Bombay High Court Allows Appeal in Land Acquisition Case — Compensation Under Section 23(1-A) and Interest Cannot Be Awarded from Date Prior to Section 4 Notification. The court held that additional compensation under Section 23(1-A) and interest on solatium must be calculated from the date of Section 4 notification, not from the date of prior possession.

High Court: Bombay High Court Bench: GOA In Favour of Prosecution
  • 68
Judgement Image
Font size:
Print

Case Note & Summary

The case arises from a land acquisition proceeding under the Land Acquisition Act, 1894 (the Act). The appellants, the Deputy Collector (L.A.)/MPT and the Executive Engineer, Public Works Department, challenged the Award dated 24.09.2007 passed by the Reference Court (Civil Judge, Senior Division) in a land acquisition reference. The respondents, Tome Carvalho and others, were the landowners whose land was acquired. Possession of the land was taken on 14.09.1998, prior to the issuance of the Section 4 notification under the Act. The Reference Court, while deciding issue nos. 4 and 5, concluded that additional compensation under Section 23(1-A) of the Act and interest on solatium should be paid from the date of possession (14.09.1998) rather than from the date of the Section 4 notification. The appellants contended that this was erroneous and contrary to the scheme of the Act, as compensation is to be determined as on the date of the Section 4 notification. The appellants relied on Supreme Court judgments in Siddappa Vasappa Kuri v. Spl. Land Acquisition Officer (AIR 2001 SC 2951) and R. L. Jain v. D. D. A. (AIR 2004 SC 1904), which overruled the earlier decision in Asst. Commissioner v. Mathapathi Basavannewwa (AIR 1995 SC 2492) that the Reference Court had relied upon. The respondents did not appear despite service. The High Court framed the point for determination: whether the Reference Court was justified in awarding compensation under Section 23(1-A) and interest from 14.09.1998, prior to the Section 4 notification. The court analyzed the scheme of the Act and the cited precedents, holding that the scheme contemplates compensation determined as on the date of the Section 4 notification. Therefore, additional compensation under Section 23(1-A) and interest on solatium cannot be awarded from a date prior to the Section 4 notification. The court allowed the appeal, set aside the impugned award to the extent it directed payment from 14.09.1998, and directed that the amounts be paid from the date of the Section 4 notification. No order as to costs.

Headnote

A) Land Acquisition - Compensation under Section 23(1-A) - Date from which payable - The issue was whether additional compensation under Section 23(1-A) of the Land Acquisition Act, 1894 should be paid from the date of possession (prior to Section 4 notification) or from the date of Section 4 notification. The court held that the scheme of the Act contemplates compensation determined as on the date of Section 4 notification, and therefore additional compensation under Section 23(1-A) and interest on solatium cannot be awarded from a date prior to the Section 4 notification. The Reference Court's award to that extent was set aside. (Paras 2-6)

B) Land Acquisition - Interest on solatium - Date from which payable - The court held that interest on solatium under Section 28 of the Land Acquisition Act, 1894 is also payable from the date of Section 4 notification, not from the date of prior possession. The Reference Court's direction to pay interest from 14.09.1998 (date of possession) was erroneous. (Paras 3-6)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Reference Court was justified to award compensation under Section 23(1-A) as well as interest from 14.09.1998 which is prior to Section 4 Notification under the Land Acquisition Act, 1894.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is allowed. The impugned Judgment and Award dated 24.09.2007 passed by the Reference Court is set aside to the extent it directed payment of compensation under Section 23(1-A) and interest on solatium from 14.09.1998. It is directed that the said amounts shall be paid from the date of Section 4 notification under the Land Acquisition Act, 1894. No order as to costs.

