Bombay High Court Considers Maintainability Objection Under Section 42 of Arbitration and Conciliation Act, 1996 in Petition Challenging Arbitral Award. Preliminary Objection Centers on Whether Prior Section 9 Application in Baroda Court and Lack of Cause of Action Oust High Court's Jurisdiction to Entertain Section 34 Petition.

High Court: Bombay High Court Bench: BOMBAY
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Ion Exchange (India) Ltd., challenged an arbitral award directing it to pay certain amounts to the respondent, Paramount Limited, by filing a petition under Section 34 of the Arbitration and Conciliation Act, 1996, before the Bombay High Court. The respondent raised a preliminary objection to the maintainability of the petition on two grounds. First, the respondent relied on Section 42 of the Act, arguing that because it had previously filed an application under Section 9 of the Act before a Baroda court on 5 May 2005, all subsequent applications arising from the same arbitration agreement must be filed exclusively in that Baroda court. The second ground was that the Bombay High Court did not qualify as the ‘Court’ as defined in Section 2(e) of the Act since no part of the cause of action related to the dispute arose within its territorial jurisdiction. The petitioner opposed these objections. It contended that the application under Section 9 filed by the respondent after the award was not an application ‘with respect to the arbitration agreement’ but rather an application for enforcement of the award, as held in Kamal Pushpa Enterprises v. D.R. Construction Company, and therefore Section 42 did not apply. The petitioner also asserted that the respondent’s Section 9 application was not a bona fide application because notice of that application was served on the petitioner only after the expiry of the limitation period for filing a Section 34 petition – the award was made on 31 March 2005 and communicated on 6 April 2005, the last date for filing the petition was 7 July 2005, but notice of the Section 9 petition was served on 20 July 2005 (or according to the respondent, 14 July 2005). The petitioner relied on the Bombay High Court’s decision in HMP Engineers Ltd. v. Ralies India Ltd. to argue that the Limitation Act did not apply to Section 34 petitions, making timely intimation crucial. Further, the petitioner claimed that it had itself earlier moved an application under Section 11 of the Act before the Bombay High Court for constitution of the arbitral tribunal, and under the Supreme Court’s ruling in M/s. S.B.P. & Co. v. M/s. Patel Engineering Ltd., such an application made the Bombay High Court the exclusive court under Section 42. On the jurisdictional question, the petitioner argued that it carried on business in Mumbai, so a suit could have been filed in Bombay under the Letters Patent, satisfying the definition of ‘Court’. The judgment text records these contentions and the court begins to analyze Section 42 and Section 2(e) but ends abruptly without reaching a conclusion. The provided excerpt does not contain the final decision on the maintainability objection or the merits of the petition. The matter remains unresolved in the supplied portion.

Headnote

A) Arbitration – Jurisdiction – Section 42, Arbitration and Conciliation Act, 1996 – Prior Section 9 application filed after award – Whether subsequent Section 34 petition can be filed in a different court – Respondent argued that the Section 9 application filed in Baroda court ousted the jurisdiction of Bombay High Court under Section 42; Court examined the legal provisions and arguments; Held: The available text does not contain the court’s final ruling on this issue. (Paras 1-4)

B) Arbitration – Definition of ‘Court’ – Section 2(e), Arbitration and Conciliation Act, 1996 – Jurisdiction based on cause of action – Respondent contended that no part of cause of action arose within Bombay High Court’s jurisdiction; Petitioner argued that it carries on business in Mumbai, giving jurisdiction under Letters Patent; Court considered the contentions; Held: Decision not included in the provided excerpt. (Paras 1-4)

C) Arbitration – Nature of Section 9 application post-award – Section 9, Arbitration and Conciliation Act, 1996 – Whether application for security of award amount is with respect to arbitration agreement – Petitioner relied on Kamal Pushpa Enterprises v. D.R. Construction Company, AIR 2000 SC 2676 to argue such application is for enforcement of award, not under Part I with respect to agreement, hence not attracting Section 42; Held: Not determined in the available text. (Paras 2, 4)

D) Arbitration – Prior Section 11 application – Section 11, Arbitration and Conciliation Act, 1996 – Whether Chief Justice is a ‘Court’ under Section 42 – Petitioner relied on M/s. S.B.P. & Co. v. M/s. Patel Engineering Ltd., 2005(9) Scale 1 to argue that an earlier Section 11 application filed before this court makes it the exclusive forum under Section 42; Held: The court’s analysis is incomplete in the provided excerpt. (Paras 2, 4)

E) Arbitration – Bona fide application under Section 42 – Section 42, Arbitration and Conciliation Act, 1996 – Requirement of good faith – Petitioner argued that the Section 9 application was not bona fide because notice was served after the limitation period for filing Section 34 petition had expired, relying on HMP Engineers Ltd. v. Ralies India Ltd., 2003(4) Mh.L.J. 931 regarding non-applicability of Limitation Act to Section 34; Held: The court’s view on this point is not present in the supplied text. (Paras 2, 4)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Bombay High Court has jurisdiction to entertain the arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996, given that the respondent had earlier filed an application under Section 9 of the same Act in a Baroda court, and whether the petition is maintainable before this court under Section 42 of the Act.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Section 42 of the Arbitration and Conciliation Act
  • 1996
  • mandates that after an application under Part I is made in a court
  • that court alone shall have jurisdiction over all subsequent applications
  • 'Court' under Section 2(e) means the principal civil court having jurisdiction over the subject matter if a suit had been filed
  • An application under Section 9 filed after the arbitral award is an application for enforcement of the award
  • not with respect to the arbitration agreement
  • The provisions of Sections 4 to 24 of the Limitation Act
  • 1963
  • do not apply to petitions under Section 34 of the Arbitration and Conciliation Act
  • An application under Section 11 for appointment of arbitrator made to the Chief Justice is a court for the purpose of Section 42
  • A prior Section 9 application must be bona fide to trigger Section 42
  • and a party cannot be allowed to abuse the provision by filing a Section 9 application after the award without timely notice to the other side
  • Jurisdiction under Section 34 is determined by the court which would have jurisdiction over the subject matter as a suit.
Subscribe to unlock Law Points Subscribe Now

