Case Note & Summary
The petitioner, Karam Chand Thapar & Bros. (Coal Sales) Ltd., filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking an injunction to restrain the respondent, Hindustan Construction Company Limited, from encashing a performance bank guarantee of Rs. 15.95 crores issued by HSBC Bank on behalf of the petitioner, and also sought return of the bank guarantee. The dispute arose out of a contract awarded by Sardar Sarovar Narmada Nigam Limited to the respondent for construction work. The respondent had sub-contracted part of the work to the petitioner, and the petitioner had furnished the bank guarantee as performance security. The respondent invoked the bank guarantee due to alleged delays and deficiencies in the petitioner's performance. The petitioner contended that the invocation was fraudulent and that there were disputes in the underlying contract. The court held that a bank guarantee is an independent contract and the beneficiary is entitled to encash it according to its terms. The court noted that the exceptions of fraud or irretrievable injustice were not made out. The court also considered the concept of 'special equities' but found no such equities in favor of the petitioner. The petition was dismissed, and the respondent was allowed to encash the bank guarantee.
Headnote
A) Arbitration - Interim Measures - Section 9 of Arbitration and Conciliation Act, 1996 - Injunction against encashment of bank guarantee - The court considered whether an injunction can be granted to restrain encashment of a performance bank guarantee. Held that a bank guarantee is an independent contract between the bank and the beneficiary, and the court should not interfere except in cases of fraud or irretrievable injustice. The petitioner failed to establish either exception. (Paras 1-26) B) Contract Law - Performance Bank Guarantee - Independence Principle - The court reiterated that a performance bank guarantee is a separate contract and the beneficiary is entitled to realize it according to its terms. The court cannot restrain encashment merely because of disputes in the underlying contract. (Paras 10-15) C) Arbitration - Special Equities - Section 9 of Arbitration and Conciliation Act, 1996 - The court examined the concept of 'special equities' as an exception to the rule against injunction. Held that special equities must be such as to make it impossible for the guarantor to reimburse himself if the guarantee is invoked, which was not shown. (Paras 16-20)
Issue of Consideration
Whether the petitioner is entitled to an injunction restraining the respondent from encashing the performance bank guarantee and for return of the bank guarantee under Section 9 of the Arbitration and Conciliation Act, 1996.
Final Decision
The petition is dismissed. The respondent is allowed to encash the performance bank guarantee.
Law Points
- Bank guarantee is an independent contract
- fraud exception
- irretrievable injustice exception
- special equities
- Section 9 of Arbitration and Conciliation Act
- 1996