Law Points

  • Compensation under Section 23(1-A) of the Land Acquisition Act
  • 1894 is payable from the date of Section 4 notification
  • not from the date of prior possession
  • Interest on solatium under Section 28 of the Land Acquisition Act
  • 1894 is also payable from the date of Section 4 notification
  • The scheme of the Land Acquisition Act contemplates compensation determined as on the date of Section 4 notification
Subscribe to unlock Law Points Subscribe Now

Case Details

2013 LawText (BOM) (09) 136

First Appeal No. 133 of 2008

2013-09-03

F. M. REIS, J

Mr. Vivek Rodrigues, Addl. Government Advocate for the Appellants

The Deputy Collector (L.A.)/MPT, Marmugao, Sada; The Executive Engineer, Works Division VI (R-S), Public Works Department, Fatorda, Margao, Goa

Tome Carvalho, Smt. Maria dos Anjos Carvalho, Maria Pio S. Carvalho, Savio Baptista Carvalho, Smt. Maria Aldina Saldana Carvalho, Dionisio N. F. Carvalho, Smt. Sarina Carvalho, Maria E. L. Carvalho, Edmundo S. N. Carvalho, Felicia Isabel Carvalho, Antonio Ivo Carvalho, Chagas Pia Carvalho

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against an award of the Reference Court in a land acquisition matter.

Remedy Sought

The appellants sought to set aside the part of the Reference Court's award that directed payment of additional compensation under Section 23(1-A) and interest on solatium from the date of possession (14.09.1998) instead of from the date of Section 4 notification.

Filing Reason

The appellants contended that the Reference Court misinterpreted the provisions of the Land Acquisition Act, 1894 by awarding compensation under Section 23(1-A) and interest from a date prior to the Section 4 notification.

Previous Decisions

The Reference Court passed an award on 24.09.2007 deciding issue nos. 4 and 5 in favor of the respondents, directing payment from the date of possession (14.09.1998).

Issues

Whether the Reference Court was justified to award compensation under Section 23(1-A) as well as interest from 14.09.1998 which is prior to Section 4 Notification under the Land Acquisition Act, 1894.

Submissions/Arguments

The learned Addl. Government Advocate for the appellants submitted that the Reference Court misinterpreted the provisions of the Act by awarding compensation under Section 23(1-A) and interest on solatium from the date of possession (14.09.1998) instead of from the date of Section 4 notification. He argued that the scheme of the Act contemplates compensation determined as on the date of Section 4 notification, and the Supreme Court in Siddappa Vasappa Kuri and R. L. Jain has overruled the earlier decision in Mathapathi Basavannewwa relied upon by the Reference Court.

Ratio Decidendi

Under the scheme of the Land Acquisition Act, 1894, compensation is to be determined as on the date of the Section 4 notification. Therefore, additional compensation under Section 23(1-A) and interest on solatium under Section 28 cannot be awarded from a date prior to the Section 4 notification, even if possession was taken earlier.

Judgment Excerpts

The learned Addl. Government Advocate pointed out that it has been held by the Apex Court that the question of awarding any interest on damages prior to the Notification under Section 4 of the said Act does not arise as the scheme of the said Act contemplates that compensation is to be determined as on the date of Section 4 Notification. The scheme of the said Act contemplates that compensation is to be determined as on the date of Section 4 Notification.

Procedural History

The Reference Court (Civil Judge, Senior Division) passed an Award on 24.09.2007 in a land acquisition reference, deciding issue nos. 4 and 5 in favor of the respondents. The appellants, being aggrieved, filed First Appeal No. 133 of 2008 before the High Court of Bombay at Goa. The High Court heard the appeal on 03.09.2013 and allowed it, modifying the award.

Acts & Sections

  • Land Acquisition Act, 1894: Section 23(1-A), Section 28, Section 4
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Appeal in Land Acquisition Case — Compensation Under Section 23(1-A) and Interest Cannot Be Awarded from Date Prior to Section 4 Notification. The court held that additional compensation under Section 23(1-A) and interest o...
Related Judgement
High Court Bombay High Court Dismisses PIL Seeking Investigation into MLA's Assets for Lack of Credible Material. Court holds that mere allegations of disproportionate assets without prima facie evidence cannot justify investigation under Prevention of Corrupti...