Case Details

2006 LawText (BOM) (06) 26

Arbitration Petition No.356 of 2005

2006-06-05

D.K. Deshmukh, J.

2006:BHC-OS:5528

Dr. V.V. Tulzapurkar, K.D.Parikh, V.Y.Divekar (for petitioner), Mr. Pradip Sancheti, Sanjay Jain (for respondent)

Ion Exchange (India) Ltd.

Paramount Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging the validity of an arbitral award.

Remedy Sought

Petitioner prayed for setting aside the arbitral award dated 31.3.2005 directing payment to the respondent.

Filing Reason

The arbitrator directed the petitioner to pay certain amounts to the respondent; the petitioner challenged the award on grounds including lack of jurisdiction and improper constitution of the tribunal.

Previous Decisions

Arbitral award made on 31.3.2005 in favour of respondent; earlier, petitioner had filed an application under Section 11 of the Act before the Bombay High Court for arbitral tribunal constitution; respondent filed an application under Section 9 before a Baroda court on 5.5.2005 seeking direction to secure the award amount.

Issues

Whether the Bombay High Court has jurisdiction to entertain the arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996, in view of the prior Section 9 application filed by the respondent in a Baroda court, given the provisions of Section 42 of the Act. Whether the Section 9 application filed after the award is an application 'with respect to the arbitration agreement' under Section 42, or merely an enforcement application. Whether the Section 9 application was a bona fide application, and whether the petitioner's lack of notice before the limitation expiry affects the application of Section 42. Whether the earlier Section 11 application filed by the petitioner before this court takes precedence under Section 42. Whether this court is the 'Court' as defined in Section 2(e) of the Act, having jurisdiction over the subject matter if a suit had been filed, given that no part of cause of action arose in Mumbai.

Submissions/Arguments

Respondent: The prior Section 9 application in Baroda court ousts the jurisdiction of this court under Section 42; all subsequent applications must be filed in Baroda; no cause of action arose in Mumbai, so this court is not the 'Court' under Section 2(e). Petitioner: The Section 9 application was not bona fide as notice was served after limitation for Section 34 petition expired; Section 42 requires a bona fide application and timely intimation; the Section 9 application after award is for enforcement, not with respect to the arbitration agreement; the earlier Section 11 application before this court makes it the exclusive court under Section 42; this court has jurisdiction because the petitioner carries on business in Mumbai, satisfying Letters Patent jurisdiction.

Judgment Excerpts

Section 42 of the Arbitration and Conciliation Act,1996, reads as under:- '42. Jurisdiction Notwithstanding anything contained elsewhere in this Part or in any other law for the time being in force, where with respect to an arbitration agreement any application under this Part has been made in a Court, that Court alone shall have jurisdiction over the arbitral proceedings and all subsequent applications arising out of that agreement and the arbitral proceedings shall be made in that Court and in no other Court.' '2(e) 'court' means the principal civil court of original jurisdiction in a district, and includes the High Court in exercise of its ordinary original civil jurisdiction, having jurisdiction to decide the questions forming the subject-matter of the arbitration if the same had been the subject-matter of a suit, but does not include any civil court of a grade inferior to such principal Civil Court, or any Court of Small Causes;' According to the petitioner, in view of the fact that the provisions of Section 4 to 24 of the Limitation Act are not applicable to the petition filed under Section 34 of the Act, Section 42 of the Act may be so read as to oblige the respondent to intimate the petitioner about the filing of application under Section 9 of the Act after the Award is made, immediately on filing the application so that the petitioner can arrange his business accordingly and can file his petition before that Court where application under Section 9 of the Act has been filed or take an informed decision about the Court in which he wants to file petition under Section 34 of the Act.

Procedural History

Arbitral award was made on 31.3.2005. Earlier, the petitioner had filed an application under Section 11 of the Arbitration and Conciliation Act before the Bombay High Court for constitution of the arbitral tribunal. On 5.5.2005, the respondent filed an application under Section 9 in a Baroda court seeking security for the award amount. The petitioner filed the present petition under Section 34 in the Bombay High Court on 29.6.2005. The respondent raised maintainability objections under Section 42 and the definition of 'Court' in the Act. The court heard arguments and was examining the provisions when the available text ends.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 2(e), 9, 11, 34, 42
  • Limitation Act, 1963: 4, 24
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Considers Maintainability Objection Under Section 42 of Arbitration and Conciliation Act, 1996 in Petition Challenging Arbitral Award. Preliminary Objection Centers on Whether Prior Section 9 Application in Baroda Court and Lack of ...
Related Judgement
Supreme Court Supreme Court Allows Appeal in Property Dispute Over Void Sale Deeds and Limitation Bar. Court Holds Sale Deeds Void for Lack of Consideration and Suits Within Limitation as Original Plaint Challenged Validity, Setting Aside High Court Order Under Li...