Bombay High Court Dismisses Petition to Restrain Bank Guarantees in Construction Contract Dispute. Court holds that invocation of bank guarantees cannot be injuncted except in cases of fraud or irretrievable injustice, and no such case was made out.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 47
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Ahluwalia Contracts (India) Ltd., filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim relief to restrain the respondents from invoking and receiving payment under performance and advance bank guarantees issued by respondent banks (Bank of Maharashtra and Yes Bank) in favor of respondent no.1, Reliance Infrastructure Ltd. The petitioner had been awarded a contract for construction work at Sasan, MP, and had furnished the bank guarantees as part of the contract. Disputes arose between the parties regarding the contract, and the petitioner apprehended that respondent no.1 would invoke the bank guarantees. The court examined the settled legal position that a bank guarantee is an independent contract between the bank and the beneficiary, and the court will not interfere with its invocation except in cases of fraud or irretrievable injustice. The petitioner failed to establish either exception. The court noted that mere disputes under the main contract do not constitute fraud, and no irretrievable injustice was demonstrated. Accordingly, the petition was dismissed, and the interim order granted earlier was vacated.

Headnote

A) Arbitration - Interim Relief - Bank Guarantee - Section 9 of the Arbitration and Conciliation Act, 1996 - Injunction against invocation of bank guarantee - The petitioner sought to restrain the respondent from invoking performance and advance bank guarantees. The court held that a bank guarantee is an independent contract between the bank and the beneficiary, and the court will not interfere except in cases of fraud or irretrievable injustice. No such case was made out. (Paras 1-10)

B) Contract Law - Bank Guarantee - Fraud Exception - Irretrievable Injustice - The court reiterated the settled principle that an injunction against invocation of a bank guarantee can only be granted if there is a clear case of fraud or irretrievable injustice. The petitioner's allegations of disputes under the main contract were insufficient to restrain the bank guarantees. (Paras 5-10)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the court can restrain the invocation and payment of bank guarantees under Section 9 of the Arbitration and Conciliation Act, 1996, in the absence of fraud or irretrievable injustice.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Petition dismissed. Interim order dated 25 March 2019 vacated.

Law Points

  • Bank guarantee is an independent contract
  • fraud exception
  • irretrievable injustice exception
  • Section 9 of Arbitration and Conciliation Act
  • 1996
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (BOM) (04) 87

Commercial Arbitration Petition (Lodg) No. 145 of 2019

2019-04-02

G.S. Kulkarni

Mr. Zal Andhyarujina with Mayur Khandeparkar, Dhiraj Mhetre, Ms. Smiti Tewari & Ms. Sonal Alagh, Parth Dua I/b. Khaitan Legal Associates, for the Petitioner. Mr. S.U. Kamdar, Senior Advocate with Sarosh Bharucha, Chirag Kamdar, with Karan Bhosale, Shrey Fattarpekar, Kiran Padalkar, Ms. Ishita Bajaj I/b. India Law Alliance, for Respondent no.1.

Ahluwalia Contracts (India) Ltd.

Reliance Infrastructure Limited, Bank of Maharashtra, Yes Bank Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim relief to restrain invocation of bank guarantees.

Remedy Sought

Restraining respondent banks from making payment under bank guarantees, restraining respondent no.1 from receiving payment, and directing deposit of amounts in court.

Filing Reason

Apprehension that respondent no.1 would invoke bank guarantees due to disputes under the construction contract.

Issues

Whether the court can restrain invocation of bank guarantees under Section 9 of the Arbitration and Conciliation Act, 1996 in the absence of fraud or irretrievable injustice.

Submissions/Arguments

Petitioner argued that disputes under the main contract justified restraint on bank guarantees. Respondent no.1 argued that bank guarantees are independent contracts and no fraud or irretrievable injustice was shown.

Ratio Decidendi

A bank guarantee is an independent contract between the bank and the beneficiary. The court will not interfere with its invocation except in cases of fraud or irretrievable injustice. Mere disputes under the main contract do not constitute fraud or irretrievable injustice.

Judgment Excerpts

This is a petition under Section 9 of the Arbitration and Conciliation Act (for short 'the Act') whereby the petitioner prays for the following interim reliefs pending the arbitral proceedings: The case of the petitioner is that the petitioner is involved interalia in the business of civil construction.

Procedural History

Petition filed under Section 9 of the Arbitration and Conciliation Act, 1996. Interim order granted on 25 March 2019. Final hearing on 25 March 2019. Judgment pronounced on 2 April 2019.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Petition to Restrain Bank Guarantees in Construction Contract Dispute. Court holds that invocation of bank guarantees cannot be injuncted except in cases of fraud or irretrievable injustice, and no such case was made out.
Related Judgement
High Court Gujarat High Court Allows Appeal and Remands Motor Accident Claim for Fresh Compensation Assessment — Tribunal's Lump-Sum Award of Rs.40,000 Set Aside for Lack of Proper Head-wise Assessment. The Court Held That Compensation for Grievous Injuries M...