Case Note & Summary
The State of Maharashtra, through the Irrigation Department, filed an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, challenging an order of the learned District Judge, Ratnagiri, dated 29 June 2006, which rejected the Government's application under Section 34 of the Act to set aside an arbitral award. The dispute arose from a construction contract awarded to Hindustan Construction Company (HCC) for civil works of a pressure and power house. The contract was awarded on 20 March 1992 with a stipulated completion date of 19 March 1997, but was extended to 31 March 2000. During execution, disputes arose regarding hidden expenses, leading to arbitration. The Arbitral Tribunal partly allowed HCC's claims, and the Government paid Rs.10.2 crore without challenge. Subsequently, further disputes led to a second arbitration, resulting in an award in favor of HCC. The Government challenged this award under Section 34, which was dismissed by the District Judge. The High Court, in this appeal, examined whether the District Judge erred in rejecting the challenge. The court held that the award was not contrary to public policy, the arbitrator's findings on hidden expenses and interest were based on evidence, and no interference was warranted under Section 34. The appeal was dismissed, upholding the District Judge's order.
Headnote
A) Arbitration Law - Challenge to Arbitral Award under Section 34 - Public Policy - The court considered whether the arbitral award was contrary to public policy under Section 34 of the Arbitration and Conciliation Act, 1996 - Held that the award did not violate public policy and the District Judge correctly rejected the challenge (Paras 2-10). B) Arbitration Law - Interest on Delayed Payments - The court examined the award of interest on delayed payments to the contractor - Held that the arbitrator's discretion to award interest was not perverse and was within the scope of the contract (Paras 11-15). C) Arbitration Law - Hidden Expenses - The court considered the claim for hidden expenses in a construction contract - Held that the arbitrator's findings on hidden expenses were based on evidence and not liable to be interfered with under Section 34 (Paras 16-20).
Issue of Consideration
Whether the learned District Judge erred in rejecting the Government's application under Section 34 of the Arbitration and Conciliation Act, 1996 challenging the arbitral award on grounds of public policy and erroneous findings.
Final Decision
The appeal is dismissed. The order of the learned District Judge, Ratnagiri dated 29 June 2006 rejecting the Government's application under Section 34 of the Arbitration and Conciliation Act, 1996 is upheld.
Law Points
- Section 37 of Arbitration and Conciliation Act
- 1996
- Section 34 of Arbitration and Conciliation Act
- Public policy
- Interest on delayed payments
- Hidden expenses in construction contracts





