Bombay High Court Dismisses Municipal Council's Appeal in Contract Recovery Suit — Limitation Period Under Article 18 of Limitation Act Runs from Completion of Work, Not from Demand or Refusal. The court upheld the trial court's decree for balance payment for work completed on 22.5.1990, as the suit filed in 1993 was within the three-year limitation period under Article 18 of the Limitation Act, 1963.

High Court: Bombay High Court In Favour of Prosecution
  • 168
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, Alibag Nagar Parishad (Municipal Council), challenged the judgment and decree of the Civil Judge, Senior Division, Raigad at Alibag in Special Civil Suit No.39 of 1993, which decreed the suit filed by the respondent-contractor for recovery of Rs.4,21,000/- with interest at 15% per annum and costs. The respondent had been awarded a contract by the appellant through tenders and completed the work on 22.5.1990. He claimed a total sum of Rs.8,20,000/- was payable, out of which he had received Rs.5,50,000/-, leaving a balance. The appellant resisted the suit on several grounds, including limitation. The trial court framed Issue No.5 on limitation and decided it against the appellant, awarding the claim. In appeal, the appellant's counsel raised only two submissions: that the suit was barred by limitation under Article 18 of the Limitation Act, 1963, as the work was completed on 22.5.1990 and the suit was filed beyond three years, and that the cause of action arose on the date of completion. The High Court examined Article 18, which prescribes a three-year period for the price of work done by the plaintiff for the defendant at his request, where no time is fixed, and the period begins when the work is done. The court noted that the work was completed on 22.5.1990 and the suit was filed in 1993, which is within three years. The court held that the cause of action arises on the date of completion of work, not on the date of demand or refusal. Therefore, the suit was within limitation. The court found no merit in the appeal and dismissed it with no order as to costs.

Headnote

A) Limitation Act - Article 18 - Price of Work Done - Period of Limitation - The period of three years for filing a suit for the price of work done by the plaintiff for the defendant at his request, where no time is fixed, begins when the work is done. The court held that the cause of action arises on the date of completion of work, not on the date of demand or refusal. (Para 3)

B) Limitation Act - Article 18 - Applicability to Contract Work - The suit for recovery of balance payment for construction work completed on 22.5.1990, filed in 1993, is within limitation as the work was completed within three years of filing. The trial court's finding on limitation was upheld. (Para 3)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the suit for recovery of balance payment for work done is barred by limitation under Article 18 of the Limitation Act, 1963, when the work was completed on 22.5.1990 and the suit was filed in 1993.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal dismissed. The trial court's decree is upheld. No order as to costs.

Law Points

  • Limitation period for recovery of price of work done runs from completion of work under Article 18 of Limitation Act
  • 1963
  • not from subsequent demand or refusal
Subscribe to unlock Law Points Subscribe Now

Case Details

2005 LawText (BOM) (02) 298

First Appeal No.998 of 1994

2005-02-07

D.G.Deshpande

Mr.C.G.Gavnekar for the appellant

Alibag Nagar Parishad

Messrs. D.D.Hajare

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against decree in suit for recovery of balance payment for work done under contract.

Remedy Sought

Appellant (Alibag Nagar Parishad) sought dismissal of the suit as barred by limitation.

Filing Reason

Respondent contractor filed suit for recovery of Rs.4,21,000/- with interest for balance payment for work completed on 22.5.1990.

Previous Decisions

Trial court decreed the suit in favor of respondent with interest at 15% per annum and costs.

Issues

Whether the suit for recovery of balance payment for work done is barred by limitation under Article 18 of the Limitation Act, 1963.

Submissions/Arguments

Appellant argued that the work was completed on 22.5.1990, and under Article 18 of the Limitation Act, the three-year period begins from the date of completion, making the suit filed in 1993 time-barred.

Ratio Decidendi

Under Article 18 of the Limitation Act, 1963, the period of limitation for a suit for the price of work done runs from the date when the work is done, not from the date of demand or refusal. Since the work was completed on 22.5.1990 and the suit was filed in 1993, it is within the three-year period.

Judgment Excerpts

Under Article 18 of the Limitation Act, 1963, period prescribed is three years for filing suit. The period begins when the work is done.

Procedural History

Respondent filed Special Civil Suit No.39 of 1993 before Civil Judge, Senior Division, Raigad at Alibag for recovery of balance payment. Trial court decreed the suit. Appellant filed First Appeal No.998 of 1994 before Bombay High Court.

Acts & Sections

  • Limitation Act, 1963: Article 18
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court at Goa Quashes Deposit Order in Appeal Under Order 41 Rule 1(3) CPC — No Stay Application Filed by Appellant. Order directing deposit of decreetal amount set aside as condition for stay cannot be imposed without appellant seeking ...
Related Judgement
High Court Bombay High Court Dismisses Municipal Council's Appeal in Contract Recovery Suit — Limitation Period Under Article 18 of Limitation Act Runs from Completion of Work, Not from Demand or Refusal. The court upheld the trial court's decree for balance ...