Case Note & Summary
The case involves a challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996. The petitioner, Khurana Constructions, was a subcontractor for civil and underground piping work at Indian Oil Corporation Ltd.'s (IOCL) Gujarat Refinery. The work was awarded by IOCL to IOT Infrastructure and Energy Services Ltd. (IOT), which then subcontracted it to Khurana via a Letter of Intent (LOI), a formal agreement dated 28 February 2005, and special conditions of work. Disputes arose, and Khurana filed claims before an arbitral tribunal. The main controversy was whether the General Conditions of Contract (GCC) from the main contract between IOCL and IOT formed part of the subcontract. IOT argued that GCC was incorporated by reference, and Clause 6.6.1.0 required notification of claims as a condition precedent to arbitration. The arbitrator accepted this, holding that Claim Nos. 3 to 10 were not notified and thus not arbitrable, and rejected them. Khurana challenged this in the High Court. The court examined the subcontract documents and found no explicit reference incorporating the GCC. The LOI, formal agreement, and special conditions did not mention the GCC. The court held that for incorporation by reference, the reference must be clear and explicit, and the parties must have intended to incorporate the document. Since the GCC was not part of the subcontract, the notification requirement did not apply. The court further held that even if the GCC were incorporated, the notification clause could not bar arbitration of claims not notified, as the arbitration clause (Clause 9.0.1.0) only referred to disputes arising out of notified claims, but the claims themselves were disputes. The court found the award patently illegal and set it aside, remanding the matter to the arbitrator for fresh consideration of Claim Nos. 3 to 10 on merits.
Headnote
A) Arbitration Law - Incorporation of Contract Terms by Reference - General Conditions of Contract - For a document to be incorporated by reference into a contract, the reference must be clear and explicit, and the parties must have intended to incorporate it. In the absence of such clear incorporation, a party cannot be bound by terms not forming part of the contract. (Paras 6-10) B) Arbitration Law - Pre-Arbitral Notification Requirement - Arbitrability of Claims - A clause requiring notification of claims as a condition precedent to arbitration must be expressly agreed upon. If the clause is not part of the subcontract, claims cannot be rejected as non-arbitrable for want of notification. (Paras 11-13) C) Arbitration Law - Challenge to Arbitral Award - Section 34 of the Arbitration and Conciliation Act, 1996 - Patent Illegality - An award that rejects claims on the ground of non-arbitrability based on a clause not forming part of the contract suffers from patent illegality and is liable to be set aside. (Paras 14-16)
Issue of Consideration
Whether the general conditions of contract (GCC) from the main contract between IOCL and IOT formed an integral part of the subcontract between Khurana and IOT, and consequently, whether the requirement of prior notification under Clause 6.6.1.0 of GCC applied to Khurana's claims, rendering Claim Nos. 3 to 10 non-arbitrable.
Final Decision
The court allowed the petition, set aside the arbitral award to the extent it rejected Claim Nos. 3 to 10 as non-arbitrable, and remanded the matter to the arbitrator for fresh consideration of those claims on merits.
Law Points
- Incorporation of general conditions of contract by reference must be explicit and clear
- Pre-arbitral notification requirement cannot be implied
- Arbitrability of claims cannot be defeated by non-existent contractual bar
- Section 34 of Arbitration and Conciliation Act
- 1996
- Patent illegality





