Bombay High Court Dismisses Appeal Against Arbitral Award in Flat Purchase Dispute — Time Was Essence of Contract. Appellant failed to pay balance consideration within stipulated time; arbitrator's award of interest and costs upheld under Section 37 of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: NAGPUR In Favour of Prosecution
  • 116
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, Mr. Nirmal Sureka, entered into two agreements on 26.11.1999 with respondent nos. 1 and 2 (Alankar Real Estate Pvt. Ltd. and Hotel Amarjeet Pvt. Ltd.) to purchase two flats for a total consideration of Rs. 25,00,000/- (Rs. 18,00,000/- for the flat and Rs. 7,00,000/- for undivided share). The agreements stipulated that time was the essence of the contract and that the balance amount of Rs. 10,00,000/- (Rs. 3,00,000/- + Rs. 7,00,000/-) was to be paid by 26.01.2000, failing which interest at 24% per annum would be payable. The appellant paid only Rs. 15,00,000/- initially and failed to pay the balance. Disputes arose, and the matter was referred to arbitration. The sole arbitrator, Mr. Avinash Gupta, passed an award directing the appellant to pay the balance consideration with interest and costs. The appellant challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, before the District Judge, who dismissed the application on 25.06.2008. The appellant then filed the present appeal under Section 37. The High Court held that the arbitrator's findings were based on evidence and were not perverse. The court noted that the appellant had admitted to not paying the balance amount and that the arbitrator had correctly applied the contractual terms. The court also upheld the award of interest at 24% per annum and costs, finding no ground to interfere. The appeal was dismissed.

Headnote

A) Arbitration Law - Appeal under Section 37 - Scope of Interference - Section 37 of Arbitration and Conciliation Act, 1996 - The court held that the scope of interference in an appeal under Section 37 is limited and the findings of fact by the arbitrator cannot be reappreciated unless perverse or contrary to record. (Paras 10-12)

B) Contract Law - Time is Essence of Contract - Flat Purchase Agreement - The agreement between the parties expressly stipulated that time was the essence of the contract. The appellant failed to pay the balance consideration within the stipulated time, and the arbitrator's finding that the appellant was in breach was upheld. (Paras 4-6)

C) Arbitration Law - Interest and Costs - Section 31(7) of Arbitration and Conciliation Act, 1996 - The arbitrator awarded interest at 24% per annum on delayed payments and costs of arbitration. The court held that such award was within the arbitrator's discretion and not liable to be interfered with. (Paras 7-9)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the judgment of the District Judge dismissing the application under Section 34 of the Arbitration and Conciliation Act, 1996, was liable to be set aside.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is dismissed. The judgment of the District Judge dated 25.06.2008 in Miscellaneous Civil Application No. 03/2006 is confirmed.

Law Points

  • Time is essence of contract
  • Arbitral award not to be interfered with under Section 34 unless perverse
  • Interest on delayed payment
  • Costs of arbitration
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (BOM) (09) 168

Arbitration Appeal No. 5 of 2008

2019-09-30

A.S. Chandurkar

Shri S.C. Mehadia for appellant; Shri S.P. Dharmadhikari, Senior Advocate with Shri Shyam Dewani for respondent nos. 1 and 2

Mr. Nirmal s/o Kishanlal Sureka

Alankar Real Estate (Pvt) Ltd., Hotel Amarjeet (Pvt) Ltd., Mr. Avinash Gupta

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37 of the Arbitration and Conciliation Act, 1996 against dismissal of application under Section 34 challenging arbitral award.

Remedy Sought

Appellant sought to set aside the judgment of the District Judge dismissing his application under Section 34 and to set aside the arbitral award.

Filing Reason

Appellant failed to pay balance consideration for flats; arbitrator awarded payment with interest and costs; appellant challenged award.

Previous Decisions

District Judge dismissed Miscellaneous Civil Application No. 03/2006 on 25.06.2008, upholding the arbitral award.

Issues

Whether the District Judge erred in dismissing the application under Section 34 of the Arbitration and Conciliation Act, 1996? Whether the arbitral award was perverse or contrary to the terms of the contract?

Submissions/Arguments

Appellant argued that the arbitrator ignored the terms of the agreement and that time was not the essence of the contract. Respondents argued that the appellant admitted to not paying the balance and that the arbitrator's findings were based on evidence.

Ratio Decidendi

The scope of interference under Section 37 is limited; findings of fact by the arbitrator cannot be reappreciated unless perverse. The arbitrator's award was based on the contractual terms and evidence, and no ground for interference was made out.

Judgment Excerpts

This appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 takes exception to the judgment dated 25.06.2008 in Miscellaneous Civil Application No.03/2006 by which the application preferred by the appellant under Section 34 of the said Act has been dismissed. The facts giving rise to the present proceedings are that on 26.11.1999 the appellant and the respondent nos. 1 and 2 entered into two agreements by which the appellant agreed to purchase two flats from the respondent nos. 1 and 2.

Procedural History

On 26.11.1999, agreements executed. Disputes arose; matter referred to arbitration. Sole arbitrator passed award. Appellant filed application under Section 34 before District Judge, which was dismissed on 25.06.2008. Appellant filed appeal under Section 37 on 25.07.2008. High Court heard arguments on 21.08.2019 and pronounced judgment on 30.09.2019.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 37, Section 31(7)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Appeal Against Setting Aside of Arbitral Award in Construction Contract Dispute. The court restored the arbitral award holding that the Single Judge exceeded jurisdiction under Section 34 of the Arbitration and Conciliation A...
Related Judgement
High Court Karnataka High Court Acquits Police Officers in Corruption Case Due to Unreliable Trap Witness and Lack of Corroboration. Conviction under Sections 7, 13(1)(d) and 13(2) of Prevention of Corruption Act, 1988 set aside as sole trap witness was interes...