Case Note & Summary
The petitioner, Mahaguj Collieries Limited, filed two arbitration petitions under Section 37 of the Arbitration and Conciliation Act, 1996, challenging an interim order dated 19th March 2018 passed by the Arbitral Tribunal. The Tribunal had rejected the petitioner's application for vacation of interim relief and partially granted the respondent's (Adani Enterprises Limited) application for interim relief, restraining the petitioner from enforcing a demand notice dated 9th November 2017 during the pendency of the arbitration. The dispute arose out of a contract between the parties, and the respondent had invoked a bank guarantee. The petitioner argued that the Tribunal's order was perverse and contrary to law, while the respondent contended that the order was just and proper. The court, after hearing the parties, held that the scope of interference under Section 37 is limited and that the Tribunal's order was based on a prima facie view and was not perverse. The court dismissed the petitions, upholding the Tribunal's order but modifying it to the extent that the amount deposited by the respondent would be kept in a fixed deposit and the restraint on the petitioner from enforcing the demand notice would continue until the disposal of the arbitration.
Headnote
A) Arbitration Law - Interim Measures - Section 9, Arbitration and Conciliation Act, 1996 - Bank Guarantee - The court examined the validity of an interim order passed by the Arbitral Tribunal restraining the respondent from enforcing a demand notice and directing the claimant to deposit the amount of the bank guarantee in a fixed deposit. The court held that the Tribunal's order was based on a prima facie view and was not perverse or contrary to law, and therefore, no interference was warranted under Section 37 of the Act. (Paras 1-10) B) Arbitration Law - Appeal against Interim Order - Section 37, Arbitration and Conciliation Act, 1996 - Scope of Interference - The court reiterated that the scope of interference under Section 37 is limited to cases where the order is perverse, contrary to law, or based on no evidence. The court found that the Tribunal had considered the relevant factors and its decision was plausible, hence the appeal was dismissed. (Paras 11-20)
Issue of Consideration
Whether the impugned order of the Arbitral Tribunal granting partial interim relief to the claimant and rejecting the respondent's application for vacation of interim relief is liable to be set aside under Section 37 of the Arbitration and Conciliation Act, 1996.
Final Decision
The court dismissed both arbitration petitions, upholding the impugned order of the Arbitral Tribunal dated 19th March 2018, with a modification that the amount deposited by the respondent shall be kept in a fixed deposit and the restraint on the petitioner from enforcing the demand notice shall continue until the disposal of the arbitration.
Law Points
- Section 37 of the Arbitration and Conciliation Act
- 1996
- Interim measures under Section 9
- Bank guarantee encashment
- Prima facie case
- Balance of convenience
- Irreparable injury
- Perversity in arbitral award
- Limited scope of appeal under Section 37




