Bombay High Court Hears Section 37 Petition Against Arbitral Tribunal’s Order Permitting Premises Inspection in a Specific Performance Dispute. The Arbitral Tribunal’s Direction Under Section 17 Was Challenged as Beyond Scope and Unnecessary, Raising Questions on Interim Measures for Evidence Gathering Under the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 6
Judgement Image
Font size:
Print

Case Note & Summary

The case involved two arbitration petitions filed by Raymond Limited under Section 37 of the Arbitration and Conciliation Act, 1996, challenging a common order of the Arbitral Tribunal dated 3 December 2018. The Arbitral Tribunal, in an arbitration initiated by the claimants (Akshaypat Singhania in one petition and Veenadevi Singhania and others in the other) against Raymond Limited for specific performance of a tripartite agreement relating to a duplex residential premises in JK House, Mumbai, had directed Raymond Limited to permit the claimants’ architect and valuer to inspect the newly redeveloped building. The impugned order required inspection within ten days. Raymond Limited contested the order on multiple grounds. It argued that the direction fell outside the scope of Section 17, which only allows interim measures for protection and preservation, not gathering of evidence. The company further contended that inspection was unnecessary because the claimant was already aware of the alleged shortfall in carpet area, and valuation could be done using comparable sale instances without physical access. Alleging an ulterior motive, the petitioner pointed to a subsequent letter from the claimants’ advocates requesting lengthy inspection periods, suggesting the real intent was to harass and gain unauthorized entry into the premises. The petitioner also faulted the Arbitral Tribunal for providing inadequate reasoning. The respondents’ arguments were partially recorded but the provided judgment excerpt did not include a detailed rebuttal. The Bombay High Court heard the matter and reserved or delivered an oral judgment, the complete text of which was not contained in the available excerpt; therefore, the court’s final analysis, ratio, and operative order remain unknown from the supplied material.

Issue of Consideration

Whether the Arbitral Tribunal’s direction permitting the claimant’s Architect and Valuer to inspect the suit premises falls within the scope of Section 17 of the Arbitration and Conciliation Act, 1996, and whether such direction is justified on merits.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Scope of Section 17 of the Arbitration and Conciliation Act
  • 1996
  • interim measures for protection versus evidence gathering
  • necessity of inspection for valuation
  • ulterior motive in seeking inspection
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (BOM) (02) 41

Arbitration Petition No. 35 of 2019 and Arbitration Petition No. 36 of 2019

2019-02-08

B. P. Colabawalla, J.

2019:BHC-OS:4392

Janak Dwarkadas, Senior Advocate a/w Gaurang Joshi, Chirag Ramdev, Dhawal Mehta, Suraj Juneja, Kaidokht Vasania, Shachi Udeshi, Aryan Srivastava i/by Wadia Ghandy & Co. for petitioner in ARBP/35/2019; Pravin Samdani, Senior Advocate a/w Chirag Kamdar, Dhawal Mehta, Suraj Juneja, Kaidokht Vasania, Sachi Udeshi, Aryan Srivastava i/by Wadia Ghandy & Co. for petitioner in ARBP/36/2019; Dr. Birendra Saraf, Advocate a/w Naushad Engineer, Rohan Dakshini, Namrata M. Shah, Aakanksha Saxena, Bhavin Shah i/by Rashmikant and Partners for respondents

Raymond Limited

Akshaypat Singhania & Anr (in ARBP 35/2019); Veenadevi Singhania & Ors (in ARBP 36/2019)

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Arbitration Petition under Section 37 of the Arbitration and Conciliation Act, 1996 challenging an arbitral tribunal’s order permitting inspection of suit premises.

Remedy Sought

Petitioner (Raymond Limited) sought to set aside the Arbitral Tribunal’s order dated 3 December 2018 that directed inspection of the newly reconstructed JK House building by the claimant’s architect and valuer.

Filing Reason

Petitioner contended that the arbitral tribunal’s direction was beyond the scope of Section 17, unnecessary, and made for ulterior motives.

Previous Decisions

The Arbitral Tribunal had passed an order on 3 December 2018 directing the petitioner to permit inspection by the claimant’s architect and valuer within ten days.

Issues

Whether the Arbitral Tribunal’s order directing inspection of the suit premises falls within the scope of Section 17 of the Arbitration and Conciliation Act, 1996. Whether the inspection was necessary given the claimant’s existing knowledge of the alleged shortfall and availability of valuation methods. Whether the application for inspection was made with ulterior motives.

Submissions/Arguments

Petitioner argued that the impugned order was beyond the scope of Section 17 as it was not an interim measure of protection but a direction to gather evidence. Petitioner contended that inspection was unnecessary because the claimant already knew the alleged shortfall in area and valuation could be done through comparable sale instances. Petitioner alleged that the application was moved with an ulterior motive to harass and gain unauthorized access, as evidenced by a subsequent letter requesting extensive inspection time. Petitioner submitted that the Arbitral Tribunal’s reasoning was inadequate to support such drastic directions. Co-petitioner adopted the above arguments and added that since the claim included an alternative prayer for quantified compensation, there was no need for site inspection.

Judgment Excerpts

The Arbitral Tribunal, vide the impugned order, directed respondent No.1 to permit the claimants' Architect and Valuer along with the claimants and/ or his/her representative and their Advocate in the presence of respondent No.1’s representative and their Advocate, to visit and take inspection of the site in which the suit premises are situated as per the mutual convenience of both parties. (Para 2) the Section 17 application, as filed, was not for the purposes of securing protection or preservation of the suit premises but was in the nature of gathering evidence and therefore beyond the purview of Section 17 of the Act. (Para 9) The directions regarding inspection were wholly unnecessary in view of the fact that the claimant was fully aware about the alleged shortfall, if any in the area of the suit premises. (Para 10)

Procedural History

Claimant filed a claim for specific performance of a tripartite agreement and alternatively compensation. During arbitral proceedings, claimant sought inspection of the redeveloped JK House building. Respondent No.1 refused, leading claimant to file an application under Section 17 for directions. The Arbitral Tribunal allowed the application on 3 December 2018, directing inspection within ten days. Aggrieved, Raymond Limited filed the present arbitration petition under Section 37 challenging that order.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 17, Section 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Hears Section 37 Petition Against Arbitral Tribunal’s Order Permitting Premises Inspection in a Specific Performance Dispute. The Arbitral Tribunal’s Direction Under Section 17 Was Challenged as Beyond Scope and Unnecessary, Rai...
Related Judgement
High Court High Court Dismisses Railways' Appeal Against Compensation for Shortage of Boiler Spares; Joint Shortage Certificate Held Binding on Railways Under Principle of Estoppel by Deed. Open Delivery Was Demanded Before Unloading and Shortage Certificate Jo...