Case Note & Summary
The Petitioner, National Iranian Tanker Company, filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging a majority arbitral award dated February 5, 2018. The dispute arose from a charter party agreement with the Respondent, Bharat Petroleum Corporation Ltd., for the carriage of crude oil. The Petitioner claimed demurrage and detention charges for delays at the discharge port. The Arbitral Tribunal, by a majority, rejected the claim on the ground that it was barred by limitation under Article 55 of the Limitation Act, 1963, as the cause of action arose on the date of completion of discharge (July 31, 2012) and the claim was filed beyond the three-year period. One arbitrator dissented. The Petitioner argued that the cause of action arose only upon demand or refusal, and that the limitation period should run from the date of the invoice or subsequent correspondence. The Respondent contended that the claim was clearly time-barred and the award was not patently illegal. The court analyzed the legal position regarding limitation for demurrage claims, noting that the cause of action accrues on the date of completion of discharge when the obligation to pay arises. The court found that the majority award's view was plausible and not perverse, and that the dissenting opinion did not render the award liable to be set aside. The court held that the petition lacked merit and dismissed it, upholding the award.
Headnote
A) Limitation Act - Demurrage Claim - Article 55 - Cause of Action - The claim for demurrage and detention charges arises on the date of completion of discharge, not on the date of subsequent demand or invoice. The court held that the Arbitral Tribunal correctly applied Article 55 of the Limitation Act, 1963, and the petition under Section 34 of the Arbitration and Conciliation Act, 1996 was dismissed as the award was not patently illegal or against public policy (Paras 1-15). B) Arbitration Act - Section 34 - Challenge to Award - Public Policy - A challenge to an arbitral award on the ground of limitation being a mixed question of law and fact, the court's interference under Section 34 is limited to cases where the view taken by the tribunal is impossible or perverse. The court held that the majority award's finding on limitation was plausible and not open to challenge (Paras 10-15).
Issue of Consideration
Whether the claim for demurrage and detention charges was barred by limitation, and whether the Arbitral Tribunal's decision to reject the claim on limitation grounds is patently illegal or against public policy under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The petition is dismissed. The majority arbitral award dated February 5, 2018 is upheld.
Law Points
- Limitation period for demurrage claim starts from date of discharge
- not from date of demand
- Article 55 Limitation Act
- 1963
- Section 34 Arbitration and Conciliation Act
- 1996
- Public policy challenge under Section 34
- Majority award binding
- Dissenting opinion not binding





