Patel Engineering Co. Ltd (PEC) challenged an arbitral award dated 25 January 2010 under Section 34 of the Arbitration and Conciliation Act, 1996 in the High Court of Bombay. The background involved a main contract awarded by the State of Maharashtra to PEC for civil work at the Koyana Hydro Electric Project in 1992. PEC entered into a subcontract agreement with B.T. Patil & Sons Belgaum (Construction) Pvt. Ltd (BTP) and a piece work agreement with BTP's sister concern SBP & Co. The agreements provided that BTP and SBP would execute work at rates less 11.5% margin for PEC, and any claims received from the employer would be passed on after deducting the margin. Disputes arose, and an arbitral tribunal was constituted. The tribunal awarded various amounts to BTP and SBP on claims relating to work done, escalation, illegal deductions, and interest at 18% p.a. The operative part of the award detailed computations for Volumes I, II, IV, V, and other heads. PEC, aggrieved by the award, filed the arbitration petition seeking to set it aside. The High Court's oral judgment set out the grounds of challenge and the operative part of the award, but the text provided does not include the court's analysis, reasoning, or final decision. The petition was heard and reserved on 22 February 2013, and pronounced on 21 March 2013.

Issue of Consideration

Whether the arbitral award dated 25 January 2010 should be set aside under Section 34 of the Arbitration and Conciliation Act, 1996?

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Arbitration award challenge
  • Section 34
  • Arbitration and Conciliation Act
  • 1996
  • subcontract agreement
  • piece work contract
  • margin/commission of 11.5%
  • interest at 18% p.a.
Subscribe to unlock Law Points Subscribe Now

Case Details

2013 LawText (BOM) (04) 89

Arbitration Petition No. 891 of 2010

2013-03-21

Anoop V. Mohta, J.

Aspi Chinoy, F. E. De Vitre, Mustafa Doctor, Nirmay Dave, Uday Hola, N. V. Bandivadekar, Sagar Mane

Patel Engineering Co. Ltd

B.T. Patil & Sons Belgaum (Construction) Pvt. Ltd

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

Petitioner (Patel Engineering Co. Ltd) sought to set aside the arbitral award dated 25 January 2010.

Filing Reason

Petitioner was aggrieved by the award that granted substantial claims to the Respondent subcontractor.

Previous Decisions

An arbitral tribunal passed an award dated 25 January 2010 in favor of the Respondent, granting various amounts for work done, escalation, and interest.

Issues

Whether the arbitral award is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

The Petitioner (Original Respondent) has challenged Award dated 25 January 2010, under section 34 of Arbitration and Conciliation Act, 1996. On 10 March 1992, PEC was awarded a contract by the State of Maharashtra for civil work pertaining to State IV of Koyana Hydro Electric Project. On 15 October 1992, PEC entered into a subcontract agreement with the Respondents B.T. Patil and Sons Belgaum (Construction) Private Limited for a portion of the work and with the BTP's sister concern SBP & Co., a Piece work Agreement.

Procedural History

On 10 March 1992, PEC awarded main contract by State of Maharashtra. On 15 October 1992, PEC entered into subcontract agreement with BTP and piece work agreement with SBP. Disputes arose; arbitration proceedings initiated. Arbitral tribunal passed award on 25 January 2010. PEC challenged the award under Section 34 of Arbitration and Conciliation Act, 1996 by filing Arbitration Petition No. 891 of 2010 in High Court of Bombay. Court heard arguments and reserved judgment on 22 February 2013; pronounced on 21 March 2013.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
  • Companies Act, 1956:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Conviction of Appellant in Abduction and Rape Case Under Indian Penal Code. Abduction by Threat and Rape of Minor Under 16 Upheld as Penetration Sufficient and Consent Immaterial Under Sections 362, 366, 375 IPC.
Related Judgement
Supreme Court Supreme Court Upholds Scheduled Caste Lessee's Right to Regularization of Nazool Land in Punjab by Setting Aside Eviction Orders. Eviction of Lessee Who Reclaimed Waste Land and Remained in Possession After Lease Expiry Held Unjustified as Economic E...