Bombay High Court Dismisses Appeal Against Arbitral Tribunal's Interim Order in Charter Hire Dispute. Section 37 of the Arbitration and Conciliation Act, 1996 Does Not Provide for Appeal Against Interim Orders Under Section 17 of the Act.

High Court: Bombay High Court
  • 58
Judgement Image
Font size:
Print

Case Note & Summary

The case involves an appeal filed by Oil and Natural Gas Corporation Ltd. (ONGC) under Section 37 of the Arbitration and Conciliation Act, 1996, challenging an interim order dated 9th August, 2004 passed by the Arbitral Tribunal. The dispute arose from a tender invited by ONGC in July 1999 for the charter hire of a jack-up rig. Five bidders responded, including the respondent, Jagson Intl. Ltd., and M/s. Neptune Exploration and Industries Ltd. Both the respondent and M/s. Neptune offered the same rigs, 'Sakhalinskaya' and 'Kurilskaya'. ONGC sought clarifications and confirmations regarding the availability of the rigs. The respondent provided a letter from the rig owners, M/s. Osneft Sakhalinmorneftegaz, dated 8th December, 1999. ONGC then issued a letter on 22nd December, 1999, asking the respondent to confirm continued availability of the rig 'Sakhalinskaya' and provide details for 'Kurilskaya' with documentary proof, as M/s. Neptune's details differed. The Arbitral Tribunal passed an interim order under Section 17 of the Act. ONGC appealed this order under Section 37. The court examined the maintainability of the appeal. It noted that Section 37 of the Act specifies the orders against which an appeal lies, including orders granting or refusing to grant interim measures under Section 9. However, there is no provision for an appeal against an interim order passed by the Arbitral Tribunal under Section 17. The court held that the appeal was not maintainable and dismissed it. The court did not address the merits of the interim order.

Headnote

A) Arbitration Law - Appeal against interim order of Arbitral Tribunal - Section 37 of the Arbitration and Conciliation Act, 1996 - Maintainability - The appellant challenged an interim order dated 9th August, 2004 passed by the Arbitral Tribunal under Section 17 of the Act. The court held that Section 37 of the Act does not provide for an appeal against an interim order passed under Section 17. The only appealable orders under Section 37 are those granting or refusing to grant interim measures under Section 9 of the Act. Therefore, the appeal was not maintainable and was dismissed. (Paras 1-5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 lies against an interim order passed by the Arbitral Tribunal under Section 17 of the Act.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is dismissed as not maintainable. No order as to costs.

Law Points

  • Section 37 of the Arbitration and Conciliation Act
  • 1996 does not provide for an appeal against an interim order passed under Section 17 of the Act
  • Section 17 of the Arbitration and Conciliation Act
  • 1996 empowers the arbitral tribunal to pass interim orders
  • 1996 only provides for appeals against orders granting or refusing to grant interim measures under Section 9 of the Act
Subscribe to unlock Law Points Subscribe Now

Case Details

2005:BHC-AS:12560

Arbitration Appeal No. 1 of 2005

2005-07-15

D.K. Deshmukh, J.

2005:BHC-AS:12560

Shri Rajiv Kumar i/b Divya Shah & Associates for the Appellants, Shri Janak Dwarkadas i/b Mr. Ashwin Shankar for the Respondents

Oil and Natural Gas Corporation Ltd.

M/s. Jagson Intl. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37 of the Arbitration and Conciliation Act, 1996 against an interim order passed by the Arbitral Tribunal under Section 17 of the Act.

Remedy Sought

The appellant sought to challenge the interim order dated 9th August, 2004 passed by the Arbitral Tribunal.

Filing Reason

The appellant was aggrieved by the interim order of the Arbitral Tribunal and sought to appeal against it.

Previous Decisions

The Arbitral Tribunal passed an interim order under Section 17 of the Arbitration and Conciliation Act, 1996 on 9th August, 2004.

Issues

Whether an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 lies against an interim order passed by the Arbitral Tribunal under Section 17 of the Act.

Submissions/Arguments

The appellant argued that the appeal was maintainable under Section 37 of the Act. The respondent contended that no appeal lies against an interim order under Section 17 of the Act.

Ratio Decidendi

Section 37 of the Arbitration and Conciliation Act, 1996 does not provide for an appeal against an interim order passed by the Arbitral Tribunal under Section 17 of the Act. The only appealable orders under Section 37 are those granting or refusing to grant interim measures under Section 9 of the Act.

Judgment Excerpts

By this Appeal filed under Section 37 of the Arbitration & Conciliation Act, the Appellants challenge the order dated 9th August, 2004 passed by the Arbitral Tribunal. Section 37 of the Act does not provide for an appeal against an interim order passed under Section 17 of the Act.

Procedural History

The Arbitral Tribunal passed an interim order under Section 17 of the Arbitration and Conciliation Act, 1996 on 9th August, 2004. The appellant filed an appeal under Section 37 of the Act before the High Court of Judicature at Bombay on an unspecified date. The High Court heard the appeal and dismissed it on 15th July, 2005.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 17, Section 37, Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Appeal Against Arbitral Tribunal's Interim Order in Charter Hire Dispute. Section 37 of the Arbitration and Conciliation Act, 1996 Does Not Provide for Appeal Against Interim Orders Under Section 17 of the Act.
Related Judgement
High Court Gujarat High Court Dismisses Appeal Seeking Enhanced Compensation in Motor Accident Claim - Tribunal's Award Upheld as Higher Than Recalculated Amount. The Court recalculated compensation based on minimum wages and correct multiplier but found the Tr...