

  • Bihar Land Reforms Act, 1950: Section 2B, Section 7, Section 7D, Section 7E
  • Bihar Land Reforms (Amendment) Act, 1972:
  • Bihar Land Reforms (Amendment) Act, 1982:
  • Bihar and Orissa Public Demands Recovery Act, 1914: Section 3(6), Section 6(3), Section 9, Schedule I Item (vii)
  • Land Acquisition Act, 1894:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds High Court's Interpretation of Lease Deed in State of Bihar v. Tata Iron & Steel Co. Ltd. — Interest on Arrears of Rent Calculated on Lump Sum Basis, Not Per Annum, Under Clause (xii) of Lease Deed. The Court held that the abs...
Related Judgement
Supreme Court Supreme Court Acquits Accused in Dowry Death Case Due to Unreliable Witnesses and Contradictions. Presumption Under Section 113B of Evidence Act Not Triggered as Prosecution Failed to Prove 'Soon Before' Cruelty.