Case Note & Summary
The Petitioner, Oil and Natural Gas Corporation Limited (ONGC), challenged an arbitral award dated 12 November 2009 passed by the Arbitral Tribunal constituted under a Memorandum of Understanding (MOU) dated 7 October 1999. The Tribunal had rejected ONGC's claim against Reliance Energy Limited on the ground of limitation. The dispute arose from pre-project activities undertaken by ONGC under the MOU, for which ONGC claimed reimbursement of expenses. The Tribunal found that the expenditure was incurred prior to 18th April 2001, and the claim was raised beyond the three-year limitation period prescribed under the Limitation Act, 1963. The Tribunal also held that the claim based on the principle of quantum meruit was similarly time-barred. ONGC filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging the award. The High Court, after considering the submissions, upheld the award, finding no error of law or fact that warranted interference. The Court noted that the Tribunal's conclusion on limitation was based on the admitted fact that the expenses were incurred before 18th April 2001, and the claim was made after the expiry of the limitation period. The petition was dismissed.
Headnote
A) Arbitration - Limitation - Bar of Limitation - Section 34 of Arbitration and Conciliation Act, 1996 read with Limitation Act, 1963 - The Arbitral Tribunal rejected the claimant's claim for pre-project expenses as barred by limitation, holding that the expenditure was incurred prior to 18th April 2001 and the claim was raised beyond the three-year period. The Court upheld the award, finding no ground for interference under Section 34. (Paras 2-3)
B) Contract - Quantum Meruit - Limitation - Limitation Act, 1963 - The claim based on quantum meruit was also held barred by limitation as the expenditure was incurred prior to 18th April 2001. The Court affirmed that the principle of quantum meruit does not extend the limitation period. (Paras 2-3)
Issue of Consideration
Whether the Arbitral Tribunal erred in rejecting the claimant's claim on the ground of limitation, and whether the claim based on quantum meruit was also barred by limitation.
Final Decision
The High Court dismissed the Arbitration Petition, upholding the arbitral award dated 12 November 2009.
Law Points
- Limitation period for claims under arbitration
- Principle of quantum meruit
- Section 34 of Arbitration and Conciliation Act
- 1996
- Application of Limitation Act
- 1963 to arbitral proceedings
Case Details
2013 LawText (BOM) (01) 61
Arbitration Petition No. 905 of 2010
Mr. S.U. Kamdar, Senior Advocate a/w Mr. Naushad Engineer, with Ms. Pooja Patil, Mr. J.P. Kapadia i/by M/s. Little & Co. for the Petitioner. Mr. J.J. Bhatt, Senior Advocate a/w Ms. Anjali Chandurkar, D.K. Kaklia, Mr. Dhishan Kukreja, Ms. Kalyani Chandurkar i/by M/s. Mulla and Mulla for the Respondent.
Oil and Natural Gas Corporation Limited
Subscribe to unlock Case Details (Citation, Judge, Date & more)
Subscribe Now
Nature of Litigation
Challenge to arbitral award under Section 34 of Arbitration and Conciliation Act, 1996
Remedy Sought
Petitioner sought setting aside of the arbitral award dated 12 November 2009
Filing Reason
Arbitral Tribunal rejected claimant's claim on ground of limitation
Previous Decisions
Arbitral Tribunal held claim barred by limitation and rejected claim
Issues
Whether the Arbitral Tribunal erred in rejecting the claim as barred by limitation?
Whether the claim based on quantum meruit was also barred by limitation?
Submissions/Arguments
Petitioner argued that the claim was not barred by limitation and the Tribunal erred.
Respondent supported the award, contending that the claim was clearly time-barred.
Ratio Decidendi
The claim for pre-project expenses under the MOU was barred by limitation as the expenditure was incurred prior to 18th April 2001 and the claim was raised beyond the three-year period. The principle of quantum meruit does not extend the limitation period. The Arbitral Tribunal's conclusion was based on admitted facts and no interference under Section 34 was warranted.
Judgment Excerpts
The conclusion of the learned Arbitral Tribunal is as under: '19. In view of the Arbitral Tribunal holding that the Claimant's claim is barred by law of limitation, the Claimant is not entitled to any relief against the Respondent in the present arbitral reference. The claimant's claim against the Respondent even on the basis of principle of quantum meruit is also barred by law of limitation since admittedly the expenditure incurred by the Claimant on preproject activities were incurred prior to 18th April 2001.'
Procedural History
The Petitioner (original Claimant) filed a claim before the Arbitral Tribunal under the MOU dated 7 October 1999. The Tribunal passed an award on 12 November 2009 rejecting the claim on limitation. The Petitioner then filed Arbitration Petition No. 905 of 2010 under Section 34 of the Arbitration and Conciliation Act, 1996 before the Bombay High Court, which dismissed the petition on 9 January 2013.
Acts & Sections
- Arbitration and Conciliation Act, 1996: Section 34
- Limitation Act, 1963:
- Companies Act, 1956: