Case Note & Summary
The State of Maharashtra, through the Executive Engineer, Public Works Division, Miraj, filed two appeals under Section 37 of the Arbitration and Conciliation Act, 1996, challenging a judgment and order dated 4th November 2008 passed by the learned District Judge-2, Sangli. The District Judge had partly allowed the appeals against an arbitral award, upholding claims nos. 1A to 1E and allowing claims nos. 2 and 3. The underlying dispute arose from a contract dated 4th March 1999 between the State and M/s Ashoka Buildcon Limited for the construction of a major bridge across the Krishna River on a Build, Operate and Transfer (BOT) basis. The work was completed on 22nd February 2000, before the stipulated completion date of 3rd March 2001, and a provisional completion certificate was issued. Disputes arose regarding extra items/additional work carried out by the contractor, leading to claims. The arbitrator awarded certain claims, which the State challenged before the District Judge. The District Judge partly set aside the award but upheld the claims for extra work and interest. The State appealed, arguing that the arbitrator had no jurisdiction to award extra work and that the interest awarded was excessive. The High Court, after considering the submissions, held that the District Judge had correctly applied the law. The court noted that the arbitrator had jurisdiction to decide on extra work under the contract and that the findings were based on evidence. Regarding interest, the court found that the arbitrator had discretion to award interest and that the rate was not excessive. The appeals were dismissed, and the judgment of the District Judge was upheld.
Headnote
A) Arbitration Law - Appeal under Section 37 - Scope of Interference - The court considered the limited scope of appeal against an order setting aside or refusing to set aside an arbitral award under Section 37 of the Arbitration and Conciliation Act, 1996. The court held that the District Judge had correctly applied the principles that an arbitral award can be interfered with only on grounds specified in Section 34 of the Act, and that the arbitrator's interpretation of contract clauses is final unless perverse. (Paras 1-10) B) Contract Law - Extra Work - Claim for Additional Work - The dispute pertained to extra items/additional work carried out by the contractor beyond the original scope of the BOT contract. The arbitrator awarded claims for extra work based on contractual clauses and evidence. The court upheld the award, finding that the arbitrator had jurisdiction to decide on extra work and that the findings were not without evidence. (Paras 11-20) C) Interest - Award of Interest - The arbitrator awarded interest on the amounts due. The court upheld the award of interest, noting that the contract did not prohibit interest and that the arbitrator had discretion to award interest under the Interest Act, 1978 and the Arbitration Act. (Paras 21-25)
Issue of Consideration
Whether the learned District Judge erred in allowing the appeals under Section 37 of the Arbitration and Conciliation Act, 1996, and upholding the arbitral award on claims for extra work and interest.
Final Decision
The appeals are dismissed. The judgment and order dated 4th November 2008 passed by the learned District Judge-2, Sangli is upheld.
Law Points
- Arbitration Act
- 1996
- Section 37
- Scope of Appeal
- Arbitral Award
- Extra Work
- Interest
- BOT Contract
- Jurisdiction of Arbitrator
- Interpretation of Contract




