Case Note & Summary
The appeal arises from a decision of a learned Single Judge dated 4 April 2012 dismissing a petition under Section 34 of the Arbitration and Conciliation Act, 1996 filed by the appellant, Hindustan Petroleum Corporation Ltd., challenging an arbitral award dated 4 November 2009. The appellant had floated a global tender for six Reactors with S.S. Clading for a Green Fuels Project. The first respondent, M/s. ISGEC, submitted a bid and a Purchase Order was placed on 1 June 2005 for a contract value of Rs.14,50,10,000/-. The contract contained a condition that the price mentioned in the Purchase Order shall remain firm and fixed till complete execution. Disputes arose and were referred to arbitration. The first respondent raised two claims: Claim no.1 for Rs.60,93,323/- which was withheld by the appellant, and Claim no.2 for a deduction of Rs.14.80 lakhs on account of delayed delivery. The appellant also raised a counter claim. The Arbitral Tribunal allowed Claim no.1, rejected Claim no.2, and rejected the counter claim. The appellant challenged the award under Section 34, which was dismissed by the learned Single Judge. In appeal, the appellant contested the decision on two aspects: the grant of Claim no.1 and the rejection of the counter claim. The court held that the scope of interference under Section 34 is limited to grounds of public policy, patent illegality, or perversity. The arbitral tribunal's findings on factual issues and contractual interpretation are not open to reappreciation. The tribunal's interpretation of the firm price condition was plausible and not perverse. Regarding the counter claim, the court found no ground to interfere as the tribunal's decision was based on appreciation of evidence and contractual terms. The appeal was dismissed.
Headnote
A) Arbitration - Section 34 of Arbitration and Conciliation Act, 1996 - Scope of Judicial Review - Challenge to arbitral award on merits - The court held that the scope of interference under Section 34 is limited to grounds of public policy, patent illegality, or perversity. The arbitral tribunal's findings on factual issues and contractual interpretation are not open to reappreciation by the court. (Paras 6-10) B) Contract Law - Firm Price Condition - Interpretation of Contract - Withholding of Payment - The contract contained a condition that the price mentioned in the Purchase Order shall remain firm and fixed till complete execution. The arbitral tribunal allowed the claim for payment of withheld amount of Rs.60,93,323/-. The court upheld the award, holding that the tribunal's interpretation of the contract was plausible and not perverse. (Paras 6-8) C) Arbitration - Counter Claim - Rejection by Arbitral Tribunal - The appellant's counter claim was rejected by the arbitral tribunal. The court found no ground to interfere as the tribunal's decision was based on appreciation of evidence and contractual terms. (Para 9)
Issue of Consideration
Whether the learned Single Judge erred in dismissing the petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging the arbitral award which allowed claim no.1 for payment of withheld amount and rejected the counter claim.
Final Decision
The appeal is dismissed. The decision of the learned Single Judge dated 4 April 2012 dismissing the petition under Section 34 of the Arbitration and Conciliation Act, 1996 is upheld. The arbitral award dated 4 November 2009 is not interfered with.
Law Points
- Arbitration
- Section 34 of Arbitration and Conciliation Act
- 1996
- Scope of judicial review
- Contractual interpretation
- Withholding of payments
- Counter claim
- Firm price condition





