Bombay High Court Dismisses Petition Challenging Industrial Court's Finding of Unfair Labour Practice for Non-Implementation of Labour Court Award. Employer Held Liable Under Items 9 and 10 of Schedule IV of MRTU & PULP Act for Failing to Implement Award Passed Against Predecessor Establishment.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 76
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Sharp Detectives Pvt. Ltd., challenged an order of the Industrial Court, Pune, dated 11 July 1996, which held that the petitioner had engaged in an unfair labour practice under Items 9 and 10 of Schedule IV of the Maharashtra Recognition of Trade Unions and Prevention of Unfair Labour Practices Act, 1971 (the Act). The dispute arose from the non-implementation of a Labour Court Award passed in Reference (IDA) No.103 of 1985 on 22 December 1986. The workman, Babu D. Tribhuvan (respondent no.1), was originally employed by M/s. International Security Services. His services were illegally terminated, and he obtained an award against that establishment. The award was not challenged by the management. Subsequently, the workman filed a complaint under Items 9 and 10 of Schedule IV of the Act, alleging that the petitioner, as a successor establishment, had failed to implement the award. The complaint was initially allowed ex-parte, but later set aside. After hearing, the Industrial Court allowed the complaint, holding the petitioner guilty of unfair labour practice. The petitioner argued that it was not a successor to M/s. International Security Services and was not bound by the award. The High Court, however, found that the Industrial Court had correctly concluded that the petitioner had taken over the establishment and was liable to implement the award. The Court noted that the petitioner did not challenge the award itself and that the complaint was specifically for non-implementation. The High Court dismissed the writ petition, upholding the Industrial Court's order.

Headnote

A) Industrial Law - Unfair Labour Practice - Non-Implementation of Award - Items 9 and 10 of Schedule IV of the Maharashtra Recognition of Trade Unions and Prevention of Unfair Labour Practices Act, 1971 - The Industrial Court held that the petitioner, a successor security agency, had engaged in unfair labour practice by failing to implement the Labour Court Award in Reference (IDA) No.103 of 1985 passed against its predecessor, M/s. International Security Services. The Court found that the petitioner had taken over the establishment and was bound by the award. The High Court upheld this finding, noting that the petitioner did not challenge the award and the complaint was filed under the Act for non-implementation. (Paras 1-4)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner, as a successor establishment, is liable for unfair labour practice under Items 9 and 10 of Schedule IV of the Maharashtra Recognition of Trade Unions and Prevention of Unfair Labour Practices Act, 1971 for not implementing an award passed against its predecessor.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed the writ petition, upholding the Industrial Court's order dated 11 July 1996.

Law Points

  • Unfair labour practice
  • Non-implementation of award
  • Successor employer liability
  • Items 9 and 10 of Schedule IV
  • MRTU & PULP Act
  • 1971
Subscribe to unlock Law Points Subscribe Now

Case Details

2006 LawText (BOM) (09) 38

WRIT PETITION NO.5268 OF 1996

2006-09-19

Smt. Nishita Mhatre

Mr. A.M. Joshi for the Petitioner, Mrs. Suvarna Telgote for Mr. R.R. Salvi for Respondent No.1

Sharp Detectives Pvt. Ltd.

Babu D. Tribhuvan, Member, Industrial Court, Pune

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging the order of the Industrial Court holding the petitioner guilty of unfair labour practice for non-implementation of a Labour Court Award.

Remedy Sought

The petitioner sought to quash the Industrial Court's order dated 11 July 1996 in Complaint (ULP) No.211 of 1988.

Filing Reason

The petitioner was held to have engaged in unfair labour practice under Items 9 and 10 of Schedule IV of the MRTU & PULP Act by not implementing the Labour Court Award in Reference (IDA) No.103 of 1985.

Previous Decisions

The Labour Court passed an Award on 22 December 1986 in Reference (IDA) No.103 of 1985 in favour of the workman against M/s. International Security Services. The Industrial Court allowed the complaint under Items 9 and 10 of Schedule IV of the Act on 11 July 1996.

Issues

Whether the petitioner is a successor establishment liable to implement the award passed against its predecessor. Whether the non-implementation of the award constitutes an unfair labour practice under Items 9 and 10 of Schedule IV of the MRTU & PULP Act.

Submissions/Arguments

The petitioner argued that it was not a successor to M/s. International Security Services and was not bound by the award. The respondent workman contended that the petitioner had taken over the establishment and was liable to implement the award.

Ratio Decidendi

An employer who takes over an establishment is bound to implement an award passed against its predecessor, and failure to do so constitutes an unfair labour practice under Items 9 and 10 of Schedule IV of the MRTU & PULP Act.

Judgment Excerpts

The Industrial Court has held that the Petitioner had indulged in an unfair labour practice under Items 9 and 10 of Schedule IV of the Maharashtra Recognition of Trade Unions and Prevention of Unfair Labour Practices Act, 1971 by not implementing the Award passed by the Labour Court in Reference (IDA) No.103 of 1985.

Procedural History

The workman obtained an Award on 22 December 1986 in Reference (IDA) No.103 of 1985 against M/s. International Security Services. The workman filed Complaint (ULP) No.211 of 1988 under Items 9 and 10 of Schedule IV of the MRTU & PULP Act against the petitioner. The Industrial Court allowed the complaint on 11 July 1996. The petitioner filed the present writ petition challenging that order.

Acts & Sections

  • Maharashtra Recognition of Trade Unions and Prevention of Unfair Labour Practices Act, 1971: Schedule IV, Items 9 and 10
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging Industrial Court's Finding of Unfair Labour Practice for Non-Implementation of Labour Court Award. Employer Held Liable Under Items 9 and 10 of Schedule IV of MRTU & PULP Act for Failing to Implement A...
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging AICTE Approval Requirement for Management Courses. AICTE's jurisdiction under Section 10 of AICTE Act, 1987 extends to management courses even if conducted by medical trusts.