Bombay High Court Dismisses Petition Challenging Arbitral Award in Commercial Dispute. Appointment of Arbitrator by Advocate on Behalf of Party Held Valid Under Section 34 of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 9
Judgement Image
Font size:
Print

Case Note & Summary

The petitioners, Cabcom Cables Limited and others, filed a petition under section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 14th January 2019 passed by a sole arbitrator. The award allowed the claims of the respondent, SBI Global Factors Limited, in a commercial dispute arising from an agreement between the parties. The petitioners argued that the appointment of the arbitrator was invalid because it was made by the respondent's advocate rather than by the respondent itself, relying on clause 23.1 of the agreement which allowed the respondent to appoint a sole arbitrator. They cited the Supreme Court judgment in TRF Ltd. v. Energo Engineering Projects Ltd. to support their contention that such an appointment was impermissible. The respondent contended that the appointment by the advocate was valid as the advocate acted on behalf of the respondent. The court examined the disclosure made by the arbitrator under section 11(8) of the Act and the submissions of both parties. The court held that the appointment by the advocate was valid because the advocate was not ineligible to act as an arbitrator, unlike the situation in TRF Ltd. where the appointing authority was itself ineligible. The court found no merit in the petition and dismissed it, upholding the arbitral award.

Headnote

A) Arbitration - Appointment of Arbitrator - Validity of Appointment by Advocate - Section 34, Arbitration and Conciliation Act, 1996 - The petitioners challenged the arbitral award on the ground that the arbitrator was appointed by the respondent's advocate and not by the respondent itself. The court held that the appointment by the advocate on behalf of the respondent is valid as the advocate acts as an agent of the party. The court distinguished the judgment in TRF Ltd. v. Energo Engineering Projects Ltd., noting that in that case the appointment was by a person who was ineligible, whereas here the advocate was not ineligible. The petition was dismissed. (Paras 1-5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the appointment of the sole arbitrator by an advocate on behalf of the respondent (original claimant) under clause 23.1 of the agreement is valid and whether the arbitral award is liable to be set aside under section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court dismissed the petition, holding that the appointment of the arbitrator by the respondent's advocate was valid and the arbitral award was not liable to be set aside.

Law Points

  • Arbitration
  • Appointment of Arbitrator
  • Section 34
  • Section 11(8)
  • TRF Ltd. v. Energo Engineering Projects Ltd.
  • Unilateral Appointment
  • Advocate Appointment
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (BOM) (09) 68

Commercial Arbitration Petition No.814 of 2019

2019-09-25

R.D. Dhanuka, J.

Mr.Varun Ahuja with Ms.Dipti Shah for the Petitioners, Mr.Ashish Mehta with Mr.Narpat Singh i/b M/s.Ethos Legal Alliance for the Respondent

Cabcom Cables Limited, Mr.Sandeep Sehgal, Ms.Poonam Sehgal, Ms.Janak Sehgal

SBI Global Factors Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

Setting aside of the arbitral award dated 14th January 2019.

Filing Reason

The petitioners alleged that the appointment of the sole arbitrator by the respondent's advocate was invalid.

Previous Decisions

Arbitral award dated 14th January 2019 passed by the learned arbitrator allowing the claims of the respondent.

Issues

Whether the appointment of the sole arbitrator by the respondent's advocate is valid under the agreement and the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Petitioners: The arbitrator was appointed by the respondent's advocate, not by the respondent itself, which is invalid under clause 23.1 of the agreement and the judgment in TRF Ltd. v. Energo Engineering Projects Ltd. Respondent: The appointment by the advocate is valid as the advocate acts as an agent of the respondent.

Ratio Decidendi

The appointment of an arbitrator by an advocate on behalf of a party is valid as the advocate acts as an agent. The judgment in TRF Ltd. v. Energo Engineering Projects Ltd. is distinguishable because in that case the appointing authority was itself ineligible, whereas here the advocate was not ineligible.

Judgment Excerpts

By this petition filed under section 34 of the Arbitration & Conciliation Act, 1996, the petitioners have impugned the arbitral award dated 14th January, 2019 passed by the learned arbitrator allowing the claims made by the respondent (original claimant). In support of the submission that the respondent itself could not have appointed the learned arbitrator and in any event through the advocate, the respondent placed reliance on the judgment of the Supreme Court in case of TRF Ltd. vs. Energo Engineering Projects Ltd.

Procedural History

The petitioners filed Commercial Arbitration Petition No.814 of 2019 under section 34 of the Arbitration and Conciliation Act, 1996 challenging the arbitral award dated 14th January 2019. The petition was heard by the High Court of Judicature at Bombay and dismissed on 25th September 2019.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 11(8)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging Arbitral Award in Commercial Dispute. Appointment of Arbitrator by Advocate on Behalf of Party Held Valid Under Section 34 of Arbitration and Conciliation Act, 1996.
Related Judgement
High Court High Court of Karnataka Dismisses Writ Appeal Challenging Single Judge Order on Maintainability of Applications Filed by New Advocate Without No Objection from Previous Advocate. The court held that termination of a General Power of Attorney does not...