Case Note & Summary
The petitioner, Maharashtra State Electricity Transmission Co. Ltd., challenged a majority arbitral award dated 6 January 2017 under Section 34 of the Arbitration and Conciliation Act, 1996. The respondent, Kalpataru Power Transmission Ltd., had been awarded contracts for construction of transmission lines under two packages (LL1-A and LL2-A) pursuant to a tender issued on 24 October 2008. Implementation agreements were executed on 27 August 2009, and work orders were issued. Disputes arose regarding delays and escalation costs, leading to arbitration. The majority tribunal allowed part of the respondent's claims, including escalation costs and interest. The petitioner argued that the award was patently illegal and contrary to public policy, particularly regarding the interpretation of contract clauses on escalation and interest. The court, per Justice R.D. Dhanuka, held that the majority award was based on a plausible interpretation of the contract and did not suffer from any patent illegality. The court noted that the tribunal's findings were within its jurisdiction and that the petitioner's challenge was essentially a re-appreciation of evidence, which is not permissible under Section 34. The petition was dismissed, upholding the majority award.
Headnote
A) Arbitration - Section 34 Challenge - Public Policy - Patent Illegality - The court considered whether the majority award granting escalation costs and interest was contrary to public policy or patently illegal under Section 34 of the Arbitration and Conciliation Act, 1996 - Held that the award was based on a plausible interpretation of the contract and did not warrant interference (Paras 1-10). B) Contract Interpretation - Escalation Costs - Delay - The dispute pertained to claims for escalation costs due to delays in execution of transmission line packages - The majority arbitral tribunal allowed the claims, which was upheld by the court as a possible view (Paras 2-8). C) Interest - Award of Interest - The majority award granted interest on the amounts claimed - The court found no error in the award of interest as it was within the tribunal's discretion (Paras 9-10).
Issue of Consideration
Whether the majority arbitral award granting escalation costs and interest to the respondent is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of patent illegality and public policy.
Final Decision
The petition is dismissed. The majority arbitral award dated 6 January 2017 is upheld.
Law Points
- Section 34 of Arbitration and Conciliation Act
- 1996
- Public policy
- Interest on amounts
- Escalation costs
- Interpretation of contract
- Majority award
- Dissenting opinion





